What changed since the last update — built 2026-10-16 11:13. Every added or revised row across the page, so you don't have to re-read the tables.
of 257 total
of 211 total
of 200 total
of 453 total
of 103 total
What the refresh did (refresh_log_20261016.md)
- Phase A: searches (FERC large load/co-location, PJM RBP/connect-and-manage, state moratoria, large-load tariffs, San Antonio UDC, SEPA DELTa) returned no new verified post-Oct-15 developments. intel.json: +0 items, +0 state_actions, +0 key_dates; as_of -> 2026-10-16, next_refresh -> 2026-10-19.
- Unconfirmed: San Antonio UDC vote outcome (Oct 15); PJM RBP re-timing; SEPA DELTa Q3 release (overdue). Memphis vote Oct 20.
- delta_tariffs.json: no changes.
- Phase A2: dockets 200 tracked (+0 added, +0 updated, +0 closed); limited status checks only.
- Phase A3: skipped (Mon-only).
Previous builds
- 2026-10-15 11:12 as-of 2026-10-15 — 0 changes
- 2026-10-14 11:12 as-of 2026-10-14 — 0 changes
- 2026-10-13 11:12 as-of 2026-10-13 — 0 changes
- 2026-10-12 11:13 as-of 2026-10-12 — 14 changes: +2 items, +2 state actions, key dates +0/~2, dockets +0/~3/-0, moratoria +3/~0/-2
- 2026-10-09 11:13 as-of 2026-10-09 — 8 changes: +1 items, +2 state actions, key dates +1/~2, dockets +0/~2/-0
- 2026-10-08 11:12 as-of 2026-10-08 — 0 changes
- 2026-10-07 11:12 as-of 2026-10-07 — 3 changes: +1 items, +2 state actions
- 2026-10-06 22:10 as-of 2026-10-06 — 14 changes: +3 items, +1 state actions, key dates +2/~3, dockets +2/~1/-2
This week's signal — what moved the needle for distressed-queue + behind-meter strategy. Click any bullet to jump to the section.
- NEW Local: Manatee County, Fla. commissioners unanimously approve one-year data center moratorium
- NEW Local: San Francisco Board of Supervisors and Oakland City Council each approve 45-day data center moratoriums
- NEW Local: Raleigh, N.C. City Council approves six-month data center moratorium (7-1); Memphis, Tenn. vote halted amid disruption and pushed to Oct. 20
- NEW PJM: Local roundup, Oct. 5-6: Anne Arundel County, Md. council approves 15-month data center moratorium; Delphos, Ohio council approves 18-month moratorium
- NEW PJM: Pennsylvania PUC approves Tentative Order on emergency load control: large new loads without secured capacity would be curtailed before other customers
- Federal: The federal data center cost bill hit a wall in the Senate. It got a majority but not the 60 votes needed to start debate, so it is stalled with no scheduled next step. Practically…
- PJM: The PJM backstop capacity auction is on hold. FERC mostly liked it but wants three problems fixed (who pays, what happens when transmission owners exit, and collateral), and the bi…
- New York: Buffalo's council voted for a two-year pause, but it passed a resolution, not a law. The pause needs a local law and the mayor's buy-in to be binding. The council could take up tha…
- ERCOT: The utility serving the Texas Panhandle wants data centers to sign 15-year deals and cover the grid build-out they cause. The PUCT still has to approve it.
- Michigan: Saginaw swapped its pause for permanent rules. Data centers can be built, but only in industrial zones, with a public approval step and strict noise, setback and water reporting.
- ⏰ Coming up (30 days): Oct 16 — Mendocino County, Calif. 45-day data center urgency ordinanc; Oct 16 — Eureka, CA 45-day data center moratorium lapses absent exten; Oct 19 — TCEQ compliance update to Gov. Abbott on the data center per
Key dates ahead — votes, filings, hearings, effective dates. As of 2026-10-16. 58 upcoming · 86 delayed · 67 completed · 67 completed.
Florida SB 484, signed May 7, 2026, takes effect July 1. Prohibits Florida utilities (FPL, Duke Energy Florida, Tampa Electric, Gulf Power) from recovering data center infrastructure costs from residential/small-business ratepayers. Requires large-load tariff structures for ≥50 MW customers.
View context →CHILLS (Conditional High Impact Large Loads Service) provides non-firm 'as available' energy/transmission as a bridge to long-term service for HILLs (≥10 MW at ≤69 kV or >50 MW at >69 kV). FERC approved HILL/HILLGA in January 2026; CHILLS refiled Feb 10 targeting July 1. Mid-April FERC order did not materialize — July 1 may slip. 90-day study + up to 5 years interruptible service. FERC approved June 5, 2026.
View context →Data centers and other large loads ≥75 MW must execute long-term cost-responsibility agreements before receiving grid service. First such state law in the US.
Virginia DEQ must deny any air permit submitted for a data center generator after July 1, 2026 unless equipped with a Tier IV engine or environmental equivalent. Applies to new permits only; existing generators grandfathered. Significant siting cost increase for VA data centers. Part of Governor's signed data center package (April 22, 2026).
View context →Legislature sent S10642/A11560 to Gov. Hochul ~June 5. Under NY law, governor has 10 days (session) or 30 days (adjourned) to sign, veto, or let lapse. If signed, first statewide data center moratorium in US — 1-year hold on ≥20 MW environmental permits. PARTIALLY RESOLVED July 14, 2026: Hochul signed Executive Order 62 (narrower DEC-permit pause, ≥50MW) instead of acting on S10642/A11560 directly — the bill's sign/veto status remains open.
View context →Follows July 1 Metropolitan Development Commission 5-3 vote advancing the proposal; council review/vote timeline not yet set.
All Interconnecting Large Load Entities must submit complete packages to their TSP/DSP by July 10. Only administrative corrections accepted after this date. Note: some early materials cited July 15; ERCOT's June 11 readiness workshop confirmed July 10.
View context →Originally expected by July 10 per pre-decision stakeholder estimates (Jefferies, June 11). PJM's Board did not finalize its position until its July 27, 2026 CIFP decisional letter directing two separate FERC filings (Reliability Backstop Procurement + bilateral facilitation; and IRAS, formerly Connect & Manage). Actual FERC filing date not yet confirmed as of this refresh — watch for filing shortly after July 27.
View context →MISO targeted an initial FERC filing for Attachment GGG (Merchant HVDC interconnection) and MPFCA changes within 30-60 days of the May 12, 2026 stakeholder feedback deadline. The 60-day outer window falls around July 12, 2026.
View context →The 2028/29 BRA results will set the capacity shortfall that the Reliability Backstop Procurement must cover. EDC input on potential reduction to procurement targets will also be incorporated before the Sept 10 bid solicitation window opens.
View context →Developers must submit full project information by July 15, 2026 to enter Batch Zero. Results delivered Jan 29, 2027; IA execution deadline Mar 1, 2027. Financial security: $50k/MW (refundability governed by PUC Rule 25.194, expected Aug/Sep 2026); plus separate $50k non-refundable direct interconnect fee.
Council meeting scheduled today to decide whether to extend the city's temporary data center moratorium or move to a permanent ban.
All six RTOs/ISOs and their transmission owners must file informational reports on generation adequacy for existing and new large loads within 30 days of the June 18 Section 206 show cause order.
View context →All six RTOs/ISOs must file generation adequacy informational reports by July 20 (30 days from June 18 show cause orders). Note: Baker Botts confirms July 20; earlier estimates cited July 18.
Each RTO/ISO must report how it will ensure adequate generation for existing and new large loads, per FERC's June 18 Section 206 show-cause orders.
FERC technical conference on long-term approaches to reforming PJM's market structure and stakeholder process. Watch for insight into how FERC views PJM's C&M and backstop frameworks, and any signals on permanent market design changes.
View context →After reviewing ILLE submissions (received by July 10), Transmission Service Providers and Distribution Service Providers must finalize and submit complete Batch Zero eligibility packages to ERCOT by July 24.
View context →Regular open meeting — check published agenda for large-load/Project 58481/59142 items.
Regular open meeting — check published agenda for large-load/Project 58481/59142 items.
Bilateral contracting process (RFP launched June 9, 2026) between buyers and sellers of new supply is expected to produce initial matches in August 2026, continuing into early 2027. Runs in parallel with the Reliability Backstop Procurement to reduce the ultimate procurement target.
View context →Distinct from the already-effective CHILLS conditional service, SPP's longer-lead cluster-study path for large loads under its Consolidated Planning Process begins this month. Interconnection agreements from this first cluster are expected by spring 2027.
View context →ERCOT will notify all TSPs/DSPs and ILLEs of their Batch Zero inclusion status and any deficiencies by August 7. UPDATE (2026-08-06): Per Gov. Abbott's Aug 3 directive, ERCOT has suspended these Batch Zero classification notifications pending the PUCT/ERCOT audit of all pending projects. ERCOT has now filed (confirmed 2026-08-13, per ERCOT Market Notice M-A080326-01) for a 'good cause' exception at the PUCT's Aug 20, 2026 open meeting. See new key_date 2026-08-20 (PUCT open meeting) for the next concrete checkpoint.
View context →ERCOT classifies each large-load applicant as base load, studied load, or excluded. UPDATE (2026-08-06): Per Gov. Abbott's Aug 3 directive, ERCOT has suspended these Batch Zero classification notifications pending the PUCT/ERCOT audit of all pending projects. ERCOT has now filed (confirmed 2026-08-13, per ERCOT Market Notice M-A080326-01) for a 'good cause' exception at the PUCT's Aug 20, 2026 open meeting. See new key_date 2026-08-20 (PUCT open meeting) for the next concrete checkpoint.
State law requires 45 days' notice to the Department of Land Conservation and Development before a moratorium hearing; staff expected to send this notice by Aug. 10 following the council's Aug. 3 unanimous vote to begin the process.
ERCOT Technical Advisory Committee workshop covering the Independent Market Monitor's State of the Market report and large-load-driven market design questions. Relevant backdrop to the ongoing PUCT 59142 / Batch Zero audit fallout.
View context →30-day delay from the July 14 non-unanimous 5-2 council vote pushes effect to on or about August 13, 2026.
Washington Utilities and Transportation Commission hybrid workshop on large-load interconnection policy for regulated electric utilities, held the same day as the WA UTC's Avista four-year GRC open meeting (UE-260007/UG-260008).
View context →A PUCT open meeting on Aug. 14 (Friday) is separately calendared with large-load/interconnection/market agenda items, ahead of the Aug. 20 open meeting where ERCOT's good-cause exception request on Batch Zero timelines is expected to be addressed. Distinct from the Aug. 20 meeting — confirm agenda posting closer to date.
View context →All six RTOs/ISOs must respond to FERC's Section 206 show cause orders — either justifying existing tariffs as just and reasonable, or filing proposed tariff revisions to address large-load and co-located load interconnection. Non-compliance may trigger FERC-directed tariff changes.
View context →Legislative public hearing scheduled for 4pm, Katie Dorsett Council Chamber, Melvin Municipal Office Building, following the council's 9-0 Aug. 3 vote to reverse its July 21 rejection (5-4) and begin the formal moratorium process.
MISO and its transmission owners must respond to FERC's June 18 show-cause order justifying or revising tariff language on large-load interconnection.
View context →Following its Aug. 5 4-3 vote to proceed toward a moratorium and stricter development-code amendments, the Denton City Council is scheduled to formally set public hearing dates on Aug. 18 (this meeting itself is not a hearing). First public hearing is tentatively planned for Sept. 22, a second for Oct. 27, with possible final adoption Dec. 2; a 90-day moratorium requires a supermajority council vote, and extension to 180 days would need another hearing in March.
View context →Following the City-County Council's 23-1 Aug. 10 passage, the Metropolitan Development Commission could give final approval to the moratorium (through Dec. 31, 2027) as early as this date.
LLWG conference call, 10:00 AM-2:00 PM ET. MISO's Attachment GGG-related large-load tariff package has still not been filed at FERC despite an earlier stakeholder-signalled window of 30-60 days after the May 12, 2026 PAC discussion; the LLWG remains the venue where a filing date would first surface. Separately, MISO's 50 MW large-load framework takes effect Sept. 1.
UPDATED (2026-08-20): Following the PUCT's grant of ERCOT's good-cause exceptions in Project No. 59142, Aug. 31, 2026 is no longer a hard cure deadline for all ILLEs. ERCOT may conditionally classify large loads rather than meet the original Aug. 7 classification deadline, and for any ILLE noticed of deficient dynamic data after Aug. 7 the 24-day cure period runs from the date of actual notification rather than expiring Aug. 31. ILLEs already noticed on or before Aug. 7 remain on the original Aug. 31 cure date. Failure to cure within the applicable window still results in removal from the Batch Zero Interconnection Study. || UPDATED (2026-09-01): The Aug. 31 target date passed with no public confirmation that ERCOT issued conditional Batch Zero classifications. The PUCT good-cause exception in Project No. 59142 permits conditional classification, but Gov. Abbott's Aug. 3 audit directive continues to gate the process — ERCOT has said the verification of Batch Zero large loads and virtual currency mining facilities will take several months and does not report until Dec. 10, 2026. Superseded in practice by the Dec. 10 audit-report date and the Jan. 29, 2027 Batch Zero study-results date.
View context →SUPERSEDED / CORRECTED: this entry previously recorded the Aug. 31 stakeholder target as missed with the filing 'unfiled at FERC.' That was incorrect. MISO filed the Large Load Interconnection Reliability Requirements at FERC on Aug. 28, 2026 (eLibrary accession 20260828-5278), three days AHEAD of the stakeholder target, requesting a Dec. 4 effective date. See the confirmed entry at 2026-08-28 (anchor miso-llirr-ferc-filed-2026-08-28). Retained for audit trail; the operative dates are FERC action on the Dec. 4 requested effective date and the Nov. 16 balance-of-show-cause-response deadline.
Any new single-site load >50 MW behind ≥1 transmission POI in MISO is subject to the new large-load framework. Existing >50 MW loads adding 25+ MW also captured. Framework governs study process, cost allocation, and service options for data centers and industrial loads in MISO territory.
View context →Executive Order 26-17 (signed July 21, 2026) directs the Department of Water, Energy and Environment to establish a data center task force addressing water and natural-resource impacts and county zoning tooling. No statutory deadline is specified in the order; date is indicative of the post-signing implementation window rather than a fixed milestone. Sen. Mike Jacobson has signaled codifying legislation for the 2027 session.
View context →Stakeholder feedback is due to MISO on the new Large Load Project Reviews process. This is the procedural layer sitting on top of MISO's 50 MW large-load framework that became effective Sept. 1, and it shapes how individual large-load projects are screened before study.
View context →DTE requested a decision by Sept. 10, 2026 and the special contracts are conditioned on approval by that date. MPSC regular meeting at 1 p.m. Roughly 1.0 GW of contracted load. Parallel track: AG Nessel's appeal of the December 2025 Saline contract approvals was briefed Aug. 7, 2026. | UPDATE Sept. 11: no Commission order, news release or press confirmation of an outcome in U-22058 had surfaced publicly as of this morning. Recorded as unresolved rather than approved or denied; verify against MPSC E-Dockets before relying on any reported result.
View context →Superseded by PJM Board's July 27, 2026 decisional letter: the confirmed Reliability Backstop Procurement bid/offer window is Sept. 30–Oct. 21, 2026 (not Sept 10–Oct 9 as earlier estimated), with results released in early December (not by Nov 20). See the 2026-09-30 and 2026-12-01 entries below.
View context →Central procurement for the Reliability Backstop Procurement runs Sept. 10 through Nov. 20, 2026, running in parallel with the bilateral matchmaking process (initial matches expected August 2026) to address the ~60 GW capacity shortfall identified in the BRA. SUPERSEDED: PJM's July 31 ER26-3380 filing sets the central bid/offer window opening at Sept. 30, 2026 with results by Dec. 2. See the Sept. 30 entry.
View context →Advanced 6-2 on first reading. Council leadership expressly declined a moratorium. Same-day counterpoint to Charlotte's moratorium-extension vote.
View context →Staff recommended an extension on Sept. 8 alongside data center study findings; the existing 150-day moratorium sunsets Nov. 5. Reported extension length (nine months) is not consistently sourced — treat the term as unconfirmed until the vote.
View context →Follows the city's Sept. 10 determination that a data center is not a permitted use at the former Hynix site under E-1 zoning (appealable to LUBA). Council is separately scheduled to take up data center policy more broadly in December 2026.
View context →Briefs from Duke Energy Florida and intervenors due following the Aug. 25-26 evidentiary hearing. A Commission decision on the 50 MW large-load tariff follows briefing; no decision date has been set.
Revised ordinance clarifies that small accessory server rooms remain permitted, addressing the standard objection that blanket bans inadvertently prohibit ordinary commercial IT infrastructure.
View context →Superseded by PJM Board's July 27, 2026 decisional letter: confirmed bid/offer window is Sept. 30–Oct. 21, 2026 with results in early December, not the Sept 10/Nov 20 estimates carried here previously.
View context →Special education session on PJM's proposed minimum voltage and frequency ride-through requirements for Large Loads, introduced at the Sept. 8 Planning Committee following the July 22 event in which ~4,000 MW of northern Virginia data center load disconnected and transferred to onsite backup generation. Registration via PJM meeting registration.
View context →Next data center-focused Zoning Commission meeting following council's Aug. 25 decision to pursue UDC amendments instead of a moratorium. Draft terms include 500-ft setbacks from residential, hospitals, schools, nursing homes and day cares; industrial/commercial districts only; downtown excluded. Staff indicated further revisions after community feedback.
View context →Deferred from Sept. 8, when the council advanced the ordinance unanimously. Reporting states the formal vote comes 'next week'; Gallatin's next regular council meeting falls Sept. 15, so treat the specific date as scheduled rather than confirmed.
View context →Passed second reading unanimously Sept. 1. Vote scheduled 4:00 p.m. CT. Two companion ordinances (100% renewable phase-in over 10 years; permissive development standards) also on the agenda. SUPERSEDED: the third reading did not occur on Sept. 15. Sponsor JB Smiley pulled the item hours beforehand and moved all data center ordinances to Oct. 6, with amendments narrowing the moratorium toward hyperscale campuses. See the Oct. 6 entry.
Stakeholder feedback is due on MISO's design for reserve products that would credit or compensate large-load curtailment. This is the demand-flexibility counterpart to the interconnection work and is directly relevant to any co-located or curtailable data center configuration in the MISO footprint.
View context →Would impose 200-foot property-line setbacks and separate daytime/nighttime noise limits. An interim ban on new applications is already in force from Sept. 8. Triggered by Nadara's interest in ~800 acres near Gans.
CORRECTION (Sept. 24): no final meeting was held Sept. 23. The DCAC released its Preliminary Learnings and Questions document Sept. 10 and opened a 45-day public comment period, which closes at 5 p.m. Oct. 24, 2026. A public listening session is set for Sept. 26. Final recommendations to Gov. Kotek are expected before year-end, after the November election. See the new Sept. 26 and Oct. 24 DCAC entries. Original: Committee convened by Gov. Kotek since January is expected to deliver a draft report to the Legislature by mid-September ahead of this final public meeting; recommendations will inform a possible 2027 statutory framework. Committee has signaled it will not recommend a statewide moratorium.
View context →PJM expects to present its governance reform package — board independence, expanded state participation, transparency — to the full membership for review and approval at the Sept. 24 Members Committee meeting. Governance sits underneath the board decisions driving the Reliability Backstop Procurement / IRAS filings (ER26-3380) and future large-load design. STATUS Sept. 25 AM: no outcome published on PJM Inside Lines or in the trade press yet, so the vote result is unconfirmed. FERC has said it will impose reforms if PJM does not agree to them by the end of September. Re-check on the next run. UPDATE Sept. 28: The Sept. 24 Members Committee met and elected Janet Dietrich to the Board of Managers (PJM Inside Lines). No governance-package vote outcome has been posted on Inside Lines or in the trade press. FERC's end-of-September deadline stands. Status stays conditional.
View context →This session is dedicated entirely to public comment on the Sept. 10 Preliminary Learnings and Questions document. It is not a decision meeting.
View context →Phase I of PJM's first reformed-process Cycle begins Sept. 28, 2026, thirty days after Phase I base case data posting, per PJM Manual 14H section 2.9 and the PJM Cycle Timeline. PJM cited this date in its Sept. 4 Answer in EL26-101 as the reason it cannot reopen a deficiency review for Oklo's withdrawn 750 MW project. Over 700 projects and more than 200 GW were accepted into Cycle 01 on Aug. 3, 2026. UPDATE Sept. 28: FERC denied Oklo's complaint on Sept. 24, so Phase I proceeds without the Oklo project.
MISO has signalled a Section 205 filing on or about end of September 2026 for a Large Load Parallel Study Process, which would allow MISO to study new large loads and their associated generation concurrently rather than sequentially. Distinct from, and earlier than, the Nov. 16 substantive show-cause response in the EL26-70 abeyance. Date is MISO's own stakeholder estimate, not a docketed deadline.
View context →Confirmed by PJM Board's July 27, 2026 decisional letter: one-time Reliability Backstop Procurement offer window runs Sept. 30–Oct. 21, 2026. Accepted supply offers capped at $555/MW-day; commitments up to 15 years finalized prior to the December 2029/30 Base Residual Auction. UPDATE (Sept. 30, 2026): FERC's Sept. 29 order in ER26-3380 suspended the RBP for five months; PJM says the process will not begin Sept. 30 and new timing is TBD (update expected at Oct. 7 MIC).
View context →DELTa is updated quarterly (Mar/Jun/Sep/Dec). The Q2 release landed mid-June 2026 at 100+ tracked tariffs, up from 77 at the Mar. 31 update. A Q3 release is due by end of September; if it does not appear, the local delta_tariffs.json supplemental records tagged '_source: Edged research' become the primary source of new tariff activity for the quarter.
View context →SB 484 requires each public utility to file a large-load tariff for Commission approval ensuring each large-load customer bears its full cost of service without shifting cost to the general body of ratepayers. Duke Energy Florida filed first (Docket 20260064-EI, hearing Aug. 25-26, briefs Sept. 15); the outcome of that contested case effectively sets the template FPL, TECO and Gulf must file against.
View context →Layers onto a July 2026 resolution barring data centers as principal uses and an August 2026 ban on large-scale facilities. The 10–50 MW band sits below most large-load tariff thresholds and above typical small-facility zoning exemptions. Date reported as tentative.
Approved by the TVA Board Aug. 20, 2026 with the 2026 IRP and FY2027 budget. The CCC recovers incremental capacity cost from data centers rather than the general rate base. The 5 MW threshold is materially lower than the 50 MW definition FERC and most RTOs use. TVA is federally self-regulated, so there is no state commission proceeding and no rehearing or intervenor path — this date is firm, not conditional.
Investor-owned utilities in Washington must submit dedicated large-load tariffs to the UTC by Oct 1, 2026. Consumer-owned utilities must adopt through governing bodies. Tariffs must avoid cost-shifting to other customers.
View context →Directed by a unanimous Sept. 2026 motion of Vice Chair Kimberly Barrow. The Tentative Order would propose updates to the order, criteria and circumstances under which customers may be curtailed during pre-emergency and emergency conditions. If approved, it is released for public comment with a final order targeted for the Jan. 28, 2027 public meeting.
Rescheduled from the Sept. 14, 2026 meeting, where only an informal comment hearing was held. 5:30 p.m., Beaufort County Administration Building, 121 W. Third St., Washington, N.C. No data center is currently planned in the county; the pause is preemptive.
View context →Moved from Sept. 15. Sponsor JB Smiley will amend the moratorium to incorporate other members' proposals and to target hyperscale campuses such as xAI's Colossus I and II. No moratorium is in force in Memphis until this passes. SUPERSEDED: meeting halted Oct. 6 amid disruption; vote moved to Oct. 20 (WSMV). See Oct. 20 entry.
View context →Supervisors adopted a 45-day urgency ordinance 5-0 on Sept. 1, 2026 barring new data centers in the unincorporated county (covering hyperscale, colocation, cloud, AI training and inference, HPC, and blockchain/crypto mining). The board set an Oct. 6 hearing at which it may extend the moratorium for up to two years while permanent regulations are developed; absent extension the ordinance lapses Oct. 16.
Committee step before the Common Council.
PJM said it will update stakeholders on revised Reliability Backstop Procurement timing at the Oct. 7, 2026 MIC meeting following FERC's Sept. 29 order.
View context →The notice of intent was approved Sept. 24. It targets Site Layer 1 LLC's gas-fired project near Hachita/Playas, whose developer signalled an NMED air permit application by Oct. 1.
View context →Replaces the city's data center moratorium.
Approximate expiry of the 45-day temporary moratorium approved Aug. 26, 2026, calculated from the approval date; the city has not published a stated end date. California interim urgency ordinances are commonly extended -- neighboring Coachella and Indio each extended 45-day pauses by roughly 10.5 months. Treat as extendable, not self-terminating.
View context →Unanimously advanced Sept. 15, 2026. Staff findings are not due back until September 2027, so the September 2027 report — not the October adoption — sets the practical duration.
The council held Councilwoman Booker's ordinance for three weeks on Sept. 22 to review amendments. It would not affect Google's existing campus.
View context →Depends on the Oct. 6 committee vote.
Only if first reading passes after the Sept. 29 hearing. Third reading Oct. 27.
View context →WGRZ reports council consideration at the 'next meeting in about two weeks'. The date is approximate and the mayor's position is pending.
Deliverable under Abbott's Sept. 14 directive. Watch for the count of referrals to county/district attorneys and the list transmitted to TCEQ for permit ineligibility — that list is the practical siting constraint.
View context →Second of two tentatively scheduled hearings on the 12-month mid-sized-facility moratorium.
Council vote on Universal Development Code amendments following the Sept. 15 Zoning Commission meeting. Open questions include whether Special Use Authorization (case-by-case council approval for each new data center) and the mayor's proposed noise limits (50 dBA day / 45 dBA night) are included. Existing facilities expected to be grandfathered as non-compliant.
View context →Follows the Zoning Commission's Sept. 15, 2026 data center-focused meeting. Working draft would confine data centers to intense commercial and industrial zones, prohibit development over the Edwards Aquifer Recharge Zone, and require a 500-foot setback from schools, daycares, residential areas and hospitals. Council declined a 90-180 day moratorium on Aug. 25, 2026 and chose the permanent UDC route instead.
View context →Close of the one-time Reliability Backstop Procurement offer window confirmed in the PJM Board of Managers' decisional letter and the ER26-3380 filing: the window runs Sept. 30 through Oct. 21, 2026, with results released in early December (tracked separately at Dec. 1) and commitments of up to 15 years finalized before the December capacity auction for the 2029/2030 Delivery Year. Accepted supply offers are capped at a MW-weighted maximum willingness to pay of $555/MW-day. The procurement targets the 6,831 MW shortfall from the 2028/2029 Delivery Year auction. The Sept. 30 open was already on the calendar; this entry pins the close, which had only been carried in narrative. UPDATE (Sept. 30, 2026): FERC's Sept. 29 order in ER26-3380 suspended the RBP for five months; PJM says the process will not begin Sept. 30 and new timing is TBD (update expected at Oct. 7 MIC).
View context →Superseded by PJM Board's July 27, 2026 decisional letter: results now expected 'early December' following the Sept. 30–Oct. 21 bid window, not 'by Nov 20' as earlier estimated. Commitments up to 15 years will be finalized prior to the December 2029/30 Base Residual Auction.
View context →Confirmed by PJM Board's July 27, 2026 decisional letter. Results finalized prior to the December 2029/30 Base Residual Auction; selected resources (new ICAP/MFO, eligible CIRs, new annual DR/DER) must come online no later than June 1, 2032. UPDATE (Sept. 30, 2026): FERC's Sept. 29 order in ER26-3380 suspended the RBP for five months; PJM says the process will not begin Sept. 30 and new timing is TBD (update expected at Oct. 7 MIC).
View context →The Mendocino County Board of Supervisors' 45-day urgency ordinance, adopted 5-0 on Sept. 1, 2026, runs to approximately Oct. 16 unless extended. Under California Government Code section 65858 it is extendable to a cumulative two years, and every comparable 2026 California urgency ordinance tracked here has been treated as extendable rather than self-terminating — hence conditional.
Approximate expiry of the 45-day urgency ordinance (Bill No. 1061-C.S.) adopted Sept. 1, 2026, calculated from the adoption date; the city has not published a stated end date. California interim urgency ordinances under Government Code section 65858 are routinely extended -- Coachella and Indio each extended 45-day pauses by roughly 10.5 months, and Palm Springs' Aug. 26 pause is on the same track. Treat as extendable, not self-terminating.
View context →This update is required by the governor's Sept. 21 directive letter. TCEQ is to issue no data center permits until the ERCOT/PUCT and TWDB audits are complete.
View context →Moved from Oct. 6 after the meeting was halted amid protests. Scope as amended not described in the source; no moratorium in force until passed.
View context →The 45-day comment window opened Sept. 10 and closes at 5 p.m. Final recommendations to Gov. Kotek are expected by year-end.
View context →Single-source: a reporter's social post quoted in the Strisker 9/29 digest. Verify against the county agenda.
View context →Second of two scheduled public hearings preceding the Dec. 2, 2026 council adoption vote on a Denton data center moratorium and stricter development rules.
Judge Hyde VETOED the ordinance on Sept. 25, 2026. An override needs 9 of 15 votes (the ordinance passed 11-4). Sponsor JP Blackwood says the override will be sought at the next regular Quorum Court meeting; the date is carried from the prior entry and should be confirmed against the Quorum Court calendar.
View context →Adoption confirmed Sept. 15, 2026, so this lapse date is now live rather than conditional. California urgency ordinances may be extended by up to 22 months and 15 days after the initial 45 days — expect an extension hearing before the lapse.
Approximate. Licking County Board of Elections requires special elections to be scheduled 60–120 days after approval; Johnstown council was expected to approve a special-election ordinance on Sept. 10, implying a vote between roughly November 2026 and January 2027. Heath must restart its petition drive after signature shortfalls, so its timeline is later and unset.
View context →Citizen-initiated charter amendment placed on the Nov. 3, 2026 ballot by emergency ordinance Sept. 3 after the Ohio Supreme Court held council must certify it. If approved, prohibits new data centers above 25 MW in city limits at the charter level, which a future council cannot repeal by ordinance. A related annexation dispute remains unresolved.
View context →Election day. Democratic nominee Gina Hinojosa is campaigning on a statewide moratorium on new data center construction pending legislative ratepayer protections; Gov. Abbott is running on the August PUCT/ERCOT comprehensive audit, which continues to gate energization of large computational loads. Texas holds the largest concentration of distressed large-load capacity nationally (~474 GW of screened requests), so the outcome is a genuine two-sided policy catalyst for ERCOT queue assets. Candidate positions are not enacted policy — no bill or docket number attaches.
View context →Adopted unanimously in early June 2026 as a 150-day study pause. If council declines to extend on Sept. 14, new data center applications resume in Charlotte on Nov. 5.
View context →Proposed Sept. 18. It would cover data centers of 20 MW or more or 50,000 sq ft or more, and crypto facilities of 5 MW or more, outside the villages of Potsdam and Norwood.
FERC's June 18, 2026 show-cause order gave RTOs 60 days to respond (Aug. 17) or 45 days to seek a 90-day abeyance (Aug. 3). MISO moved for abeyance on Aug. 3; American Municipal Power filed the only opposition on Aug. 7. If the abeyance is granted, the substantive filing lands on or before roughly Nov. 15-16, 2026. The motion remains undecided as of Aug. 26, so this date is conditional on FERC granting the abeyance.
View context →MISO and its Transmission Owners committed to filing a complete response to FERC's June 18, 2026 Section 206 show-cause order on large load integration by Nov. 16, 2026. With the Aug. 31 stakeholder target for the standalone Large Load Interconnection Reliability Requirements tariff having passed unfiled, this is now the binding federal deadline for MISO's large-load framework.
View context →Pritzker wants bills requiring data centers to pay their energy and water costs, support new renewables, report water use and sign community agreements. A legislative working group is drafting. No bill number yet.
View context →Estimate based on reporting that the ordinance is expected back "within 60 days"; no meeting date set. This is the binding vote.
View context →Council passed the second reading and waived the third on Aug. 24, 2026. The moratorium is dated from July, so it runs through Nov. 23, 2026. Council retains authority for a single 60-day extension if permanent data center zoning rules are not finished, which would push expiry to roughly Jan. 22, 2027.
View context →Hillsboro adopted an emergency 120-day pause on July 28, 2026 covering all new data centers and battery energy storage systems, with permanent limits under consideration. Date is computed from the adoption date and is approximate; the council signalled it would weigh permanent restrictions and review roughly $84M/yr in property tax abatements before expiry.
PJM stated at the Sept. 8, 2026 Planning Committee that it plans to file proposed solutions to FERC in November 2026 responding to the June 18 order in Docket EL26-67-000, which found the PJM Tariff 'does not specify ramp rate or ride-through requirements.' Only the month was stated; the placeholder is set at month-end and should be replaced once a filing date is docketed.
View context →Commissioners indicated on Sept. 15, 2026 that the item could come back in early December once staff completes its study of zoning, electric load, water and noise. Exact date not set.
View context →Scheduled council vote on adopting the Denton data center moratorium following the Sept. 22 and Oct. 27 public hearings. Duration not yet specified in the initiating action.
MISO asked FERC to let its large-load reliability framework (filed Aug. 28, 2026, accession 20260828-5278) take effect Dec. 4, 2026. CONDITIONAL on a FERC order accepting the filing; FERC may accept, accept subject to condition, set for hearing, or reject. If accepted, visibility, PMU, ramp and ride-through obligations begin attaching to MISO transmission customers taking service for large loads, subject to the grandfathering provisions.
ERCOT SVP of Regulatory Policy and General Counsel Chad Seely told the Commission at the Aug. 20, 2026 open meeting that ERCOT's 'goal is to head toward a December 10 filing' of the comprehensive verification and audit report required by Gov. Abbott's Aug. 3 directive, delivered roughly a week ahead of the PUCT's December open meeting. RFIs to provisionally-qualified Batch Zero loads begin late August/early September, with possible additional rounds in October and November. Completion of this audit is the gating item for Batch Zero classification and study activity to resume and for large load energization approvals to be granted.
Mayor Kaarin Knudson confirmed at the packed Sept. 15, 2026 hearing that the former Hynix site E-1 zoning determination stands and does not wait on December. The Dec. 14 session is where the council can update land-use code to regulate data centers city-wide.
The draft falls due during the 120-day moratorium adopted Sept. 22 (which lapses about Jan. 20, 2027 absent extension). The board has said it will consider an extension.
View context →Following the Aug. 27, 2026 initiating resolution, Austin's zoning staff stated they intend to bring proposed data center regulations back to Council in phases, with the first round hoped for by the end of 2026. The full Land Development Code amendment process — which is the only vehicle that can actually prohibit hyperscale facilities under Texas law — may extend into spring 2027. Interim: large-scale data center projects within city limits require Council approval.
View context →The bill passed both houses June 4, 2026 (Senate 44-16, Assembly 102-39) and would impose a one-year permitting moratorium on data centers at a 20 MW threshold — lower than the 50 MW threshold in Executive Order 62, which Hochul issued July 14 in lieu of signing. It also creates a separate utility rate category for data centers plus host-community benefit and renewable requirements. Hochul has until Dec. 31, 2026; inaction is a pocket veto. 60 legislators signed an Aug. 24 letter urging signature.
View context →FERC directed NERC to file one or more new or modified mandatory Reliability Standards governing the integration of computational loads by Dec. 31, 2026. NERC's Project 2026-02 (Computational Load Alignment, Phase 1) closed its initial formal comment period and ballot on Sept. 18, 2026; the SAR proposes Glossary definitions for computational load and computational load entity plus a new standard on near-term large computational load integration.
The Director of the Office of Energy must deliver the plan by Dec. 31, 2026, in consultation with the GOED executive director and each electric utility, identifying the facilities required to serve large load anticipated through 2036 while ensuring no costs are passed to Nevada ratepayers.
View context →Starting 2027, ERCOT's official load forecast only counts large loads with a signed Interconnection Agreement satisfying PUC Project 58481 requirements. Speculative/pre-IA load drops out of forecast. Direct impact: projects without a signed IA by year-end 2026 lose their queue position for forecast purposes.
Under Executive Order 2026-05 (signed Aug. 18, 2026), data center projects above 25 MW seeking expedited DEP review must execute a consent order and agreement committing to supply from new generating resources within the same PJM zone, with a firm clean energy share (solar, advanced nuclear, battery storage) starting at 10% on Jan. 1, rising to 14.5% three years later and 32% by Jan. 1, 2035.
View context →Approximately 120 days from the Sept. 14, 2026 declaration. The city intends to adopt updated zoning, utility and location criteria within the window, so the operative outcome is the replacement ordinance rather than the lapse.
View context →Spanberger said she will work with the General Assembly to write the Framework's standards into statute in the session beginning January 2027. The by-right elimination for projects above 25 MW, the ban on local-government NDAs, and limits on behind-the-meter generation are proposals only and have no legal effect until enacted. House Democratic Caucus signaled support; the Data Center Coalition is withholding position pending detail. Convening date is the customary second-Wednesday-of-January start and should be confirmed against the General Assembly calendar.
View context →EO 22 Sec. I.B.1 requires the Office of the Chief Energy Officer to publish an initial Toolkit within 120 days of the Sept. 18, 2026 effective date — model disclosure templates, community-benefit agreement approaches, and impact-evaluation guidance for local governments. Date is computed from the EO's own 120-day clock.
View context →Adopted Sept. 21, 2026. Council may extend roughly six months after the Data Center Task Force reports in December.
Following the Oct. 1, 2026 Tentative Order and a public comment period, the Commission targets its Jan. 28, 2027 public meeting for a final order. Target date set by the Commission's own September 2026 motion; not a statutory deadline.
PUC anticipates considering a Final Order at its Jan. 28, 2027 public meeting, after 30-day initial and 15-day reply comment periods following Pennsylvania Bulletin publication.
View context →Capacity allocations per year for 2028-2032 delivered to classified applicants.
Under PJM's C&M framework, EDCs/TOs must provide PJM with a list of large loads (≥50 MW) expected to be in service by June 2027. This list gates which loads fall inside vs. outside C&M obligations.
View context →180 days from the Sept. 14, 2026 effective date, absent council extension.
EO 22 Secs. I.C.1–I.C.3 set a 180-day clock from Sept. 18, 2026 for DEQ to deliver to the Governor an accelerated noise-rulemaking timeline and workplan, a cooling water scarcity area rulemaking workplan, and findings on diesel/backup-generation cumulative impacts including Tier II-to-Tier IV retrofit measures. Virginia Energy's methane-reduction recommendations share the same 180-day deadline. Date computed from the EO's own clock.
View context →Adopted unanimously Sept. 21, 2026; council may follow with a limit or ban.
Council's deferred vote on five appeals of the Project Taurus planning approval, set for one week after the April 6, 2027 municipal election. Power and sound studies due in the interim.
EO 22 Sec. I.C.4 requires Virginia Energy to submit findings and recommended best practices on lower-impact, community-aligned siting within 240 days of Sept. 18, 2026 — brownfield and adaptive reuse, edge and distributed models, regional diversification into areas with existing infrastructure capacity, waste-heat and reclaimed-water co-location, and mitigation of transmission impacts on scenic and historic landscapes. Date computed from the EO's own clock.
View context →Miamisburg's nine-month moratorium, adopted 6-0 on Sept. 1, 2026, runs to approximately June 1, 2027. The city intends to adopt zoning rules and development standards before expiry; extension or replacement by permanent standards is the more likely outcome than a clean lapse.
View context →Under PJM's Interim Resource Adequacy Service (IRAS, formerly Connect and Manage), new Large Loads (≥50 MW cumulative at a single site) that do not bring their own new generation by June 1, 2027 and have not otherwise secured supply become subject to curtailment ahead of Pre-Emergency Load Management during capacity shortages, tracked via the new PJM Large Load Registry.
View context →Ayotte announced Sept. 2 she will propose a statewide moratorium of 'a period of years' in her next budget, which cannot take effect before roughly the start of the FY2028 biennium. An executive order could act sooner but none has been issued — as of today there is no enforceable New Hampshire restriction.
View context →One-year moratorium on data centers with peak demand of 20 MW or more, adopted Aug. 3, 2026. The board intends to adopt permanent zoning regulations addressing grid demand within the period. Threshold is deliberately below the 50 MW state EO 62 trigger.
View context →Mattoon's moratorium on data centers above 21,780 sq ft renews annually by default. Unlike a standard lapse-by-default pause, terminating or modifying it requires an affirmative City Council vote, so the base case is continuation into a second year.
View context →Staff recommendations on water, electricity, infrastructure and environmental regulation are due by August 2027, or a status report if regulations are not ready. Absent replacement standards the pause lapses on this date.
View context →City-limits-only pause on new data center and BESS applications adopted 9-0 on Aug. 27, 2026 lapses unless extended or replaced by permanent development standards. Elkhart County unaffected throughout.
View context →EO 22 Sec. I.B.3 directs the Office of the Chief Energy Officer to submit proposed VA-LEAD (Virginia Local Energy and Accountable Data Centers) tiered scoring criteria and an implementation plan by the end of calendar year 2027. Once established, VA-LEAD becomes the baseline by which executive branch agencies align incentives and administrative services, prioritizing developers at the highest tier — a forward gate on state support for Virginia projects.
View context →Extended 7-0 on Sept. 22, 2026 from Jan. 1, 2027.
Adopted unanimously Aug. 27, 2026 with periodic staff progress reports to council. Exempts enterprise/co-located data processing equipment under 1 MW. No applications were pending at adoption, so nothing was grandfathered.
$0.011/kWh consumption tax enacted June 30, 2026 expires unless the General Assembly extends it.
Resources awarded 15-year commitments through the Reliability Backstop Procurement must come online no later than June 1, 2032; developers bear transmission network upgrade costs, expected to be reflected in their offers.
View context →DOE directed FERC to act by April 30. FERC missed that deadline but publicly committed to acting on the broader large-load interconnection docket (covering all RTOs, not just PJM) by June 2026. NARUC objected to federal preemption. See June 15 key date.
View context →Land Use and Sustainability + Parks & City Light committees vote on proposed 365-day moratorium and companion impact study resolution.
Full 9-member City Council expected to vote on 1-year moratorium on new large data center siting. If passed, takes effect immediately and lasts 365 days (extendable 6 months). RESULT: Council voted 9-0 to enact 1-year moratorium.
MISO's first compliance filing for FERC Order 1920 (long-term regional transmission planning and cost allocation reforms) is due June 12, 2026. Interregional compliance filing due December 2026.
View context →FERC publicly committed to acting by June 2026 on a proceeding that could extend co-location and BTM rules beyond PJM to MISO, SPP, and CAISO. This is the single highest-impact near-term regulatory event for multi-ISO distressed queue strategy. Watch for an ANOPR or NOPR.
View context →FERC acts on comprehensive national rulemaking covering all RTOs/ISOs. Would establish binding rules: 60-day expedited studies for flexible loads; cost allocation methodology; co-location standards beyond PJM.
SEPA's DELTa database (Database of Emerging Large-Load Tariffs) releases quarterly: March, June, September, December. Q1 release (March 31) covered 77 tariffs at 60 utilities (51 approved, 26 pending). Q2 will capture PA model tariff framework, Dominion VA rate class, Xcel CO, and any new utility filings since March. Check sepapower.org and cross-reference 5 Edged supplemental records tagged _source. COMPLETED: Q2 release shows 77 tariffs (51 approved + 26 proposed) across 60+ utilities.
Minneapolis City Council committee public hearing on the 6-month moratorium ordinance enacted May 22. Opportunity for public comment before any modifications.
FERC committed on April 16, 2026 to issuing its national large-load interconnection order (RM26-4) by end of June 2026. As of June 22, no order has been published. Expected to establish national standards for processing ≥20 MW interconnection requests, including study timelines and cost allocation. — RESOLVED: FERC issued Section 206 show cause orders to all 6 RTOs/ISOs on June 18, satisfying the commitment. Show cause responses due Aug 17.
Deadline for parties to file interventions in the six RM26-4 show cause dockets. Passed July 9.
Distinct from S10642/A11560 (still unsigned/unvetoed). EO 62 pauses discretionary DEC environmental permits only, for one year, at a 50 MW threshold vs. the bill's 20 MW.
View context →Deadline for large-load developers to submit full project info (models, commissioning plan, attestations, fees) for Batch Zero classification.
Decides how much of Dominion's ~$1.5B transmission cost bill is allocated directly to data centers (≥25MW hyperscale customers) vs. spread to residential ratepayers. Testimony concluded July 14-15, 2026. As of Aug 3, 2026 no order has appeared in public reporting or on scc.virginia.gov docket search for Case PUR-2026-00056 — tracked as pending/watch rather than assumed decided; will confirm outcome once an order is published.
Deadline passed today. RTOs/TOs could request up to 90 days' abeyance on the Aug 17 tariff-justification deadline; FERC signaled it will heavily scrutinize such requests and disfavor extending any granted abeyance period. Outcome of any specific RTO requests not yet public as of this refresh.
Council voted 23-1 (Councilor Michael-Paul Hart the lone no) on Aug. 10 to prevent new data center permitting through Dec. 31, 2027. Sent to the Metropolitan Development Commission for final approval, possible as early as Aug. 19. Three already-approved projects (DC Blox/Warren Twp, Metrobloks/Martindale-Brightwood, Sabey/Decatur Twp) are unaffected.
Full 26-member Metro Council voted 24-1 on Aug. 13 to approve the moratorium (advanced 7-1 by the Planning & Zoning Committee Aug. 4-5), pausing new data center construction approvals for six months or until Metro Council adopts comprehensive zoning rules -- whichever comes first. Sponsor Councilwoman Jennifer Chappell called it 'the start in a long process'; advocacy group No Data Center 502 had pushed unsuccessfully for a full year.
RESOLVED (2026-08-20): The Commission approved all three good-cause exceptions ERCOT filed Aug. 10 in Project No. 59142 under 16 TAC 25.3(b): (1) relief from the Planning Guide 9.3.1(2)(a) Aug. 7 Batch Zero classification deadline, allowing conditional classification; (2) deviation from Planning Guide 5.3.5(5)(a)(ii) so conditionally-eligible Base Loads may join the August and November Quarterly Stability Assessments (6 projects identified for August on Q1-2027 energization, 17 for November on Q2-2027); and (3) authority to notice dynamic-data deficiencies after Aug. 7 with a 24-day cure period running from actual notification. ERCOT SVP of Regulatory Policy / GC Chad Seely stated ERCOT will not complete the Batch Zero study by April 9, 2027 and has not yet proposed a new deadline. ERCOT is targeting a Dec. 10, 2026 comprehensive verification/audit report filing; RFIs to Batch Zero loads begin late August/early September with possible further rounds in October and November.
HELD. Day one (Aug. 25) ran ~5 hours of testimony from Duke witnesses and intervenor experts. Florida Rising (Earthjustice) was admitted as a party over Duke's objection; OPC, FIPUG and PCS Phosphate White Springs also of record. Day two Aug. 26. No order issued; post-hearing briefs due Sept. 15.
MISO filed its large-load reliability framework at FERC on Aug. 28, 2026 (eLibrary accession 20260828-5278), requesting a Dec. 4, 2026 effective date. Retains the 50 MW 'large load' threshold and adds a 'computational load' subclass (large loads with at least 25 MW of IT-equipment demand). Four requirement areas: visibility (modeling data plus real-time and day-ahead forecasts), PMU monitoring for computational loads, ramp-rate limits on stable-state transitions, and voltage/frequency ride-through minimums. Grandfathering provisions cover existing and near-complete commercial arrangements. Partial show-cause response only — transmission products and study processes, cost-shift protections, and 'electrically proximate' generation treatment are deferred to the Nov. 16 filing.
Oklo asked FERC to order PJM to reinstate a 750 MW advanced nuclear / natural gas / fuel cell project (Meta-backed, Ohio) into the current interconnection study cycle at its original queue position. PJM withdrew the project citing deficiencies including an alleged failure to demonstrate low-voltage ride-through. Oklo claims at least a 14-month delay, sought any waivers needed to avoid disrupting the study cycle, and requested that PJM be directed to answer by Sept. 4.
View context →An IBLA administrative judge granted a stay pending appeal, halting a data center on an 80-acre BLM parcel near I-11 and US-95. The judge found persuasive evidence BLM acted arbitrarily or capriciously in carrying a 2023 solar project NEPA review forward to a data center as 'substantially the same' project. Appellants: City of Boulder City, Center for Biological Diversity, Sierra Club. No merits decision yet; the stay remains until IBLA rules.
COMPLETED — PJM filed its Rule 213 Answer on Sept. 4, 2026, the date Oklo had requested, asking FERC to deny the complaint in full. PJM argues Oklo never furnished a working model demonstrating the full 750 MW facility is stable at its Maximum Facility Output, that Tariff Part VIII, Subpart B, section 403(B) affords only one deficiency-cure opportunity, and that reinstatement would delay Phase I of Cycle 01 for the 715 compliant projects. Next watch item is Oklo's answer/reply and any FERC order; the operative pressure date is the Sept. 28 Phase I start.
View context →Adopted Sept. 8, 2026. County board ordinance enacting a text amendment to the Lake County Code of Ordinances (reported as amending Chapter 151): defines 'data center' in county code for the first time and bars new applications in unincorporated Lake County, effective immediately, running to May 2027 (reported May 11, 2027) or until permanent regulations are adopted. Unincorporated territory only — municipalities including Grayslake (T5 campus) unaffected.
View context →OUTCOME: not an adoption. Council voted unanimously to ADVANCE the 12-month moratorium and deferred the binding vote to the next regular meeting (reported as 'next week'); see the Sept. 15 entry. The 60-day interim pause adopted July 28 remains the operative restriction until the formal vote.
View context →Judge L. Brooks Anderholt ruled the county prejudicially abused its discretion by approving a lot merger for a ~1M sq ft campus without environmental review. Developer has stated an intent to appeal; appellate timeline not yet set.
View context →Unanimous vote halting applications, permits and rezonings for data centers and other large-scale power-intensive facilities in unincorporated areas. Longest local pause currently tracked.
View context →First permanent county-level prohibition in Kentucky; Versailles and Midway city councils adopted identical language so the ban is uniform countywide. Fiscal Court meeting Sept. 8, 2026; reported Sept. 10. Permanent — no expiry date.
View context →Ends by-right status in industrial zones; permanent zoning text amendment with no sunset. Definitions to be revisited at a later meeting.
View context →Council extended the pause from staff's proposed 150 days to 180 days. Previously approved data centers are exempt. Expires on or about March 13, 2027 absent extension.
Would bar council approval of any data center exceeding 10,000 sq ft for one year pending a community impact study. Planning Board is composed of council members; full council vote date not yet set.
Declared after a public hearing at the Sept. 14, 2026 meeting. Halts acceptance, review and approval of permits and development proposals for new data storage, processing and IT facilities under the Woodburn Development Ordinance. Other industrial projects unaffected. No applications pending.
View context →Covers unincorporated Laurens County only; the cities of Laurens and Clinton retain their own zoning authority. Twelve-month term running from adoption.
Commissioners voiced support Sept. 15, 2026 but did not enact a moratorium. Staff will study zoning districts, electric load, water and noise; the moratorium's length will be set by that study. The commission could take the issue up again in early December.
View context →Binding second reading of the moratorium ordinance advanced on first reading Sept. 1. Google's ~$832M 'Project Maize' data center is already under construction in the city and is expected to be grandfathered. Until the second reading passes, no moratorium is in force in Michigan City. | OUTCOME (Sept. 15, 2026): Council voted 8-1 to TABLE the ordinance rather than adopt it, routing the question back through the plan commission. Council Attorney Nick Snow said members will instead draft a resolution directing the planning department. A separate proposal to create a data center zoning district is pending.
View context →Passed late Tuesday, Sept. 15, 2026. Richmond is the third Bay Area city with a pause, after Oakley and Gilroy. Under a staff amendment the city may continue to accept and process applications but cannot approve them or issue permits. Extendable by up to 22 months and 15 days.
View context →First data center cost-allocation bill to pass a chamber of Congress. Adds a PURPA Sec. 111(d) standard directing state PUCs to consider large-load standards for data centers above 100 MW. Now in the Senate with no scheduled action. Watch for Senate Energy and Natural Resources referral or attachment to a year-end energy vehicle.
View context →Thirty days after the Aug. 17 RTO/ISO and transmission owner filings, interested entities may respond in EL26-67 (PJM), EL26-68 (SPP), EL26-69 (NYISO), EL26-70 (MISO), EL26-71 (CAISO) and EL26-72 (ISO-NE) on whether each tariff is just and reasonable and what replacement provisions should apply. Abeyance motions — PJM and TOs July 28, the other five Aug. 3 — remain undecided; American Municipal Power filed the sole opposition, against MISO's motion, on Aug. 7. UPDATE (Sept. 17, 2026 spot-check): the 30-day interested-party response window closed Sept. 16 as scheduled. No FERC merits order has issued in RM26-4 or the EL26-67 through EL26-72 dockets as of this check.
Lawmakers return to Jefferson City for the annual veto session; opponents of hyperscale data centers plan to rally inside the Capitol Rotunda. Coincides with the House Future Caucus's pledge to re-file large-load cost-recovery legislation in 2027. OUTCOME (Sept. 16, 2026): roughly 200 people rallied in the Capitol rotunda demanding a statewide hyperscale moratorium and marched to the Governor's Mansion to deliver petitions; one arrest was reported. The separately scheduled House committee hearing on data center rules was cancelled. No legislative action was taken - the veto session produced no data center bill, vote or override.
View context →After a nine-hour hearing, council deferred five appeals of the June planning approval to April 13, 2027, pending power and sound studies. Four arrests followed an altercation during public comment.
Supervisor Raymond Lancto and member Kristy Baker voted for the pause; three members voted against. The rejection clears the way for NCCS's proposed ~400 MW facility near the former Alcoa East plant.
Executive order (not a council ordinance) pausing new data center approvals for one year; scope covers any project connecting to or increasing demand on city-owned or city-operated utilities, including projects outside city limits.
Gov. Spanberger signed Executive Order 22 (2026) at the Virginia State Capitol. Sec. I.B.4 takes effect upon issuance. Also bans executive-branch NDAs and designates the Eastern Virginia Groundwater Management Area a cooling water scarcity area. Rescinds Youngkin EO 30 and Executive Directive 5.
View context →Executive order, not legislation. Effective immediately on signing and applies to every GOED abatement application not yet acted upon. Sets an unabatable 4.6% combined sales-and-use plus Local School Support Tax floor and bars applicants controlled by a designated foreign adversary.
View context →Flat $100,000 study fee; 24-month schedule-slip notice trigger.
Rescheduled from Aug. 17, 2026, when council unanimously delayed the third reading to allow an additional public safety committee meeting. Passage would pause approval of new and pending data center applications countywide for 12 months; the NorthMark project under construction on Pine Street is exempt. | RESOLVED: passed 5-1 on Sept. 21, 2026 with four narrowing amendments — see spartanburg-sc-moratorium-passed-2026-09-21.
Three bills direct the CPUC toward large-load cost allocation and special data center rates; three mandate water and resource disclosure, with AB 2469 barring local approval until projected water use is disclosed; SB 887 removes blanket CEQA exemptions with a conservation-standards fast track. Bill signatures, not an executive order. Chapter numbers and operative dates not yet reported; CPUC implementation routes into R.26-04-009.
View context →Four amendments adopted before the vote: 65 MW threshold; exemption for projects already holding county approval; siting confined to established industrial parks or former industrial sites; no on-site generation except emergency backup; primary use limited to data storage, management and processing. Ordinance number not reported. Twelve-month term; expiry date not published.
View context →First of two required public hearings held Sept. 22. All 20 speakers supported the moratorium; some asked for a longer pause or an outright ban. Second hearing Oct. 27; final council consideration early December. A 90-day moratorium needs a supermajority under Texas HB 2559.
First hearing on Ordinance 26-42 held Sept. 22. Coverage says the one-year moratorium would run from Sept. 22. Final adoption vote is at the Oct. 6 second hearing. Your Observer headlined it as the county "issuing" a ban; that article could not be read in full, so the Oct. 6 vote is treated as the binding step.
View context →Held Sept. 22. Council voted 6-3 on a resolution DIRECTING the Area Plan Commission to draft a ban. Not itself a ban. Binding ordinance expected back in about 60 days (see st-joseph-county-in-ordinance-return).
SUP required outside opportunity zones after a 90-day grace period.
Approximate date: reported Sept. 10 as 'in two weeks.' Revived proposal retains tax incentives and adds a $7.5M developer commitment to the Ferguson Neighborhood Improvement Program over 10 years, plus $1B in industrial revenue bonds and long-term abatements. The measure previously stalled in May on a split vote. Confirm the exact meeting date on the city agenda.
View context →An executive order, not a bill. Tax-exemption repeal requires 2027 legislation.
Response to Site Layer 1 LLC's proposed natural gas-powered data center near Hachita and Playas, disclosed via legal notice, that could consume up to 2.3 million cubic feet of gas hourly — implying roughly 250–400 MW of behind-the-meter generation and no interconnection queue footprint. RESOLVED Sept. 24, 2026: commissioners approved a notice of intent to consider the one-year moratorium (Shelley dissenting). The binding vote is set for Oct. 8. See the new Oct. 8 entry.
View context →Complaint denied. The 750 MW Virginia project stays out of PJM Cycle 01. Options: resubmit in the next cycle, or the Expedited Interconnection Track (open to Dec. 31, 2027). Five similar complaints are still pending.
View context →Unanimous. The 50 MW threshold follows the state hyperscale definition.
Covers the incentives and community benefits agreement. The commission's response has not been reported.
Vetoed three days after the 11-4 passage, citing legal and financial risk. An override vote is expected.
View context →First reading held Sept. 28, 2026. Second reading is in October (date not reported). Not yet in force.
Unanimous. Not yet in force.
Industrial districts only; Planning Commission approval; 500-ft setbacks; 55 dBA cap.
Held Sept. 29: the Council APPROVED Golombek's resolution for a two-year pause plus a nine-member task force. It is a resolution, not yet a local law; the mayor is reviewing with Corporation Counsel. The local-law follow-up is tracked separately (mid-October).
View context →15+ year terms, minimum bills, security and exit charges. The filing date is approximate (reported Sept. 29). A PUCT decision is expected in 2027.
Both bills passed the legislature and were delivered to the governor, who has until the end of September 2026 to sign or veto. Newsom has not signaled his position. CONDITIONAL — the precise last day within the signature window depends on the delivery date; California governors commonly act in the final days. Interacts with CAISO's pending FERC show-cause response on large-load and co-located-load interconnection. RESOLVED Sept. 21, 2026: Newsom signed AB 2383, SB 886 and SB 1168, plus four further bills (AB 2469, AB 1577, AB 2619 on water/resource disclosure and SB 887 ending blanket CEQA exemptions) -- a seven-bill package, signed nine days ahead of the end-of-September deadline. No veto.
View context →Adoption vote. Commissioners have already voted unanimously in support of a 12-month pause; this is the statutorily required second hearing. UPDATE Oct. 12: MySuncoast reports unanimous approval of the one-year moratorium (article dated Oct. 8, vote described as "Thursday").
View context →Public hearing capped at 30 minutes at the Oct. 6, 2026 council meeting, 7 p.m., municipal building on West Hargett Street. Draft covers new data centers above 10,000 square feet. Council may vote the same night. UPDATE: council approved 7-1 on Oct. 6 (Axios Raleigh); expires April 6, 2027.
Approved in committee; follows Gilroy and Richmond. UPDATE Oct. 12: Oakland City Council approved the 45-day moratorium unanimously on Oct. 6 (SFist, Oct. 7).
View context →Active dockets & PUC proceedings — every open (or recently resolved) case we're tracking across FERC and state commissions. 200 tracked, 45 open. As of 2026-10-16.
| Jurisdiction | Docket # | Title | Status | Next action | Last activity |
|---|---|---|---|---|---|
| U.S. Congress (119th) — House passed; Senate cloture failed 57-43 | H.R. 9340 |
In plain EnglishStalled in the Senate after a 57-43 procedural vote on Sept. 30; no path to enactment is scheduled.
|
Passed House 417-3 (Sept. 16, 2026); Senate cloture on motion to proceed failed 57-43 on Sept. 30, 2026 (60 needed); stalled | No further Senate action scheduled; senators leaving to campaign. Watch for a renewed vote or attachment to a year-end package. | 2026-09-30 |
| PUCT | Project 58481 |
In plain EnglishTexas finalized the rules for connecting big loads, and they are softer than proposed. The large per-MW fee is gone, and projects get more slack on schedule slips.
|
Final Rule Adopted — Sept. 18, 2026 | Rule takes effect and TDSPs implement the new study/security process. Confirm the effective date and whether any per-MW financial-security posting remains (sources conflict). | 2026-09-18 |
| PUCT | Project 59142 |
In plain EnglishTexas regulators formally excused ERCOT from the Batch Zero deadlines the Abbott audit blew through, so the process is procedurally unstuck — but ERCOT told the Commission the actual study results will now land later than April 9, 2027 and it can't say when. The real gate is ERCOT's audit report, targeted for Dec. 10, 2026. UPDATE (backfill): ERCOT issued first Batch Zero classifications privately on Sept. 3 under market notice M-A080326-04. All are conditional; some base loads were reclassified to studied load. ERCOT briefed the PUCT on Batch Zero at the Sept. 11 open meeting.
|
Open — First Batch Zero Classifications Issued Privately Sept. 3, 2026 (all conditional); Verification/Audit Underway | ERCOT to issue RFIs to provisionally-qualified Batch Zero loads (late Aug/early Sept 2026, with possible further rounds in Oct/Nov) and to file its comprehensive verification and audit report with the Commission, targeting Dec. 10, 2026 ahead of the December open meeting. ERCOT has NOT yet requested relief from the April 9, 2027 Batch Zero study delivery date but stated on the record it will not be met and that a replacement timeline is still being developed. Dec 10, 2026 |
2026-09-11 |
| ERCOT | PGRR145 / NPRR1325 |
In plain EnglishThe mechanism that decides which of ERCOT's ~440 GW of proposed large loads actually get a shot at real capacity allocation for 2028-2032. Missing a deadline here effectively means starting over under whatever process comes next.
|
Approved — Effective, Batch Zero Submission Window Open | Large-load applicants must cure deficient dynamic model data by Aug 31, 2026 or be removed from the Batch Zero Interconnection Study; ERCOT now targets delivery of the Batch Zero Interconnection Study report and Load Commissioning Plans with MW allocations (2028-2032) by April 9, 2027 (updated from the previously reported Jan 29, 2027 target) Apr 9, 2027 |
2026-08-12 |
| Virginia SCC | PUR-2025-00058 |
In plain EnglishThis is the case that produced Virginia's answer to 'who pays for the data center buildout' — data centers get a dedicated rate class with real skin in the game (minimum billing, long contracts), while residential increases came in well under what Dominion asked for.
|
Order Issued — Implementation Pending (rates effective 2027) | GS-5 rate class (≥25 MW, 85% min. billing demand, 14-yr contracts) takes effect Jan 1, 2027 |
2026-07-01 |
| New York PSC | Case 26-E-0045 |
In plain EnglishNew York is running three tracks at once on data centers: this PSC proceeding (technical/cost-allocation), the still-unsigned legislative moratorium bill, and Hochul's narrower executive order. This docket is where the eventual NY large-load tariff will likely get built.
|
Open — Active, Stakeholder Comment Phase | Technical conference scheduled before Dec 31, 2026; DPS Staff White Paper with comprehensive proposal expected by Feb 12, 2027. Stakeholder reply comments closed May 13, 2026. Dec 31, 2026 |
2026-07-31 |
| Pennsylvania PUC | M-2025-3054271 |
In plain EnglishPennsylvania built a template other states are likely to copy: big customers pay their own way (but-for standard) or can self-build the infrastructure they need instead of socializing costs to other ratepayers.
|
Final Order Issued — Utilities Filing Compliance Tariffs | Utility compliance tariff filings (e.g., PPL LP-5/LP-6) proceed toward approval | 2026-05-13 |
| Ohio PUCO | Case 24-508-EL-ATA |
In plain EnglishThe template case for 'take-or-pay at 85%' large-load tariffs nationally. Watch the Ohio House bill that would extend this structure statewide beyond AEP's territory.
|
Order Issued — Tariff in Effect | Monitor for extension to rest of Ohio via pending House bill | 2026-02-20 |
| Georgia PSC | Docket 44280 |
In plain EnglishGeorgia doesn't have a single 'data center tariff' docket like Ohio or Pennsylvania — it runs the cost-allocation fight through the IRP process instead. This is the docket to watch for how much new gas/solar capacity gets justified by data center load.
|
Open — Ongoing (Triennial IRP + Updates) | PSC review of Customer Identified Resource program filings; Georgia Power's Quarterly Large Load Economic Development Report for Q1 2026 was filed May 15, 2026 per the 2025 IRP Stipulation; a base-rate freeze (ordered Jul 31, 2025) remains in effect through 2028 | 2026-05-15 |
| FERC | RM26-4 |
In plain EnglishThe single most consequential federal docket in this space — it's forcing every RTO/ISO to show its homework on large-load rules within months, not years. NYISO and ISO-NE, largely untested on this so far, are the ones to watch most closely.
|
Open — Show Cause Responses Filed; Abeyance Motions Undecided | Interested-party responses due ~Sept. 16, 2026 in the six companion EL26-67 through EL26-72 dockets; FERC ruling on the abeyance motions outstanding. As of Sept. 17, 2026 the interested-party response window has closed; no Commission order had issued and the next enforceable step is FERC action on the record. MISO and its transmission owners have committed to a full show-cause response by Nov. 16, 2026. Sep 16, 2026 (past) |
2026-08-17 |
| FERC | EL25-49-000 et al. |
In plain EnglishFERC keeps sending PJM's homework back for revisions — PJM tried to redefine what counts as a 'co-located' data center+power plant setup, FERC said no, and PJM has resubmitted; we're waiting on FERC's next grade.
|
Further Compliance Filing Submitted (May 18, ER26-1088-001) — Awaiting FERC Review | FERC review of PJM's May 18, 2026 further compliance filing (Docket ER26-1088-001) responding to FERC's April 16 order, which accepted PJM's interconnection-pathway clarifications but rejected its revised 'Co-Located Load' definition and BTM application changes | 2026-05-18 |
| FERC | ER26-1323 |
In plain EnglishSPP's answer to 'we can't wait years for a full interconnection study' — fast access in exchange for accepting you might get curtailed when the grid is stressed. Georgia/Texas/Virginia don't have an exact equivalent yet.
|
Approved — Effective | Monitor CHILLS uptake / curtailment performance | 2026-06-05 |
| CAISO | Large Load Considerations Initiative (stakeholder, no docket #) |
In plain EnglishCAISO is still working through its own internal process for setting technical rules for large loads (separate from the FERC order below) — it posted a detailed draft in mid-June and is now taking stakeholder feedback.
|
Open — Straw Proposal Process Continuing; Targeting Nov 16, 2026 FERC Compliance Filing (under EL26-71) | CAISO's stakeholder timeline: further straw proposal (~Aug 12, 2026), stakeholder workshops (Aug 19 and Sept 28), comments due Sept 2 and Oct 12, CAISO Board of Governors review Oct 28 — feeding into a targeted Nov 16, 2026 FERC compliance filing responding to the EL26-71 show-cause order Nov 16, 2026 |
2026-07-20 |
| Minnesota PUC | Docket 25-289 |
In plain EnglishMinnesota's version of the 'you can't just leave and stick residents with the bill' large-load tariff — long contracts, real exit penalties.
|
Approved | Monitor compliance filings; separate data-center rate class to be built into future Xcel rate cases | 2026-05-15 |
| Oregon PUC | UM 2377 |
In plain EnglishOregon's answer skews toward long, size-scaled contracts with a real surcharge on the biggest projects — notably stricter than Georgia's approach, in the same range as Virginia's.
|
Approved (Order No. 26-154) | PacifiCorp/Pacific Power has since filed its own large-load tariff — Schedule 401 'Service to New Large Energy Use Facilities' (Advice No. 25-015) under Docket UE 463, implementing HB 3546 — now pending Commission review (tracked separately in this file) | 2026-05-07 |
| Washington UTC | Data Center Workgroup (SB 5982 implementation) — no adjudicative docket yet |
In plain EnglishWashington splits into two clocks. Pricing arrives Oct. 1, 2026 when utilities file SB 5982 large-load tariffs. Siting, water and cost-shift rules are a 2027 legislative question that has not been drafted. The 20 MW threshold legislators keep reaching for would capture mid-scale and colocation load that most jurisdictions leave alone.
|
Open — Stakeholder Workgroup; Final Report Due Later 2026; 2027 Legislation Signaled | Two gating deliverables: Data Center Workgroup final report (later in 2026) and the Governor's task force report, both expected to frame 2027 legislation. Separately, SB 5982 requires Washington utilities to file large-load tariffs by Oct. 1, 2026. Oct 1, 2026 (past) |
2026-08-26 |
| Oklahoma OCC | Case No. PUD2026-000046 (OG&E) — PSO case number not yet confirmed |
In plain EnglishOklahoma regulators now have a firm decision date — November 3, 2026 — for OG&E's large-load data center rate plan. PSO's parallel filing is still working through the process without a confirmed case number yet.
|
Open — Procedural Schedule Set, Decision Expected Nov 3, 2026 | OCC decision on OG&E large-load tariff (Case No. PUD2026-000046) scheduled for November 3, 2026 Nov 3, 2026 |
2026-07-01 |
| Colorado PUC | Proceeding 26AL-0137E |
In plain EnglishColorado is not really arguing about whether data centers pay — the 50 MW cost-causation structure is fairly conventional. The fight is over the Speed-to-Market carve-out, which would be the fastest route to energized load in Xcel Colorado if it survives. Strip it out and Colorado becomes a slower but more predictable jurisdiction.
|
Open — Public Comment Hearing Held Aug 25, 2026; Non-Unanimous Settlement Pending Commission Decision | Commission deliberation/decision on the non-unanimous settlement. Principal contested issues: the Speed-to-Market pathway that would let large loads reach service outside the tariff under review, the 50 MW threshold, and cost-allocation methodology. No decision date set. | 2026-08-25 |
| Illinois ICC | Docket Nos. 25-0677 / 25-0679 (Consol.) |
In plain EnglishA deposit requirement, not a full tariff — Illinois is moving in stages rather than adopting an Ohio/Pennsylvania-style comprehensive framework in one shot.
|
Approved | Monitor for interaction with the separate LDPAC consumer-protection investigation (below) | 2026-03-20 |
| Illinois ICC | Staff-Directed Investigation (opened by 2026-04-23) — Docket # TBD |
In plain EnglishThis is the docket that will decide whether Illinois residential ratepayers end up subsidizing ComEd's data-center-driven grid upgrades, or whether developers pay their own way.
|
Open — Investigation Directed | ICC Staff to report on methods protecting consumers from distribution-upgrade cost burdens tied to data centers; investigation is to be completed within 8 months of the Mar 20, 2026 order (i.e., around November 2026) Nov 20, 2026 |
2026-04-23 |
| Maryland General Assembly | HB 120 (2026RS) |
In plain EnglishMaryland's most aggressive moratorium proposal failed — worth watching whether a narrower version returns next session given NY's EO 62 precedent.
|
Dead — Failed to Advance | None this session — monitor for reintroduction in 2027 | 2026-04-13 |
| New York DEC / PSC | Executive Order No. 62 (not an adjudicated docket) |
In plain EnglishBelongs in this tracker as the single most consequential near-term action item for anyone with a ≥50MW NY project awaiting a DEC permit.
|
Signed — In Effect | Monitor for expiration/renewal in July 2027; separately, S10642/A11560 passed both houses of the Legislature on Jun 4, 2026 (Senate 44-16, Assembly 102-39) and awaits action — now tracked as its own record in this file — with most observers expecting Hochul to let it lapse or veto it given EO 62 already covers similar ground Jul 14, 2027 |
2026-07-14 |
| FERC | ER26-1556 / ER26-1563 (PJM DR tariff revisions — verify exact docket before citing) |
In plain EnglishThis directly affects how much 'capacity value' demand response — including curtailable large loads — gets credited for in PJM's capacity market, which flows straight into auction clearing prices data centers are exposed to.
|
Approved (Order ~2026-05-05) | 24/7 DR availability window takes effect Jun 1, 2027 |
2026-05-05 |
| FERC / NERC | NERC Project 2026-02 (filed under RM26-4) |
In plain EnglishThis decides who officially counts as a 'large load' for reliability-compliance purposes nationally — directly relevant to which data centers/co-location projects get pulled into mandatory reliability requirements (voltage ride-through, etc.).
|
Open — Initial Formal Comment Period and Ballot Closed Sept. 18, 2026; Standards Filing Due Dec. 31, 2026 | NERC to file one or more new or modified mandatory Reliability Standards governing computational load integration with FERC by Dec. 31, 2026, per FERC directive. Phase 1 SAR proposes Glossary definitions for 'computational load' and 'computational load entity' plus a new standard on near-term large computational load integration. Dec 31, 2026 |
2026-09-18 |
| MISO | Attachment GGG / MHVDC — Not Yet Filed at FERC |
In plain EnglishRelevant to merchant HVDC / co-located generation projects connecting into MISO — worth re-checking FERC eLibrary directly once MISO actually files, since our source shows this is still pending. As of Aug. 28 nothing has hit the FERC docket yet; MISO's public position is still 'before end of August,' and the full show-cause response is separately committed for Nov. 16, 2026.
|
Pre-Filing — Stakeholder Process (PAC-2024-6); Aug. 31 target MISSED, still unfiled at FERC as of Sept. 1, 2026 | Aug. 31, 2026 target passed without a filing. MISO's 50 MW large-load framework is nominally effective today (Sept. 1) with no accepted FERC tariff authority behind it. The binding deadline is now the Nov. 16, 2026 MISO/Transmission Owner response to FERC's June 18 Section 206 show-cause order. Watch for an ER26-series docket number to be assigned on filing. Nov 16, 2026 |
2026-09-01 |
| DOE / ERCOT | DOE Order 202-26-01 |
In plain EnglishThe federal government can now, in an emergency, effectively commandeer a data center's on-site backup generators to help keep the ERCOT grid up. Directly relevant to anyone underwriting BTM generation economics.
|
Issued — In Effect | Monitor for renewal/expiration and ERCOT M-13-style compliance guidance | 2026-01-24 |
| DOE / PJM | DOE 202(c) Emergency Order (PJM) |
In plain EnglishSame mechanism as ERCOT's order, now a standing PJM manual procedure rather than a one-off emergency order — meaningful for any PJM-area co-location/BTM deal underwriting.
|
Issued — In Effect | PJM Manual 13 Revision 98 formalizes the BTM Emergency Procedure going forward | 2026-02-01 |
| New Jersey BPU | S731/A796 implementation — BPU tariff docket(s) not yet opened |
In plain EnglishNew Jersey's new law is on the books, but the actual utility-specific rate filings that will set real dollar terms haven't been submitted to the BPU yet — that's due by early January 2027.
|
Statute Enacted — Utility Tariff Filings Not Yet Due | Each NJ electric public utility must file a tariff application with the BPU for large-load data centers (100 MW+ maximum monthly demand) within 180 days of the law's effective date Jan 3, 2027 |
2026-09-16 |
| North Carolina UC | Docket Nos. E-7 Sub 1329 (Duke Energy Carolinas) / E-2 Sub 1380 (Duke Energy Progress) rate cases; dedicated Large Load Tariff (LLT) proceeding per Jul 20, 2026 settlement, docket # TBD |
In plain EnglishNorth Carolina doesn't have an approved data center tariff yet, but Duke Energy has put a specific proposal on the table and state law already requires one to exist by 2028 — this is one to watch for a ruling this fall.
|
Settlement Reached (Jul 20, 2026) — Dedicated Large Load Tariff Proceeding To Be Established | NCUC to open and rule on the dedicated Large Load Tariff (LLT) proceeding agreed to in the Jul 20, 2026 rate case settlement; the LLT will apply to large-load agreements signed on or after Jan 1, 2027; final order expected late 2026 Nov 1, 2026 |
2026-07-20 |
| Indiana IURC | Cause No. 46097 |
In plain EnglishIndiana's rule making data centers pay their own way on the grid is signed, sealed, and being watched — if a data center tries to walk back a large chunk of its committed power use, regulators have to sign off first.
|
Approved — Implementation Ongoing (Settlement) | Monitor I&M compliance reporting; any planned reduction of more than 20% of a large-load customer's contracted peak capacity must be submitted to the IURC for review and approval | 2026-06-01 |
| Michigan PSC | U-21859 |
In plain EnglishMichigan's Consumers Energy now has an approved rulebook for what a big data center has to commit to and pay if it wants power — including a hefty exit fee if it backs out early.
|
Approved — In Effect | Consumers Energy annual compliance reporting on large-load tariff contracts, capacity/energy demand changes, and terminations | 2025-11-06 |
| Michigan MPSC | U-22061 |
In plain EnglishRegulators told DTE to stop doing one-off data center deals and write a real tariff. DTE did — it's docket U-22061, and it covers anyone asking for more than 100 MW, which is essentially every AI data center.
|
Open — DTE large-load tariff application confirmed on file; contested case, briefing underway | MPSC review of DTE's proposed Large Load Provision applying to customers requesting service above 100 MW (administrative fees of $100K/$250K by contracted capacity tier, 15-year minimum-billing-demand termination fee); ALJ Katherine E. Talbot presiding. No commission decision date published as of this refresh. | 2026-08-03 |
| Wisconsin PSC | 6630-TE-113 |
In plain EnglishWisconsin widened its special data-center rate class to catch smaller projects too, and locked customers into 15-year contracts so they can't leave existing ratepayers holding the bag.
|
Order Issued (Apr 24, 2026) — VLC Tariff Overhauled | We Energies implementation of revised Very Large Customer tariff (lowered 100 MW eligibility threshold, 15-year minimum initial term) | 2026-04-24 |
| Wisconsin PSC | 6680-TE-115 |
In plain EnglishWisconsin told Alliant Energy to stop cutting one-off deals with each data center and instead publish one standard rate plan everyone can see.
|
Approved with Modifications (May 7, 2026) — Meta Beaver Dam Contract Approved; Standalone Large-Load Tariff Directed | Alliant Energy to file a standalone large-load tariff per the PSC's May 7, 2026 order, in addition to the now-approved Individual Contract Rate agreement serving the Meta data center campus in Beaver Dam | 2026-05-07 |
| South Carolina General Assembly | S.867 (Data Center Development Act) |
In plain EnglishSouth Carolina came close to requiring a special state permit before any new data center could break ground, but the legislative session appears to have run out the clock before a final vote — worth re-checking next cycle.
|
Passed Senate Committee (Apr 28, 2026) — Session Adjourned Without Full Senate Floor Vote; No 2026 Enactment | Confirm whether S.867 carries over into a later session or must be reintroduced; companion bill H.5215 (Ratepayer Protection and Large Load Customer Infrastructure Accountability Act), introduced Feb. 19, 2026, also did not reach final passage in 2026 | 2026-04-28 |
| Louisiana PSC | R-37905 |
In plain EnglishLouisiana regulators are still figuring out the rules for data centers that want to build their own private power hookups instead of using the regular grid — a conference happened in May, but there's no final rulebook yet.
|
Open — Comment Period on Non-Binding Guidelines Closed (Jun 19, 2026 via repository Docket X-37921); Finalization Pending | LPSC to finalize the Large Load Additions Non-Binding Guidelines after reviewing stakeholder comments filed in repository Docket X-37921 (comment period closed Jun 19, 2026, following the May 7, 2026 technical conference) | 2026-06-19 |
| FERC | ER26-3380-000 |
In plain EnglishFERC has ruled: mostly yes, but paused for five months with three open problems. The Sept. 30 bid window is off and no new date is set.
|
FERC Order Issued Sept. 29, 2026 — Accepted in Large Part, Suspended Five Months (eff. Feb. 28, 2027, subject to refund); PJM Timing TBD | PJM to update on revised RBP timing at Oct. 7 MIC; PJM to address FERC's three flagged issues (cost allocation, TO exit costs, LSE collateral). Sept. 30-Oct. 21 window will not proceed. Oct 7, 2026 (past) |
2026-09-29 |
| FERC | PJM CIFP — Interim Resource Adequacy Service (IRAS, formerly 'Connect and Manage') (FERC docket # TBD — filing pending) |
In plain EnglishIf a data center doesn't bring its own power plant and isn't running by June 2027, PJM can now cut its power first — before regular emergency demand-response programs kick in — and PJM will keep a public registry of exactly where these big loads are.
|
Board Decision Issued (July 27, 2026) — FERC Filing Pending | PJM's related large-load curtailment ('IRAS') filing was targeted for around Aug. 7, 2026; as of this Aug. 10, 2026 refresh no confirmed public filing or FERC docket number has been located — flagging as overdue relative to PJM's own stated target. Curtailment exposure for qualifying large loads begins June 1, 2027. Jun 1, 2027 |
2026-08-10 |
| FERC | EL26-71-000 |
In plain EnglishThis is FERC's individual order to California's grid operator (CAISO) telling it to either justify its current data-center connection rules or propose fixes, due by mid-August 2026. It's the CAISO-specific piece of the broader six-ISO FERC crackdown.
|
Open — Show Cause Response Deadline Passed (Aug. 17, 2026); Abeyance Motion Pending | Interested-party response window closes ~Sept. 16, 2026; FERC has not yet ruled on the CAISO abeyance motion. As of Sept. 17, 2026 the interested-party response window has closed; no Commission order had issued and the next enforceable step is FERC action on the record. MISO and its transmission owners have committed to a full show-cause response by Nov. 16, 2026. Nov 16, 2026 |
2026-08-17 |
| Arizona ACC | E-00000A-25-0069 |
In plain EnglishArizona's utility regulator is building out its rulebook for how data centers get connected and charged, starting with an April workshop; meanwhile the state's largest utility (APS) is in a live rate case trying to charge data centers significantly more.
|
Open — Workshop Held (April 16, 2026), Follow-On Proceedings Ongoing | Monitor for Commission action following workshop; APS rate case (separate docket, evidentiary hearing May–July 2026) proposes ~45% rate increase for data center customers effective 2H2026 | 2026-07-09 |
| Oklahoma Legislature | SB1488 (2026 Regular Session) |
In plain EnglishA separate, broader Oklahoma bill that would have paused big data center construction for years didn't get a committee vote and is dead for this session — a narrower ratepayer-protection law (HB 2992) passed instead.
|
Failed — Did Not Advance Out of Committee, Session Adjourned | None — bill died this session; monitor for reintroduction in 2027 | 2026-07-31 |
| Nevada PUC | PUCN Docket No. 20-08014 |
In plain EnglishMicrosoft is asking Nevada regulators to make large AI data center customers pay directly for the grid upgrades built just for them, so other NV Energy customers aren't stuck with the bill. Comments are open through October 2026; a decision isn't expected until mid-2027.
|
Open — Public Comment Period (through October 2026) | Evidentiary hearings scheduled January 2027; final decision expected mid-2027. Jan 1, 2027 |
2026-05 |
| Utah PSC | Consolidated Docket Nos. 25-R318-01 & 24-035-43 |
In plain EnglishUtah regulators are studying how to design a special electricity rate for very large customers like data centers on Rocky Mountain Power's system, including how those customers should pay for new power lines built to serve them.
|
Open — Scoping Comment Round Complete (Reply Comments Filed Mar 19, 2026); Awaiting Further Commission Action | Commission reviewing initial (Mar 5, 2026) and reply (Mar 19, 2026) scoping comments on large-load flexible tariff design; no hearing date confirmed in public sources yet. Related: a separate RMP large-load service contract docket (26-035-05) is also pending. | 2026-03-19 |
| SPP | Consolidated Planning Process (CPP) — Large Load Cluster Study (stakeholder, no FERC docket #) |
In plain EnglishThis is SPP's slower, more thorough track for data centers that want a real firm grid connection rather than the fast-but-curtailable CHILLS option. The first batch of projects starts moving through this process this month.
|
Open — First Cluster Study Window Held Apr 1–May 31, 2026; 180-Day Interconnection Cluster Study Underway | 180-day large-load Interconnection Cluster Study proceeding after FERC approved SPP's reformed CPP queue design on Mar 13, 2026; final interconnection agreements from the first cycle expected early 2027 Mar 1, 2027 |
2026-08-03 |
| Virginia SCC | PUR-2026-00056 |
Dominion Rider T-1 (Transmission Rate Adjustment Clause) Annual Review — Data Center Cost Assignment
In plain EnglishThis is the case investors should watch as the mechanism for how Virginia shifts transmission buildout costs onto data centers going forward. The SCC didn't just approve a rate — it told Dominion to go build the actual cost-assignment tariff, so the real number (and who it hits) is still to come in a follow-on filing.
|
Order Issued — Directs Development of Data Center Cost-Assignment Tariff (follow-on tariff design pending) | Dominion to develop and file a new tariff mechanism directly assigning transmission costs (new substations/lines built solely for large loads) to data centers/large-load customers; timing not yet specified by SCC | 2026-08-05 |
| South Carolina PSC | Docket No. 2025-6-G (Generic Docket — Large-Load Customers) |
In plain EnglishSouth Carolina regulators are opening a dedicated case to write the actual rate and interconnection rules for large data-center customers, separate from the state legislature's siting-permit bill.
|
Open — Petition Filed Per Duke Energy Carolinas/Progress Settlement | PSC to establish procedural schedule and evaluate large-load rate schedules, interconnection rules, and service regulations | 2026-06-01 |
| Kentucky PSC | Case No. 2025-00140 |
In plain EnglishKentucky's PSC signed off on a specific electricity rate plan that East Kentucky Power Cooperative can use just for data center customers, distinct from its standard industrial rates.
|
Approved | None — tariff approved and in effect. | 2025-10-30 |
| Kentucky PSC | Rate case docket (KU/LG&E) — specific case # not confirmed in public reporting |
In plain EnglishKU and LG&E got the green light for a new rate category designed for customers — like data centers — that draw power almost constantly at a steady high level, which is priced differently than typical industrial usage.
|
Approved | None identified — tariff approved as part of KU/LG&E's broader rate review. | 2026-02 |
| Kentucky Legislature | HB 593 / HB 544 (2026 Regular Session) |
In plain EnglishKentucky lawmakers tried to pass rules forcing big data centers to pay for their own grid upgrades, but the effort collapsed at the end of the legislative session amid opposition from utilities and tech companies like Amazon. Nothing changed as a result — the issue could resurface next session.
|
Closed — Failed to Pass (2026 session adjourned April 16, 2026) | None this session; could be reintroduced in a future session. | 2026-04-16 |
| California CPUC | R.26-04-009 |
In plain EnglishCalifornia is later to the large-load-tariff table than Ohio, Pennsylvania, or Georgia, but it just opened the case that will decide how the state's utilities charge data centers for the grid upgrades built to serve them.
|
Open — Rulemaking Instituted (Apr 2026), SB 57 Cost-Impact Assessment Due Jan 1, 2027 | CPUC to develop a data-center-specific rate/tariff framework and cost-recovery approach (interconnection, transmission/distribution, generation) per SB 886 and SB 57; Commission-mandated cost-impact assessment due by Jan 1, 2027 Jan 1, 2027 |
2026-04-10 |
| Missouri PSC | Case No. EO-2025-0154 |
In plain EnglishMissouri's second-largest investor-owned utility now has a specific, PSC-approved rate plan for feeding very large loads like data centers, built with direct input from Google and the Data Center Coalition.
|
Approved | Monitor Evergy Missouri Metro / Missouri West compliance filings under the approved LLPS tariff | 2026-07 |
| Iowa Utilities Commission | TF-2025-0007 / TF-2025-0047 |
In plain EnglishIowa is still handling data centers deal-by-deal rather than through one statewide rulebook — these are the two contracts approved so far for the Google and QTS projects sharing an industrial park near Cedar Rapids.
|
Approved | Monitor for a generic/statewide Iowa large-load tariff docket; legislation (e.g., HF 2447) has been proposed directing the IUC to adopt one, but no such generic docket is confirmed yet | 2026-04 |
| Nebraska Legislature | LB 1261 (2026) |
In plain EnglishNebraska is telling the biggest data centers (think 1+ GW projects) to bring or fund their own power plant rather than expect the state's public power utilities to build it and spread the cost to everyone else.
|
Enacted — In Effect (July 17, 2026) | Monitor for first projects utilizing the privately-funded generation pathway | 2026-04-10 |
| Nebraska Legislature | LB 1010 (2026) |
In plain EnglishNebraska data centers and crypto miners now have to report how much power they're actually using — a transparency step short of a full tariff, paired with a separate law (LB 1261) governing how the biggest projects get their power.
|
Enacted — In Effect (July 17, 2026) | Monitor for implementing reporting rules/guidance from Nebraska public power utilities | 2026-04-10 |
| Oregon PUC | UE 463 (Advice No. 25-015, Schedule 401) |
In plain EnglishOregon's second major utility, PacifiCorp/Pacific Power, has now put its own version of a data-center rate plan on the table — separate from PGE's already-approved one — aimed at making big new loads pay their own infrastructure freight.
|
Filed — Pending Commission Review | OPUC review of PacifiCorp's proposed Schedule 401 large-load tariff, including its proposal to eliminate most of the line-extension allowance for new customers ≥25MW | 2026-05-11 |
| New York Legislature | S10642 / A11560 |
In plain EnglishNew York's legislature actually passed a broader, harder-edged data center moratorium than what Hochul ultimately did on her own — but she appears to be sidestepping it with her own executive order rather than signing it into law.
|
Passed Legislature (Jun 4, 2026) — Awaiting Governor's Action | Governor Hochul to sign, veto, or allow the bill to become law; commentary broadly expects a veto (or the bill lapsing without action) given Executive Order No. 62 (tracked separately in this file) already implements a similar one-year pause via executive action | 2026-06-04 |
| PUCT | Docket No. 59220 |
In plain EnglishTexas regulators said yes to this data center plugging into a wind farm, but only if it agrees to go dark fast (30 minutes) when the grid is stressed, and it doesn't get paid for that flexibility the way normal demand-response participants would.
|
Order Issued -- Curtailment Terms Affirmed (late July 2026) | None -- order issued; monitor for compliance filings or appeals | 2026-07-24 |
| Florida PSC | 20260064-EI |
In plain EnglishDuke Energy Florida wants a special rate for AI data centers, and regulators haven't thrown the plan out — but they also haven't approved it, and a hearing in late August will decide whether it holds up.
|
Active — Evidentiary Hearing Held Aug. 25; Day 2 Aug. 26, 2026 | Post-hearing briefs were due Sept. 15, 2026 following the Aug. 2026 evidentiary hearing. Await Commission decision on Duke Energy Florida's Large Load Customer Policy, Large Load Customer Agreement and related CIAC changes under SB 484 (50 MW firm-load threshold, including co-located load). Tariffs were suspended June 19, 2026 rather than allowed to take effect; agenda conference date not yet published. | 2026-09-15 |
| Florida PSC | Statewide rulemaking — CS/CS/SB 484 (2026) implementation |
In plain EnglishFlorida's new law forces every big electric utility to submit a special data-center rate plan to regulators by October 1, 2026, and makes sure data centers — not everyday ratepayers — cover the cost of the power they use, while also tightening water permitting for large data centers.
|
Rulemaking Pending — Statute Effective July 1, 2026 | Each public electric utility must file a large-load tariff for PSC approval by Oct. 1, 2026; PSC must adopt implementing rules; independent OPPAGA study of large-scale data center impacts also required Oct 1, 2026 (past) |
2026-07-01 |
| Florida PSC | 20250011-EI (LLCS-1 large load tariff, via Nov. 2025 rate settlement) |
In plain EnglishFPL already has a special, pricier electricity rate track for very large customers like data centers, approved alongside its big 2025 rate case — separate from the new statewide tariff-filing mandate every utility now faces under SB 484.
|
Approved (as part of November 2025 rate case settlement) | Monitor for amendments as FPL processes large-load (incl. data center) interconnection requests under LLCS-1 and CS/CS/SB 484's Oct. 1, 2026 statewide tariff-filing deadline Oct 1, 2026 (past) |
2025-11-20 |
| FERC | EL26-67-000 |
In plain EnglishFERC's order telling PJM to either defend its current data-center connection rules or propose fixes, due mid-August 2026 — the PJM piece of a nationwide six-ISO crackdown.
|
Open — Show Cause Response Deadline Passed (Aug. 17, 2026); Abeyance Motion Pending | Interested-party responses close ~Sept. 16, 2026. Separately, PJM introduced proposed Large Load voltage/frequency ride-through standards at its Sept. 8 Planning Committee and states it will file proposed solutions at FERC in November 2026; PC special education session Sept. 15. As of Sept. 17, 2026 the interested-party response window has closed; no Commission order had issued and the next enforceable step is FERC action on the record. MISO and its transmission owners have committed to a full show-cause response by Nov. 16, 2026. Nov 16, 2026 |
2026-09-10 |
| FERC | EL26-68-000 |
In plain EnglishFERC's order telling SPP to either defend its current data-center connection rules or propose fixes, due mid-August 2026.
|
Open — Show Cause Response Deadline Passed (Aug. 17, 2026); Abeyance Motion Pending | Interested-party response window closes ~Sept. 16, 2026; FERC has not yet ruled on the SPP abeyance motion. As of Sept. 17, 2026 the interested-party response window has closed; no Commission order had issued and the next enforceable step is FERC action on the record. MISO and its transmission owners have committed to a full show-cause response by Nov. 16, 2026. Nov 16, 2026 |
2026-08-17 |
| FERC | EL26-69-000 |
In plain EnglishFERC's order telling NYISO to either defend its current data-center connection rules or propose fixes, due mid-August 2026.
|
Open — Show Cause Response Deadline Passed (Aug. 17, 2026); Abeyance Motion Pending | Interested-party response window closes ~Sept. 16, 2026; FERC has not yet ruled on the NYISO abeyance motion. As of Sept. 17, 2026 the interested-party response window has closed; no Commission order had issued and the next enforceable step is FERC action on the record. MISO and its transmission owners have committed to a full show-cause response by Nov. 16, 2026. Nov 16, 2026 |
2026-08-17 |
| FERC | EL26-70-000 |
In plain EnglishFERC's order telling MISO to either defend its current data-center connection rules or propose fixes, due mid-August 2026.
|
Open — Show Cause Response Deadline Passed (Aug. 17, 2026); Abeyance Motion Pending | Interested-party response window closes ~Sept. 16, 2026; FERC has not yet ruled on the MISO abeyance motion (American Municipal Power filed the sole opposition, Aug. 7). As of Sept. 17, 2026 the interested-party response window has closed; no Commission order had issued and the next enforceable step is FERC action on the record. MISO and its transmission owners have committed to a full show-cause response by Nov. 16, 2026. Nov 16, 2026 |
2026-08-17 |
| FERC | EL26-72-000 |
In plain EnglishFERC's order telling ISO-NE to either defend its current data-center connection rules or propose fixes, due mid-August 2026.
|
Open — Show Cause Response Deadline Passed (Aug. 17, 2026); Abeyance Motion Pending | Interested-party response window closes ~Sept. 16, 2026; FERC has not yet ruled on the ISO-NE abeyance motion. As of Sept. 17, 2026 the interested-party response window has closed; no Commission order had issued and the next enforceable step is FERC action on the record. MISO and its transmission owners have committed to a full show-cause response by Nov. 16, 2026. Nov 16, 2026 |
2026-08-17 |
| PUCT | Project 58480 |
In plain EnglishThis is the rule that decides which of the hundreds of proposed data centers actually count toward ERCOT's official 'how much power do we need to plan for' number.
|
Open — Rulemaking, Adoption Targeted Early-Mid 2026 | Rule adoption pending; defines ≥10 MW single-site 'large load customer' threshold and documentation/milestone requirements feeding ERCOT's transmission planning and resource-adequacy forecasts | 2026-07-15 |
| PUCT | Project 58482 |
In plain EnglishTexas is building an opt-in 'get paid to power down during emergencies' program for big power users, separate from the mandatory curtailment deals struck case-by-case for co-located data centers.
|
Open — Rulemaking (SB 6 mandate), Scoping Underway | Rule adoption expected later in 2026; creates the voluntary demand-reduction program for large loads required by SB 6 | 2026-06-01 |
| PUCT | Project 58484 |
In plain EnglishThis is where Texas regulators are deciding whether data centers are covering the true cost of the power lines built to serve them, or quietly pushing that cost onto everyone else's bill.
|
Open — Rulemaking, Draft Report Issued (comments requested) | PUCT evaluating whether existing wholesale transmission cost-allocation methodology and retail ratemaking practices appropriately assign transmission costs by customer class, including large loads | 2026-03-30 |
| PUCT | Project 59772 |
In plain EnglishRegulators are trying to fix ERCOT's official demand forecast so it reflects data centers that are actually likely to get built, not just every proposal that's filed paperwork.
|
Open — Active | PUCT/ERCOT working to refine which large-load queue entries are reflected in the official 2026 load forecast, amid concern the headline queue overstates real near-term demand | 2026-06-18 |
| PUCO (Ohio) | 26-113-EL-ATA |
In plain EnglishOhio regulators are making sure that if a data center gets a special power deal and then decides to bail on it, the cost of covering that gap falls on the data center — not on everyone else's electric bill.
|
Open — Compliance/Implementation Phase | PUCO-ordered process requiring data center customers to give AEP Ohio 180-day notice before returning to standard/default service; AEP Ohio procures replacement energy via standalone auctions or spot purchases, cost assigned entirely to the data center customer | 2026-08-07 |
| South Carolina PSC | 2026-138-E |
In plain EnglishSouth Carolina's general 'how should we think about data centers' policy conversation, separate from the specific fight over one company's gas plant.
|
Open — Comment Phase | Generic proceeding collecting stakeholder comments on how South Carolina should handle large-load (data center) additions; feeds into utility-specific dockets like 2026-158-E | 2026-08-07 |
| South Carolina PSC | 2026-158-E |
In plain EnglishA $3 billion data center wants to build its own private gas power plant big enough to rival a utility plant, and is arguing state regulators have no say over it because it's not selling that power to the public. Regulators haven't decided yet — and the company is building anyway.
|
Open — Contested, Awaiting Commission Decision on CECPCN Jurisdiction | PSC to rule on whether Valara's 450 MW behind-the-meter gas plant (6x the 75 MW Siting Act threshold) requires a Certificate of Environmental Compatibility and Public Convenience and Necessity (CECPCN) despite Valara's argument that a private, non-public-serving generator is exempt; no decision reached after Aug 5 hearing (largest PSC turnout since 2018) | 2026-08-07 |
| Louisiana PSC | X-37921 |
In plain EnglishLouisiana is writing a general playbook for handling future data-center power deals, drawing lessons from the massive Meta/Entergy deal that's already under construction.
|
Open — Comment Period Closed, Guidelines Pending | LPSC to finalize non-binding guidelines for large-load additions after a May 7, 2026 technical conference; comments closed June 19, 2026 | 2026-06-19 |
| Georgia PSC | 55378 |
In plain EnglishGeorgia Power has to tell regulators every quarter what's happening with big new power customers like data centers — a rare, regular window into the actual pipeline rather than one-off announcements.
|
Open — Ongoing Compliance Reporting | Georgia Power continues quarterly filings on large-load economic-development activity per the 2023 IRP Update stipulation; next quarterly report expected per standard cadence | 2026-08-01 |
| Michigan MPSC | U-22058 |
In plain EnglishMichigan's regulator was supposed to rule on Google's data center power contracts by Sept. 10. Four days later there is still no published decision.
|
Pending — No Public Order 4 Days Past Conditioned Decision Date | Await issuance of an MPSC order in U-22058. Verify against MPSC E-Dockets; no order, Commission news release or contemporaneous press report had surfaced publicly as of the morning of Sept. 14, 2026. | 2026-09-14 |
| Fort Worth, TX (City Council) | Ordinance — number not yet assigned (Ch. 212 Tex. Local Gov't Code process) |
In plain EnglishFort Worth hasn't actually paused data center construction yet -- it just started the roughly six-month legal process required to do so, and today's move mainly bites through a new permit-application paperwork requirement (proof of PUCT/ERCOT interconnection approval), not a construction freeze.
|
Initiated — First Reading/Procedural Vote Only, Not Yet Effective | City must complete Texas Local Gov't Code Ch. 212 notice/hearing steps, including two ordinance readings not less than 28 days apart, before the moratorium can take effect; earliest possible effective date reported as Feb. 16, 2027. New PUCT/ERCOT interconnection-approval-evidence permit requirement is already in effect. Newly-created Data Center & Infrastructure Commission expected to hold initial meetings and inform final moratorium scope. Feb 16, 2027 |
2026-08-11 |
| Georgia Legislature | HB 1012 (2025-2026 Regular Session) |
In plain EnglishA bill to freeze new data center permitting statewide in Georgia was introduced but never got out of committee, so it has no legal effect. Georgia's more active local moratoriums (24 tracked) and SB 476's tax-credit rollback remain the operative pressure points instead.
|
Died in Committee — Did Not Advance | None this session; monitor for 2027 re-introduction | 2026-01-28 |
| Pennsylvania (Governor / DEP) | Executive Order 2026-05 |
In plain EnglishPennsylvania's fast permitting lane is now conditional: bring new, increasingly clean, in-zone generation and sign a consent order, or wait until every local and water permit is already secured. Sell-side read it as largely foreclosing contracts that simply resell existing IPP fleet output to PJM data centers, though Talen's legacy Susquehanna-Amazon arrangement appears unaffected.
|
Executed — DEP Implementation Pending (review process to be developed) | PA DEP to develop and stand up the two-track permitting review process and the consent order and agreement template; firm clean energy obligation for signatories begins at 10% on Jan. 1, 2027 Jan 1, 2027 |
2026-08-18 |
| Delaware PSC | 25-0826 |
In plain EnglishDelaware is one of the very few jurisdictions that has actually stopped connecting new large loads outright rather than just repricing them. If you are underwriting anything in Delmarva Power territory in Delaware, the queue is closed to new large loads until the PSC finishes this tariff, and no end date has been set. That makes Delaware materially more restrictive than a typical cost-allocation tariff state.
|
Open — Hearing Examiner Appointed; Interconnection Pause In Effect | Hearing Examiner process to develop large-load tariff for Delmarva customers ≥25 MW; interconnection pause remains in effect until a tariff is established. No decision date set. | 2026-04-01 |
| TVA (federal — self-regulated) | TVA Board action — no docket # (TVA sets its own rates; not state-PUC jurisdictional) |
In plain EnglishThe Tennessee Valley is now a priced market for large load. TVA is federal and sets its own rates, so there is no state commission docket to intervene in and no litigation path of the kind you get in Florida or Colorado — the Board voted and it is done. The 5 MW threshold is unusually low compared with the 50 MW line FERC and most RTOs use, so it captures far more projects than a typical large-load tariff.
|
Approved — Board Action Aug. 20, 2026; Effective Oct. 1, 2026 | Rate takes effect Oct. 1, 2026; ~10% overall billing increase phased across three fiscal years. Monitor local power company (LPC) pass-through implementation. Oct 1, 2026 (past) |
2026-08-20 |
| New Mexico PRC | Large-load rate design working group — no docket # yet |
In plain EnglishNew Mexico is early — the rules are being written, not litigated. That means a developer siting there now faces genuine terms risk: the tariff that ultimately applies could carry minimum-revenue and exit-fee provisions that do not exist today.
|
Pre-Filing — Working Group Announced | PRC to convene a working group on large-customer rate structures; PNM has signalled it will file a large-load tariff (minimum revenue requirements, exit fees, ratepayer protections) later in 2026. Two additional utility filings expected. | 2026-07-14 |
| Alabama Legislature | AL SB 270 |
In plain EnglishAlabama already prices large customers separately. This bill would add a second hurdle — a data center would have to be shown to benefit ratepayers statewide, not just cover its own costs, which is a meaningfully higher bar than most states apply.
|
Introduced | Monitor for committee action / carryover into the next Alabama regular session. No hearing scheduled in public sources. | 2026-02-20 |
| Alabama PSC | Docket 33709 |
In plain EnglishAlabama is building a contract-approval conveyor belt rather than a published tariff. The 60-day deemed-approval clock is the feature that matters: if adopted as proposed, an Alabama Power large-load contract becomes effective by default unless the Commission affirmatively steps in. That is materially faster and less transparent than a contested tariff proceeding — good for speed to energization, but it means the terms live in confidential contracts rather than a public tariff you can underwrite against.
|
Open — Generic Proceeding Established July 8, 2026; Public Comment and Reply Round | Commission action on comments and adoption of final review procedures. Public comment and reply schedule posted by the APSC; no order date set. | 2026-08-27 |
| Kansas KCC | 25-EKME-315-TAR |
In plain EnglishKansas is one of the cleanest resolved templates in the country and worth using as a benchmark. Note the threshold is 75 MW — higher than the 50 MW line most states use — so mid-scale campuses fall outside it entirely. The economics are demanding but knowable: 80% minimum bill on contract demand, two years of collateral, and a 12-to-17 year commitment. Because it settled unanimously with both the Data Center Coalition and Google at the table, it is a useful read on what hyperscalers will actually sign.
|
Order Issued — Unanimous Settlement Approved Nov 6, 2025; Tariff In Effect | None pending. Tariff is operative; monitor for compliance filings, threshold revisions, or any successor docket extending LLPS terms. | 2025-11-06 |
| San Antonio, TX (City Council) | Council Consideration Request (Galvan) — Universal Development Code amendments; no ordinance # yet |
In plain EnglishTexas's second-largest city said no to a pause and may still end up harder to build in. A 90-day moratorium expires on its own; Special Use Authorization does not — it converts every new San Antonio data center into a discretionary council vote, which is worse for schedule certainty than a temporary freeze. Watch Oct. 15 for whether SUA and the 500-ft setback survive; industry lobbyists called 500 ft too restrictive, and activists cited Tucson's Aug. 5 ordinance at 1,000 ft from commercial and a half mile from residential as the better benchmark.
|
Moratorium Rejected Aug. 25, 2026 — UDC Amendments at Zoning Commission; Council Vote Set Oct. 15, 2026 | City Council vote on the Unified Development Code data center amendments Oct. 15, 2026. Working draft would confine data centers to intense commercial and industrial zones, prohibit development over the Edwards Aquifer Recharge Zone, and require a 500-foot setback from schools, daycares, residential areas and hospitals. Outcome of the Sept. 15 Zoning Commission meeting not separately reported as of Sept. 22, 2026. Oct 15, 2026 (past) |
2026-09-15 |
| Austin, TX (City Council) | Council resolution initiating Land Development Code amendments (Fuentes et al.) — no ordinance # yet |
In plain EnglishAustin has not frozen anything, but it has taken large data centers out of the by-right column. Above roughly 20 MW there were already no clear rules; above 75 MW there were none at all, and now any large-scale project inside city limits has to win a Council vote while the code is rewritten by a body where at least five members want hyperscale banned outright. The MW directly at stake in Austin proper is small — 10 small facilities, no hyperscale applications on file — because the real Central Texas hyperscale pipeline sits in unincorporated Travis, Williamson and Hays county land beyond city zoning reach. Treat this as a precedent and county-contagion risk rather than a near-term MW cancellation, and stack it against the Aug. 3 Abbott directive, which independently gates new ERCOT interconnection approvals on a PUCT/ERCOT audit. Watch the phased ordinance drafts: the first package, targeted for end of 2026, is where a hard MW cap or a hyperscale prohibition would first become enforceable text.
|
LDC Amendment Process Initiated Aug 27, 2026 — No Moratorium; Interim Council-Approval Gate | City staff to return phased draft Land Development Code amendments to Council; first phase targeted by end of 2026, full process potentially into spring 2027. Interim: large-scale data center projects within city limits require Council approval before proceeding. Dec 31, 2026 |
2026-08-27 |
| Elkhart, IN (City Council) | City ordinance — number not published in available reporting |
In plain EnglishElkhart's council unanimously stopped taking new data center and battery-storage applications inside the city until the end of 2027 while it studies impacts and writes rules. Only the city is covered — a developer can still go to the county. No ordinance number appears in the available reporting, so none is asserted here.
|
Adopted — Effective | City completes impact studies (electrical capacity, water, public safety, traffic, noise, environment) and drafts permanent development standards before the pause lapses. Dec 31, 2027 |
2026-08-27 |
| Montana PSC | Large New Load Service Tariff Rule No. 24 — docket # not identified in public sources |
In plain EnglishMontana's biggest utility asked regulators in March to approve special rules for any new customer over 5 MW, which in practice means data centers. Those customers would have to sign 15-year contracts. Separately, Montana law says the utility cannot actually serve a big new customer until the commission specifically finds it will not hurt everyone else's rates — so even after the rules are approved, each individual data center deal needs its own approval. NorthWestern has already signed letters of intent with three developers, one of them over 1,000 MW.
|
Filed (Mar. 31, 2026) — Pending Commission Review; Public Comment Taken Mid-2026 | Await MPSC order on the LNL Rule. Note the statutory gate: under Mont. Code Ann. § 69-8-201 NorthWestern may not serve a large new load customer until the Commission determines service will not adversely affect other customers long-term — so each large load contract requires affirmative Commission sign-off independent of the tariff's approval. | 2026-08-31 |
| Mississippi PSC | 2025-UN-112 |
In plain EnglishMississippi regulators have an open case on how much data centers should pay for the power they use, opened in February. Mississippi matters here because of the very large projects announced in the state, and consumer advocates have argued households are quietly picking up part of the tab. This is a newly-added jurisdiction for us — the details are thin and worth confirming directly against the commission's docket system.
|
Open — Filed Feb. 27, 2026 | Monitor for Commission order and for any Entergy Mississippi / Mississippi Power large-load tariff compliance filings arising from the docket. | 2026-08-31 |
| Nebraska (Governor / DED / DWEE) | Executive Order 26-17 |
In plain EnglishNebraska's governor signed an executive order in July that cuts off the state's main tax break for data centers and sets up a task force on water and power. It is an executive order, not a law, and it is not a construction ban — the governor said that outright. Local governments can still approve projects; they just will not carry state tax rebates. A state senator plans to turn it into legislation in 2027.
|
Signed — In Effect (July 21, 2026) | DWEE to stand up the data center task force (no statutory deadline in the order). Sen. Mike Jacobson has signaled codifying legislation for the 2027 session — monitor Nebraska Legislature introduction in January 2027. | 2026-07-21 |
| Maryland PSC | Public Conference 72 (PC72) |
In plain EnglishBefore Maryland can charge data centers under a special rate class, it has to define who counts as one. PC72 is that argument. Whether the trigger is a load-factor test or an aggregate-demand test decides how many projects get pulled in — including whether several smaller sites under one owner get added together.
|
Open — Definitional Phase | Commission to settle the working definitions of 'load factor' and 'aggregate demand' that will determine which customers fall inside Maryland's large-load rate schedules; utilities are separately required to create new large-load rate schedules subject to PSC approval. | 2026-08-31 |
| Maryland General Assembly | SB 992 (2026RS) |
In plain EnglishMaryland wants data centers to sign in at the door: register with the PSC before you interconnect, and accept a demand response obligation. In exchange the bill waives the certificate-of-need process in some cases — a real speed benefit. The unresolved fight between the two chambers was the load-factor threshold, which is just a way of arguing about how many projects get caught. Verify enactment before relying on this.
|
Passed Senate; went to conference committee to reconcile with House version — final disposition not confirmed in the public sources reviewed | Confirm final enactment status and, if enacted, track the PSC's Jan. 1, 2027 statutory deadline to establish the large-load registration process by order or regulation. Jan 1, 2027 |
2026-04-13 |
| Arkansas PSC | 26-001-U |
In plain EnglishArkansas is the clearest example of a utility building the whole regulatory stack around one hyperscale customer: a special contract to lock the load in, a solar deal, a gas plant, and then a rate case to pay for all of it. This is the rate case. The political friction is that the Google contract terms are confidential while ratepayers are being asked to absorb an increase.
|
Open — Pending | Await APSC action on the formula rate plan; contested at a July 29, 2026 public hearing over the rate increase and the confidentiality of the Google data center arrangements. | 2026-07-29 |
| Arkansas PSC | 25-055-P |
In plain EnglishThis is the contract that makes the customer's promise enforceable. It matters because Entergy is using it to justify building new generation — regulators generally will not approve a power plant for a load that can walk away.
|
Open / Recently Acted — status not individually confirmed in this sweep | Confirm current APSC status; this is the docket that establishes whether the anchor large load is real and contractually binding, and therefore underpins the generation dockets 25-054-U and 25-047-U. | 2026-07-29 |
| South Dakota Legislature | SB 232 (2026) |
In plain EnglishSouth Dakota looked at a statewide pause on the biggest data centers and said no — but only because it decided that call belongs to towns and counties, not the state. That is not a green light; see SB 135.
|
Dead — Tabled in Senate State Affairs (Feb. 18, 2026) | None this session — monitor for reintroduction in 2027. | 2026-02-18 |
| South Dakota Legislature | SB 135 (2026) |
In plain EnglishInstead of a statewide pause, South Dakota locked in the right of every town and county to impose its own. For a developer this is worse than a single statewide rule, not better — it means the fight happens in every jurisdiction separately, with no state preemption to appeal to.
|
Enacted | Monitor South Dakota municipal and county moratorium activity, which this law expressly protects from state preemption. | 2026-03-01 |
| Wyoming PSC | MDU High Density Contracted Demand Response Tariff — docket # not identified in public sources |
In plain EnglishWyoming set its large-load trigger at 10 megawatts, far lower than most states, and it did not create a special rate — it created a curtailment contract. If you have 10 MW of dense compute at 85% load factor in MDU territory, you sign an agreement to be dialed back. Small-market states are converging on demand response as the price of entry.
|
Approved | Confirm the Wyoming PSC docket number and effective date; track first contracts executed under the tariff. | 2026-08-31 |
| FERC | EL26-101-000 |
In plain EnglishFERC ruled for PJM. Oklo's 750 MW Virginia project stays out of this study round, but Oklo can refile or use the fast-track lane.
|
Order Issued — Complaint Rejected (Sept. 24, 2026) | Rehearing requests are due within 30 days of the order (by about Oct. 26, 2026). Otherwise Oklo may resubmit in the next cycle or use the Expedited Interconnection Track (open to Dec. 31, 2027). Oct 26, 2026 |
2026-09-24 |
| FERC | Accession 20260828-5278 — ER docket # not yet reported |
In plain EnglishMISO did file its large-load rulebook — ramp limits, ride-through, monitoring — and wants it live Dec. 4. Data centers get their own category so the strict rules don't hit ordinary factories.
|
Pending — filed Aug. 28, 2026; awaiting FERC order on requested Dec. 4 effective date | FERC order accepting, conditioning, setting for hearing, or rejecting the filing ahead of MISO's requested Dec. 4, 2026 effective date Dec 4, 2026 |
2026-08-28 |
| California Legislature | AB 2383 / SB 886 / SB 1168 / AB 2469 / AB 1577 / AB 2619 / SB 887 |
In plain EnglishCalifornia's legislature passed two bills making data centers cover their own power costs. Newsom has until the end of September to sign or veto them. As of Sept. 8 there are three such bills, not two. The newest, SB 1168, passed with no votes against it and is aimed specifically at who pays for the wires. Whatever the governor signs, the utility commission still has to decide what it actually means. UPDATE: he signed them -- all three, plus four more on water disclosure and environmental review. Seven laws total. The utility commission still has to write the actual rates.
|
Signed into law Sept. 21, 2026 -- seven-bill package enacted; CPUC implementation pending | CPUC implementation of the large-load cost-allocation and special-rate directives, routed into R.26-04-009; chapter numbers and operative dates to be confirmed | 2026-09-21 |
| Interior Board of Land Appeals (IBLA) | Townsite Solar 2 BLM ROW appeal — IBLA docket # not reported |
In plain EnglishA federal appeals judge froze a data center BLM had approved on public land by recycling an old solar project's environmental review. Swapping a solar farm for a data center isn't the same project.
|
Stay granted — project halted pending merits review | IBLA merits decision on whether BLM's reuse of the 2023 solar NEPA analysis for a data center was arbitrary and capricious; no scheduled date announced | 2026-09-01 |
| Michigan City, IN (Common Council) | Data center moratorium ordinance — first reading Sept. 1, 2026 (ordinance # not reported) |
In plain EnglishMichigan City took a first vote toward pausing new data centers. The real vote is Sept. 15; Google's project already under construction should be exempt.
|
Tabled 8-1 at Second Reading — Referred Back Through the Plan Commission | Council members to draft a resolution directing the city's planning department on what regulations to develop; no new vote date set. A separate proposal to add a data center district to the zoning ordinance is pending. | 2026-09-15 |
| Eureka, CA (City Council) | Bill No. 1061-C.S. (urgency ordinance) |
In plain EnglishEureka banned new data centers immediately for 45 days while it writes zoning rules. Because the ban also covers the coastal zone, the permanent rules will need state Coastal Commission sign-off too -- which takes a while, so expect the city to keep extending the temporary ban.
|
Adopted and in force -- interim urgency ordinance, effective on adoption Sept. 1, 2026 | Staff to return with proposed permanent zoning standards and regulations for data centers; council action to extend the interim ordinance under California Government Code section 65858 required before the ~Oct. 16, 2026 lapse if standards are not yet adopted. Coastal-zone provisions will additionally require California Coastal Commission certification of any permanent local coastal program amendment. Oct 16, 2026 — TODAY |
2026-09-01 |
| Mattoon, IL (City Council) | One-year data center moratorium resolution — ordinance/resolution # not reported |
In plain EnglishMattoon paused any data center bigger than about half an acre for a year, out to 1.5 miles past the city line. Unusually, the pause renews itself each year unless the council votes to end it, so the default is that it stays. Existing operations can keep running.
|
Adopted and in force — one-year term, renews annually absent affirmative council action | Annual auto-renewal absent an affirmative Council vote to modify or terminate; watch for adoption of permanent zoning standards in the interim. Sep 2, 2027 |
2026-09-02 |
| Miamisburg, OH (City Council) | Nine-month data center moratorium — ordinance # not reported |
In plain EnglishMiamisburg stopped new data centers for nine months, 6-0. The trigger was a possible facility at the old Hutchings coal plant site, which developers like because the grid connection is already built. The city wants zoning rules written first.
|
Adopted and in force — nine-month term | City to evaluate impacts and adopt zoning rules and development standards before expiry; watch for permanent standards or extension. Jun 1, 2027 |
2026-09-01 |
| Mendocino County, CA (Board of Supervisors) | 45-day data center urgency ordinance — ordinance # not reported |
In plain EnglishMendocino County's supervisors blocked new data centers across unincorporated parts of the county immediately, for 45 days. It's the first California county — rather than city — to do this, and these pauses are usually extended rather than allowed to expire.
|
Adopted and in force — interim urgency ordinance, effective on adoption Sept. 1, 2026 | Board consideration of an extension under California Government Code section 65858 (extendable to a cumulative two years) or lapse; staff to develop permanent standards. Oct 16, 2026 — TODAY |
2026-09-01 |
| Lake County, IL (County Board) | Eight-month unincorporated-area data center moratorium — text amendment to Lake County Code of Ordinances (reported Ch. 151); ordinance # not reported |
In plain EnglishLake County, north of Chicago, voted Tuesday to stop taking data center proposals in the areas it zones directly, starting immediately and running to May 2027. It also wrote a definition of 'data center' into county code for the first time, which is what it needs before it can set real rules. Cities and villages inside the county can still approve projects.
|
Adopted Sept. 8, 2026 — in force immediately; runs to May 2027 (reported May 11, 2027) or until permanent regulations adopted | County staff development of permanent data center development restrictions during the moratorium term; moratorium expiry or early lift on adoption of permanent regulations. May 11, 2027 |
2026-09-08 |
| Trenton, OH (City Council / Butler County Board of Elections) | Citizen-initiated charter amendment — Nov. 3, 2026 ballot (emergency ordinance, no. not reported) |
In plain EnglishTrenton residents gathered enough signatures to force a public vote on banning data centers over 25 MW. The council refused to put it on the ballot; the Ohio Supreme Court ordered it to. Voters decide Nov. 3. If it passes it goes into the city charter, so a future council cannot simply repeal it.
|
On the ballot — council certified by emergency ordinance Sept. 3, 2026 after adverse Ohio Supreme Court ruling | Municipal election — voters decide the charter amendment Nov 3, 2026 |
2026-09-03 |
| Gallatin, TN (City Council) | Data center construction moratorium ordinance (shortened from 12 months to 6 at the Sept. 15, 2026 meeting) — ordinance number not reported |
In plain EnglishThey agreed unanimously to move the year-long pause forward but did not actually pass it. The shorter July pause is what's still in force.
|
Amended at Sept. 15, 2026 Meeting — Shortened From 12 Months to 6; Readings Continuing | Both the data center and companion apartment moratorium ordinances were shortened from one year to six months at the Sept. 15, 2026 council meeting; the apartment ordinance passed first reading. Final outcome of the data center ordinance's readings not yet publicly reported as of Sept. 17, 2026 — confirm at the next council meeting. | 2026-09-16 |
| Festus, MO (City Council) | Annexation ordinances — three Highway 67 parcels, CRG campus (ordinance nos. not reported) |
In plain EnglishMost local news in this tracker is towns blocking data centers. Festus is the opposite — it keeps annexing land to make a huge campus possible, and it rushed this vote to beat a new state law that would have limited annexations. Voters threw out every incumbent over this project in April, and the replacement council approved it anyway.
|
Approved — annexation adopted Sept. 3, 2026; no site plans filed; opposition litigation pending | CRG site plan submission and rezoning/permitting; Crystal City suit over the new Jefferson County annexation statute proceeds. Council's Sept. 14 meeting was cancelled for lack of quorum, so next procedural steps are unscheduled. | 2026-09-03 |
| PJM (Members Committee / Board of Managers) | FERC-directed governance reform package — Stakeholder/Members Committee process, no docket # yet |
In plain EnglishFERC told PJM to change how it is governed — a more independent board, more say for states, more transparency. PJM puts that package to a membership vote on Sept. 24. It sounds procedural, but the board is what decides the big large-load and capacity questions, so who sits on it matters.
|
Open — Sept. 24 Members Committee held (Board election completed); governance-package outcome not yet published; FERC end-of-September deadline | Confirm the Members Committee vote result. FERC has said it will impose reforms if PJM does not agree by end of September. Sep 30, 2026 (past) |
2026-09-24 |
| Charlotte, NC (City Council) | 150-day data center moratorium (adopted June 2026) — extension item, ordinance # not reported |
In plain EnglishCharlotte's data center pause runs out Nov. 5. Staff want it extended — reportedly by nine months, but that number isn't nailed down. Council decides Sept. 14.
|
Extension Item Before Full Council — Sept. 14, 2026 Vote Outcome Not Yet Verified | Verify the Sept. 14, 2026 full-council vote on staff's requested nine-month extension (for air-pollution monitoring and noise-limit work). The existing 150-day moratorium expires in early November 2026; absent an extension it lapses. Nov 1, 2026 |
2026-09-14 |
| Burgin, KY (City Council) | Ordinance to rejoin the joint Mercer County / Harrodsburg / Burgin Planning and Zoning Commission — first reading Sept. 8, 2026 (ordinance # not reported) |
In plain EnglishBurgin left the county zoning body, which is why it could annex land for a data center the county moratorium would otherwise block. It just voted — barely, on the mayor's tiebreaker — to start rejoining. One more vote to go.
|
Advanced on First Reading Sept. 8, 2026 (mayor's tie-breaking vote) — Not in Force Pending Second Reading | Second reading and final adoption vote (date not reported) | 2026-09-08 |
| New Hampshire (Governor / Legislature) | Proposed statewide data center moratorium — budget vehicle, no bill number assigned yet |
In plain EnglishNew Hampshire's governor said she's against any data center in the state and wants a multi-year ban — but she's putting it in next year's budget, so nothing is blocked yet.
|
Announced Sept. 2, 2026 — Not Filed; No Enforceable Restriction in Effect | Introduction of the governor's budget containing the moratorium proposal; earliest effective date approximately July 2027 Jul 1, 2027 |
2026-09-02 |
| Kokomo, IN (Common Council) | Amended data center zoning ordinance — ordinance # not reported (moratorium expressly declined) |
In plain EnglishKokomo is the counter-example on this map: instead of pausing data centers, its council turned down a moratorium and is loosening zoning to allow them on industrial land. Final vote Sept. 14.
|
Second Reading Held Sept. 14, 2026 — Final Adoption Outcome Not Yet Verified | Verify the Sept. 14, 2026 second-reading/final adoption vote. The amendment would make data centers a permitted use on all industrial sites with a 200-ft setback from residential districts and 300-ft separation from any existing home; it adds no noise or utility-use restrictions. Advanced 6-2 on first reading Aug. 24, 2026 (Plough, Stephenson opposed). | 2026-09-14 |
| Woodford County, KY (Fiscal Court) | Permanent countywide data center prohibition — ordinance # not reported |
In plain EnglishA Kentucky horse county banned data centers permanently, and got both of its cities to pass the same ban so there is no way around it.
|
Closed — Ordinance Adopted (Permanent Ban) | None — permanent prohibition in force. Monitor only for legal challenge or repeal. | 2026-09-08 |
| Levy County, FL (Board of County Commissioners) | Ordinance 2026-05 |
In plain EnglishA Florida county stopped taking data center applications for three years while it studies whether it has enough water and power.
|
Closed — Ordinance Adopted; Moratorium In Force | Staff study and regulatory recommendations due to the Board by August 2027, or a status report if regulations are not ready. Aug 31, 2027 |
2026-09-10 |
| Christiansburg, VA (Town Council) | Zoning text amendment — conditional use permit requirement for data centers; ordinance # not reported |
In plain EnglishA Virginia town made every data center need a special permit and a public hearing instead of being approved automatically.
|
Closed — Adopted 6-0 | Council to revisit data center definitions at a later meeting; CUP requirement remains in force in the interim. | 2026-09-10 |
| Imperial County Superior Court (CA) | Imperial County Superior Court — CEQA writ proceeding; case number not reported |
In plain EnglishA California judge cancelled a county's approval of a huge data center because the county skipped the environmental study the law requires.
|
Order Issued — Approval Vacated; Environmental Review Ordered | Developer has stated intent to appeal; county must conduct CEQA review before any re-approval. Appellate filing deadline not reported. | 2026-09-09 |
| Eugene, OR (City / Land Use) | Use determination — former Hynix site, E-1 Campus Employment zoning; case number not reported |
In plain EnglishEugene said a data center is not the kind of employer its zoning was written for, so the project cannot be built there. The buyer can appeal to a state board.
|
Denied — Appealable to Oregon LUBA; Broader Moratorium Request Deferred to December | Eugene residents packed the Sept. 15, 2026 hearing urging a city-wide moratorium beyond the Hynix site. Mayor Kaarin Knudson said the E-1 zoning determination stands and does not wait on December. Council revisits data center land-use policy — including possible code amendments — Dec. 14, 2026. Dec 14, 2026 |
2026-09-16 |
| Clinton Township, PA (Board of Supervisors) | Lindy Corporation land development application — 20-building data center campus; application # not reported |
In plain EnglishA Pennsylvania township rejected a 20-building campus because its own engineer said the plan was not sound and the application was incomplete.
|
Denied — Revised Application Possible | Attorneys to meet with the applicant within 15 days of the vote to review deficiencies; a revised submission remains possible. Sep 25, 2026 (past) |
2026-09-10 |
| Lancaster County, NE (County Board) | Data center impact task forces — moratorium declined; no ordinance or docket # |
In plain EnglishNebraska's Lancaster County considered pausing data centers, decided against it, and set up study groups instead.
|
Moratorium Declined — Study Task Forces Formed | Task force findings and any resulting zoning recommendations; no date announced. | 2026-09-10 |
| Lubbock, TX (City Council) | Non-binding resolution directing staff to develop large-scale data center standards; resolution # not reported |
In plain EnglishLubbock has started the moratorium clock, but nothing is blocked until two hearings are held, likely around December.
|
Moratorium Procedure Initiated 5-2 (Sept. 22) — Two Public Hearings Required Before Effect | Two public hearings, then adoption of the 90-day moratorium (about 90 days before effect; one 90-day extension allowed). Hearing dates not reported. | 2026-09-22 |
| Heath & Johnstown, OH (Licking County Board of Elections) | Municipal charter amendments banning facilities above 25 MW — special election petitions; no case # assigned |
In plain EnglishTwo Ohio towns missed the November ballot deadline for data center limits, so residents are trying to force special elections instead.
|
Pending — Petition/Special Election Process | Johnstown council expected to approve a special-election ordinance; Heath petitioners must restart their signature drive. Board of Elections requires special elections 60–120 days after approval, implying a vote between roughly Nov. 2026 and Jan. 2027. Oct 31, 2026 |
2026-09-10 |
| Ferguson, MO (City Council) | Emerson campus data center redevelopment — bond/abatement ordinance, ordinance # not reported |
In plain EnglishFerguson's council said yes, 4-3, to the Emerson campus data center deal: up to $1.5 billion in tax breaks and $22 billion in bonds authorized, with up to 300 MW of data center capacity possible.
|
Approved 4-3 by City Council (Sept. 23, 2026) | None pending at council level; incentive and bond documentation to be finalized between the city and Next Revolution Technologies LLC. No further council vote currently scheduled. | 2026-09-23 |
| PJM (Planning Committee / FERC) | Large Load Ride Through — PC stakeholder process; FERC docket not yet assigned (compliance track for EL26-67-000) |
In plain EnglishPJM wants to require big data centers to stay plugged in during grid disturbances instead of switching to their own backup generators, because 4,000 MW dropping off at once destabilizes the system for everyone else.
|
Open — Proposal Introduced at Planning Committee; FERC Filing Targeted November 2026 | PC Special Session — Large Load Ride Through Education, Sept. 15, 2026; PJM filing at FERC targeted for November 2026 (month only stated). Outcome of the scheduled 2026-09-15 action not yet publicly reported as of Sept. 17, 2026 — carried forward for confirmation. Sep 15, 2026 (past) |
2026-09-10 |
| FERC (Office of Energy Projects) | DeepGreen Western Passage SPV preliminary permit — P-docket number not reported in public coverage |
In plain EnglishFederal regulators gave a developer permission to study building a data center underwater off the Maine coast. The town has banned data centers locally and residents are trying to get formal standing in the federal case.
|
Accepted — Preliminary Permit Application Accepted Aug. 19, 2026; Intervention Sought | Resident coalition ECHO is seeking intervenor status in the FERC permitting process; Eastport is separately considering citizen-initiated ordinances and has an existing 180-day local moratorium. | 2026-09-08 |
| Pinal County, AZ (Board of Supervisors) | Vermaland 3,300-acre data center campus rezoning — case number not reported |
In plain EnglishA developer cut its huge data center plan by more than 80 percent and Pinal County supervisors rejected it anyway, 4-1.
|
Denied 4-1 | None scheduled. Developer response not reported; Arizona officials remain divided on a statewide pause. | 2026-09-08 |
| Escambia County, FL (Board of County Commissioners) | 12-month moratorium on 10–50 MW data centers — ordinance # not yet assigned |
In plain EnglishEscambia County is writing a pause for medium-sized data centers — the size band that most state and local rules miss entirely.
|
Hearings Being Scheduled — Not Yet Adopted | Public hearings tentatively Oct. 1 and Oct. 15, 2026. Oct 1, 2026 (past) |
2026-09-08 |
| Orange County, FL (Board of County Commissioners) | Proposed one-year moratorium on AI data center applications — no ordinance # yet |
In plain EnglishCommissioners backed a pause in concept but enacted nothing on Sept. 15 — this is a direction to staff, not an ordinance. Orange County remains open through at least early December. The framing stays water rather than power, and SB 484 (signed earlier in 2026) left this to local governments rather than preempting it, which is why Florida is being fought county by county.
|
Direction to Staff Sept. 15, 2026 — No Ordinance Adopted; Possible December Return | Staff study of zoning districts, electric load, water and noise; item could return to the commission in early December 2026. Moratorium length to be set by the study timeline. Dec 1, 2026 |
2026-09-16 |
| Springhill Township, PA (Board of Supervisors) | Interim ban plus two pending data center / power-plant ordinances — ordinance #s not reported |
In plain EnglishThe township froze new applications right away so nothing could be filed while it finishes writing the real setback and noise rules nine days later.
|
Adopted — Data Center and Power-Generation Ordinances Unanimously Approved | Ordinances in force; watch for conditional-use applications in the heavy and light industrial districts. A separate noise-and-dust ordinance was approved Sept. 7, 2026. | 2026-09-17 |
| Grant County, NM (Board of County Commissioners) | Proposed one-year data center moratorium modeled on Socorro County ordinance — no ordinance # yet |
In plain EnglishResidents found out about a huge gas-powered data center from a legal notice. Because it would make its own power, it never shows up in grid interconnection data at all.
|
Notice of Intent Approved — Binding Vote Oct. 8, 2026 | Commission vote on the one-year moratorium ordinance. Oct 8, 2026 (past) |
2026-09-24 |
| Jasper County, SC (County Council) | Temporary moratorium on data centers, crypto mining and data processing — ordinance # not reported |
In plain EnglishJasper County took the first of several votes needed to pause new data centers. It is not law yet.
|
Passed Second Reading Sept. 21, 2026 — Third Reading Pending (pending-ordinance doctrine applies) | Third and final reading at the next council meeting (date not reported). | 2026-09-21 |
| Mount Pleasant, SC (Town Council) | Proposed 120-day data center moratorium — no ordinance # yet |
In plain EnglishMount Pleasant wants a short pause to fix a gap in its zoning rules that would otherwise let very large data centers into light industrial areas.
|
Proposed — Debate Scheduled | Council debate on the 120-day moratorium; specific date not reported. | 2026-09-08 |
| Fort Wayne, IN (Common Council) | One-year data center pause and nine-member large-development commission — ordinance # not reported |
In plain EnglishA Fort Wayne councilwoman wants a one-year pause and a study commission. The backlash is over Google's campus, which is already built and running.
|
Held for Amendments — Vote Rescheduled | Council takes up the amended one-year moratorium ordinance. Oct 13, 2026 (past) |
2026-09-22 |
| Rock County, WI (County Board) | Five data center resolutions including a 13-member advisory committee and an NDA policy — resolution #s not reported |
In plain EnglishRock County is considering rules about data center secrecy and non-disclosure agreements, not just the usual water and noise limits.
|
Advanced to County Board — Staff Committee Recommended 6-3 | County Board consideration of the five resolutions; date not reported. | 2026-09-09 |
| Gorham, ME (Town Council / Planning Board) | Proposed permanent data center ban — referred to planning board; ordinance # not reported |
In plain EnglishGorham's temporary pause is being converted into a permanent ban, now heading to the planning board.
|
Referred to Planning Board for Public Hearing | Planning board public hearing on the proposed permanent ban; date not reported. | 2026-09-08 |
| Raritan Township, NJ (Township Committee / Planning Board) | Ordinance No. 26-32 |
In plain EnglishRaritan rewrote its data center ban so it does not accidentally outlaw ordinary office server closets.
|
Adopted — Data Centers Prohibited in All Zoning Districts | Ban in force via amendment to the township Land Development Code. Accessory server rooms remain permitted at up to 10% of floor space or 2,000 sq ft, whichever is less. | 2026-09-15 |
| Zeeland Township, MI (Township Board) | One-year data center and energy facility moratorium (repeal and replace) — ordinance # not reported |
In plain EnglishThe township cancelled its old pause and passed a fresh one-year pause the same night, this time covering power plants too.
|
Adopted — In Force | Master plan update; moratorium runs one year from adoption. Sep 7, 2027 |
2026-09-07 |
| Kearney, NE (City Council) | Project Horizon 368 MW data center expansion and accompanying regulations — ordinance # not reported |
In plain EnglishKearney wrote ten pages of water and noise rules first, then approved a 368 MW data center under them.
|
Approved — Regulations Adopted First | Construction and compliance with the newly adopted water-efficiency and noise regulations; sound-deafening walls committed by the developer. | 2026-09-09 |
| Weld County, CO (Board of County Commissioners) | Global AI data center construction permit — permit # not reported |
In plain EnglishWeld County approved what will be Colorado's biggest data center, while other counties are pausing.
|
Approved | Verify megawatt sizing, interconnection posture and utility service arrangement against county records before use in sizing analysis — not available in initial reporting. | 2026-09-11 |
| Fort Madison, IA (City Council / Planning & Zoning Commission) | 'High Infrastructure Impact Development' ordinance — under development, no ordinance # yet |
In plain EnglishFort Madison wants rules where the more power and water a facility needs, the more review it has to go through.
|
Under Development | Planning & Zoning Commission continues developing the ordinance; no date reported. | 2026-09-08 |
| Connecticut (Governor's Office) | Gubernatorial policy statement — no bill, executive order or PURA docket |
In plain EnglishConnecticut's governor said big AI data centers do not belong in the state. It is an opinion, not a law or an order — nothing has been filed anywhere.
|
Stated Executive Posture — No Legal Instrument | None. No executive order, bill or PURA proceeding has been initiated. Watch the 2027 legislative session and any PURA docket opening. | 2026-09-07 |
| Statesville, NC (City Council) | 180-day data center moratorium — ordinance # not reported (second reading Sept. 14, 2026) |
In plain EnglishA third Charlotte-region city has paused data centers, and this council made the pause longer than staff asked for. Statesville sits on I-77 in Iredell County, directly in the path of Charlotte-area spillover while Charlotte's own moratorium runs.
|
Adopted — In Force Sept. 14, 2026 | Land-use study and text amendments during the 180-day window; council action required to extend or replace before expiry. Mar 13, 2027 |
2026-09-14 |
| Memphis, TN (City Council) | 12-month data center permit moratorium — ordinance # not reported (third reading Sept. 15, 2026) |
In plain EnglishNo moratorium is in force in Memphis. The final vote slipped three weeks and the ordinance is being rewritten to aim at hyperscale campuses, which means the version that passes may be narrower than the citywide freeze originally noticed — and TVA's new data center rate class takes effect Oct. 1, before the council votes.
|
Vote Halted Oct. 6 Amid Disruption — Rescheduled to Oct. 20, 2026 | Council vote on the moratorium ordinance rescheduled to Oct. 20, 2026. Oct 20, 2026 |
2026-10-06 |
| Richmond, CA (City Council) | 45-day urgency data center moratorium — ordinance # not yet assigned |
In plain EnglishAdopted on the four-fifths urgency vote and in force immediately. A staff amendment lets the city keep accepting and processing applications during the pause — it just cannot approve them or issue permits — so queue position is preserved but nothing moves. Richmond is the Bay Area's third moratorium city after Oakley and Gilroy. Expect extension, not expiry: these ordinances are almost always stretched toward the 22-month-15-day statutory ceiling.
|
Adopted Sept. 15, 2026 — 45-Day Urgency Moratorium In Force | Extension hearing expected before the 45 days lapse (~Oct. 30, 2026); California urgency ordinances are extendable by up to 22 months and 15 days. Oct 30, 2026 |
2026-09-16 |
| Bemidji, MN (Planning Board / City Council) | One-year data center moratorium — ordinance # not yet assigned |
In plain EnglishThe 10,000 sq ft trigger is unusually low — Minneapolis used 350,000 sq ft. At that threshold the pause functions as a total ban on any data center of any size. And because the Planning Board is made up of council members, the 6-1 vote is a strong read on where the full council lands.
|
Advanced 6-1 by Planning Board — Full Council Vote Not Yet Scheduled | Full Bemidji City Council vote on adoption; date not yet announced. | 2026-09-14 |
| Tennessee General Assembly | HB 1847 (Data Center Cost Responsibility Act) |
In plain EnglishTennessee put cost-responsibility in statute but rejected the transparency piece — data centers must pay their own way, but nobody has to report how much power or water they actually use. That gap is part of why Memphis is legislating locally.
|
Enacted — Signed by Gov. Bill Lee, May 2026 | Implementation by Tennessee utilities and TVA local power companies; no further legislative action pending. A companion registration/reporting bill (SB 1682 / HB 2061) failed in committee March 2026. | 2026-05-01 |
| San Francisco, CA (Board of Supervisors) | 45-day interim zoning moratorium urgency ordinance — file/ordinance # not yet reported |
In plain EnglishThe unusual feature is scope: this reaches power-capacity expansions at buildings that already exist, not just new construction. In a built-out urban market like San Francisco, capacity uprates at existing colo space are the main growth path, so this closes the usual workaround. It is introduced, not adopted.
|
Adopted — Board of Supervisors approved 45-day moratorium unanimously Oct. 6, 2026 (per SFist) | Planning Commission study; possible extension up to 22 months 15 days. | 2026-10-06 |
| Hayward, CA (City Council) | Legislative referral — zoning code amendment to prohibit data centers; no ordinance # yet |
In plain EnglishHayward is skipping the temporary-pause step and going straight at a permanent zoning prohibition. Nothing is prohibited yet — a referral only starts the drafting — but a city that already added a conditional-use hurdle in April is not a favorable jurisdiction.
|
Legislative Referral Heard Sept. 15, 2026 — Staff Drafting if Majority-Backed | If a council majority backed the referral, staff prepares a zoning code amendment or ordinance prohibiting data center development and returns it for council action at a later date. | 2026-09-15 |
| Elgin, IL (City Council) | One-year data center moratorium — ordinance # not yet assigned |
In plain EnglishA pre-emptive moratorium in a city with zero pipeline — this is the pattern to watch in the Chicago collar counties, where jurisdictions are closing themselves off before a developer ever approaches. Not yet final.
|
Preliminary Approval (Unanimous) — Final Adoption Vote Pending | Final city council adoption vote at a future meeting (date not announced). | 2026-09-15 |
| Manatee County, FL (Board of County Commissioners) | Ordinance 26-42 — 12-month data center / large-load moratorium |
In plain EnglishThe drafting language is the thing to note — it is written around utility burden, not around the words 'data center,' so relabeling a project as something else will not avoid it. Two hearings left before it is in force.
|
Adopted — one-year moratorium approved unanimously (reported Oct. 8, 2026) | Moratorium in effect for one year; ordinance number/effective date to be confirmed. | 2026-10-08 |
| Texas Water Development Board (TWDB) / Governor | Gubernatorial directive on major water user survey enforcement — no docket # (agency directive) |
In plain EnglishTexas found a non-electric chokepoint. A campus that skipped its water survey can be locked out of TCEQ permits, which most large sites need. Add 'did the operator file its TWDB major-water-user survey' to Texas site diligence.
|
Directive Issued Sept. 14, 2026 — Agency Compliance Report Due Oct. 14, 2026 | TWDB compliance and enforcement update due to Gov. Abbott by Oct. 14, 2026, including referrals to county/district attorneys and notification to TCEQ of permit-ineligible non-filers. Oct 14, 2026 (past) |
2026-09-14 |
| Woodburn, OR (City Council) | 120-day data center moratorium — ordinance/resolution # not reported |
In plain EnglishA pre-emptive four-month freeze in a city with zero applications on file. It is use-specific — other industrial development continues — so the binding constraint is the replacement zoning ordinance due in January, not the pause.
|
Adopted Unanimously Sept. 14, 2026 — In Force | City staff to update zoning rules, utility/infrastructure requirements and location criteria within the 120-day window; moratorium lapses ~Jan. 12, 2027 absent extension or a replacement ordinance. Jan 12, 2027 |
2026-09-14 |
| Raleigh, NC (City Council) | Draft six-month data center moratorium — ordinance number not yet assigned |
In plain EnglishRaleigh was the last large Triangle city without a pause. Six months is short and the 10,000 sq ft floor exempts the small facilities already operating, so this is a rule-writing window rather than a hard freeze — but combined with Cary (18 months), Durham County (nine) and Charlotte, it closes the region to new merchant entitlement.
|
Approved Oct. 6, 2026 (7-1) — Six-Month Moratorium, Expires April 6, 2027 | Council to rewrite development rules on noise, water, air and light pollution during the pause. Apr 6, 2027 |
2026-10-06 |
| Cary, NC (Town Council) | 18-month data center moratorium ordinance — ordinance number not reported in sources reviewed |
In plain EnglishThe longest pause in the Raleigh-Durham region and the binding one. Because nothing was pending, no queue was grandfathered — any Cary project now starts after February 2028 at the earliest. The 1 MW exemption is the template other jurisdictions are copying to avoid freezing ordinary office and hospital IT.
|
Adopted Unanimously Aug. 27, 2026 — In Force | Periodic staff progress reports to council during the moratorium; permanent ordinance decision expected February 2028. Feb 1, 2028 |
2026-08-27 |
| Leon County, FL (Board of County Commissioners) | 18-month large-scale data center moratorium ordinance — ordinance number not yet assigned |
In plain EnglishFlorida's third county to move in a week, after Manatee and Orange. Eighteen months is long by national standards and the September 2027 staff deadline effectively sets the real duration. The hurricane-damage exemption is the one opening a developer could try to use inside the window.
|
Advanced Unanimously Sept. 15, 2026 — Final Adoption Vote Pending | Final adoption vote Oct. 13, 2026; staff findings and recommended regulations due back September 2027. Oct 13, 2026 (past) |
2026-09-16 |
| Marysville, KS (City Council) | 12-month data center moratorium ordinance — ordinance number not reported in sources reviewed |
In plain EnglishSmall city, but it extends the moratorium wave into a state with essentially no prior local activity and no hyperscale pipeline. The drafting follows the emerging national template: broad definition, incidental-server-room carve-out, one year to write rules.
|
Adopted Unanimously — In Force | Planning Commission review of citizen concerns and zoning code amendments during the 12-month window. | 2026-09-16 |
| Santa Cruz County, CA (Board of Supervisors) | Proposed voter-approval requirement for AI data centers — measure rejected, no ordinance number assigned |
In plain EnglishThe first local vote in weeks to go the developers' way, but the structure matters: a ballot requirement would not expire the way a moratorium does. If the sponsor takes it to a citizen initiative, the result would be far harder to unwind than the urgency ordinances neighboring California jurisdictions have adopted.
|
Rejected — Study Session Directed; Ballot Petition Threatened | Board study session on data center impacts before any regulation is drafted; Supervisor Justin Cummings said he may pursue a citizen petition to place the requirement on the ballot. No date set. | 2026-09-16 |
| Riverside, CA (City Council) | AI ad hoc committee (13-month term) alongside Land Use Committee 90-day data center moratorium — no ordinance number reported |
In plain EnglishThe committee outlives the moratorium by more than four times, which tells you the 90-day pause is not the end state. Riverside is a tight Southern California load pocket, so the permanent framework this produces matters beyond the city line.
|
Committee Established Sept. 15, 2026 — Moratorium In Force | Monthly ad hoc committee meetings over a 13-month term producing citywide AI and data center policy recommendations; the 90-day Land Use Committee moratorium lapses well before the committee reports. | 2026-09-16 |
| Colorado Springs, CO (City Council) | Project Taurus planning approval appeals — five appeals of the June 2026 Planning Department approval; no docket # assigned |
In plain EnglishColorado's biggest data center siting fight is frozen for seven months and lands one week after the city election — whoever wins decides it.
|
Open — Postponed 7-2 to April 13, 2027 | Council decision on the five appeals, rescheduled to the April 13, 2027 council meeting — one week after the April 6, 2027 municipal election. Power and sound studies to be completed in the interim. Apr 13, 2027 |
2026-09-17 |
| Massena, NY (Town Board) | Proposed six-month data center moratorium — local law # not assigned (rejected) |
In plain EnglishMassena's board rejected a pause 3-2, so the 400 MW project at the old Alcoa site keeps moving — a rare local win for a developer this month.
|
Rejected — Failed 3-2 on Sept. 17, 2026 | None scheduled on the moratorium itself. A residents' petition drive and the town's parallel zoning-code review remain open and could reintroduce restrictions. | 2026-09-17 |
| Gary, IN (Office of the Mayor) | Mayoral executive order — one-year data center moratorium; EO number not reported |
In plain EnglishGary's mayor paused data centers for a year by his own order, and drew the line around the city's utilities rather than the city limits.
|
In Force — Executive Order Signed Sept. 17, 2026 | City study of grid, water, infrastructure and economic-development impacts during the one-year pause; Common Council could codify or displace the order by ordinance. Sep 17, 2027 |
2026-09-17 |
| Virginia (Office of the Governor / Office of the Chief Energy Officer, DEQ, Virginia Energy, VEDP) | Executive Order 22 (2026) — Virginia Data Center Accountability Framework; agency rulemakings not yet assigned case numbers |
In plain EnglishVirginia's governor signed an executive order that, starting immediately, cuts every new 25 MW-and-up data center out of the state's site-readiness and fast-track permitting programs, and stops state agencies from signing secrecy agreements about proposed projects. It does NOT pause construction and does NOT change local zoning — the by-right repeal and the local NDA ban are bills the legislature has to pass starting January 2027. Read this as added timeline and friction on new Virginia siting, plus a series of DEQ rulemakings on noise, cooling water and diesel backup generators arriving through 2027 that will tighten permitting for projects not yet through.
|
Executed — self-executing directives in force; implementing rulemakings and legislative package pending | Office of the Chief Energy Officer to publish the Data Center Planning and Community Engagement Toolkit within 120 days (approx. Jan. 16, 2027); DEQ 180-day deliverables on noise rulemaking, cooling water scarcity area criteria and backup-generation cumulative impacts (approx. Mar. 17, 2027); Virginia Energy 240-day siting recommendations (approx. May 16, 2027); VA-LEAD criteria by end of CY2027. Separately, the by-right elimination above 25 MW and local NDA ban go to the General Assembly session convening January 2027. Jan 16, 2027 |
2026-09-18 |
| Spartanburg County, SC (County Council) | Countywide 12-month data center moratorium ordinance — ordinance # not reported |
In plain EnglishThe pause is law. The amendments matter more than the pause: nothing above 65 MW for a year, no bringing your own generation, and new projects confined to industrial parks or brownfields. Anything the county already approved proceeds unaffected.
|
Enacted — Passed Third and Final Reading 5-1 (Sept. 21, 2026), Amended | Moratorium in effect for 12 months from adoption. County to develop permanent data center regulations during the pause. Ordinance number and precise expiry date not yet published; watch for the adopted ordinance text to confirm the 65 MW threshold language and grandfathering scope. | 2026-09-21 |
| St. Joseph County, IN (County Council) | Resolution banning new hyperscale data centers — resolution # not reported |
In plain EnglishSouth Bend's county council is voting on a permanent ban — not a pause — on new hyperscale data centers, and a majority has already said publicly it will vote yes. Two hyperscaler builds already in the ground would be grandfathered. This is a materially harder action than the 45-day urgency ordinances driving most of the national moratorium count, and it sits inside MISO Zone 6. UPDATE Sept. 22: the resolution passed 6-3 (Hess, Catanzarite, Schaetlze opposed), but it is a directive to draft a ban, not the ban itself.
|
Resolution Adopted 6-3 (Sept. 22, 2026) — Area Plan Commission Drafting Ban Ordinance | Area Plan Commission drafts zoning amendments and definitions, including treatment of existing projects; ordinance expected back before full council within ~60 days for the binding vote. Nov 21, 2026 |
2026-09-22 |
| Evansville, IN (City Council / Area Plan Commission) | 180-day data center moratorium ordinance — ordinance # not yet assigned |
In plain EnglishEvansville is the latest Indiana city to start a moratorium clock. Nothing is in force yet — this is the first of the required council readings.
|
First Reading Held Sept. 28, 2026 — Second Reading in October | Second reading before the City Council in October 2026 (date not reported). | 2026-09-28 |
| Pennsylvania PUC | M-2026-3064961 (emergency electric load control regulations rulemaking) |
In plain EnglishPennsylvania regulators are writing down, in binding regulation, who gets curtailed first when PJM runs short of power — and separately opening the question of who pays for the grid upgrades large data centers require. For siting decisions in PJM's western half, these two proceedings matter more than any local moratorium headline. Watch the Oct. 1 meeting for the draft.
|
Open — Tentative Order Approved Oct. 1, 2026; Comment Period Pending PA Bulletin Publication | Initial comments due 30 days after Pennsylvania Bulletin publication; reply comments 15 days later; Final Order anticipated at Jan. 28, 2027 public meeting. Fall technical conference on large-load cost responsibility date not yet announced. Jan 28, 2027 |
2026-10-01 |
| Nevada (Office of the Governor / GOED) | Executive Order 2026-005 |
In plain EnglishNevada attached a price to its data center tax break instead of banning anything. Pay school tax in full, sign a binding community commitment on water, cost of service and emergency grid behavior, or your abatement application does not reach the board. Projects underwritten on a full abatement need repricing. Because it is an executive order, a future governor or the Legislature can reverse it.
|
Issued — In Effect (signed and effective Sept. 18, 2026) | Nevada Community Support Commitment to be established by the GOED executive director in consultation with the State Engineer, the PUCN, state agencies, local governments and school districts (no deadline stated). Responsible Speed to Power Plan due from the Director of the Office of Energy to the Governor by Dec. 31, 2026. Dec 31, 2026 |
2026-09-18 |
| Laurens County, SC (County Council) | Ordinance #1012 |
In plain EnglishA second upstate South Carolina county paused for a year, a week ahead of Spartanburg. It covers county land only — the two city governments inside the county can still approve projects, which is the only near-term path into Laurens County.
|
Enacted — Passed Third and Final Reading 6-0 (Sept. 14, 2026) | Moratorium runs 12 months from adoption. County to use the period to develop data center regulations addressing water use, electricity demand and environmental impact. Precise expiry date not published. | 2026-09-14 |
| Baltimore County, MD (County Council) | Moratorium extension bill — bill # not reported |
In plain EnglishThe one metro-scale moratorium in the Baltimore region just got another full year. Anything sited in Baltimore County is dead until 2028 at the earliest. Underwriting should treat the county as closed, not paused.
|
Enacted — Extension Passed 7-0 (Sept. 22, 2026) | Moratorium runs through Dec. 31, 2027. Dec 31, 2027 |
2026-09-22 |
| Salem, OR (City Council) | 120-day data center moratorium — ordinance # not reported |
In plain EnglishSalem finished what it started in August. The pause is short (to Jan. 19) but it catches the project that prompted it: the city attorney says Verrus is frozen too. Watch December, when the task force reports and council decides whether to extend.
|
Enacted — Final Approval Sept. 21, 2026; Expires Jan. 19, 2027 | Data Center Task Force recommendations to council in December; possible ~6-month extension decision. Dec 15, 2026 |
2026-09-22 |
| Galesburg, IL (City Council) | 180-day data center moratorium — ordinance # not reported |
In plain EnglishPre-emptive: no application pending. Closes Galesburg through early April 2027.
|
Enacted — Passed Unanimously Sept. 21, 2026; Expires Apr. 3, 2027 | City to draft regulations; a limit or ban may follow. Apr 3, 2027 |
2026-09-21 |
| Normal, IL (Town Council) | Data center moratorium extension — ordinance # not reported |
In plain EnglishBloomington-Normal stays closed into mid-2027.
|
Enacted — Extension Passed 6-1 (Sept. 21, 2026) | Moratorium runs through May 31, 2027. May 31, 2027 |
2026-09-21 |
| Denton, TX (City Council) | Proposed 90-day data center moratorium + development code updates — ordinance # not yet assigned |
In plain EnglishTexas law makes moratoria hard: it needs a supermajority, and the council split 4-3 to proceed. Public support is lopsided, but the math on the council is the real test in December.
|
Public Hearings Underway — First Held Sept. 22, 2026 | Second public hearing; final council consideration expected early December (supermajority required under Texas HB 2559). Oct 27, 2026 |
2026-09-22 |
| Texas Commission on Environmental Quality (TCEQ) / Governor | Gubernatorial directive letter to TCEQ Executive Director — no docket # (agency directive) |
In plain EnglishSelf-generation no longer gets a project around the Texas audit, because the plant needs a TCEQ permit and TCEQ has been told to issue none.
|
Directive Issued Sept. 21, 2026 — In Effect; Compliance Update Due Oct. 19 | TCEQ compliance update to the Office of the Governor. Oct 19, 2026 |
2026-09-21 |
| Chicago, IL (City Council / Mayor) | Mayoral 12-month data center moratorium ordinance — ordinance # not reported |
In plain EnglishThe largest-city moratorium proposal in the country has been introduced, but it has already stalled procedurally.
|
Introduced Sept. 23, 2026 — Committee Referral Delayed by Parliamentary Maneuver | Committee referral and consideration; competing Conway regulate-now ordinance also pending. No date reported. | 2026-09-23 |
| Pima County, AZ (Board of Supervisors) | 120-day data center moratorium resolution — resolution # not reported |
In plain EnglishThe Tucson area has paused new data centers for four months. It does not reach the one already being built.
|
Adopted 3-2 (Sept. 22, 2026) — In Effect 120 Days | Draft zoning code text due; the board will consider extending the moratorium. Dec 15, 2026 |
2026-09-22 |
| Kershaw County, SC (County Council) | One-year data center / crypto mining moratorium ordinance — ordinance # not reported |
In plain EnglishKershaw County, S.C. is closed to new data centers for one year.
|
Adopted — Third Reading Unanimous (Sept. 22, 2026) | County study and development of regulations during the one-year pause. | 2026-09-22 |
| North Port, FL (City Commission) | 18-month data center moratorium ordinance — ordinance # not reported |
In plain EnglishNorth Port is paused for 18 months except for the one live project, which the commission can still reject.
|
Adopted 3-2 (Sept. 22, 2026) | Staff to study and draft data center land-development rules. Deep Park (~896,000 sq ft) application proceeds to review but needs commission approval. | 2026-09-22 |
| Massachusetts (Governor / EEA / state permitting agencies) | Executive Order No. 658 |
In plain EnglishIn Massachusetts, the host town decides first, and big projects must bring their own clean power or pay ratepayers back.
|
In Effect — Signed Sept. 8, 2026 | Agency implementation of the framework and design of the Ratepayer Protection Fund; watch for municipal responses such as the Boston zoning ban proposal. | 2026-09-08 |
| St. Bernard, OH (Village Council) | 12-month data center moratorium — ordinance # not reported |
In plain EnglishThe village has paused new data centers for a year, but the one project already filed still gets heard.
|
Adopted — In Effect Sept. 24, 2026 | BZA conditional-use hearing on the CAI Investments Ivorydale application (date not reported). | 2026-09-24 |
| Woodbury, MN (City Council) | Interim Ordinance — study and moratorium on data centers and high-volume public infrastructure users (ordinance # not reported) |
In plain EnglishNew data centers and expansions are frozen for up to a year in this Twin Cities suburb.
|
Adopted — In Effect (up to 1 year) | City study of water, power, noise and zoning, followed by possible permanent regulations. | 2026-09-23 |
| Marshall County, IA (Board of Supervisors) | Six-month moratorium resolution — resolution # not reported |
In plain EnglishApplications are paused while the county writes rules, and the pause can be extended.
|
Adopted — In Effect (6 months, extendable) | Monthly zoning commission work sessions on a permanent ordinance. | 2026-09-23 |
| Tulare County, CA (Board of Supervisors) | Urgency data center moratorium extension — ordinance # not reported |
In plain EnglishThe pause now runs close to a year while permanent rules are drafted.
|
Extended — In Effect (~10 months) | Staff recommendations on permanent zoning (CUP, standards, or ban). | 2026-09-22 |
| Pulaski County, AR (Quorum Court) | High-density digital infrastructure ordinance — ordinance # not reported |
In plain EnglishThe rules have passed but are not in force until the county judge signs them.
|
Vetoed by County Judge Sept. 25, 2026 — Override Vote Expected | Quorum Court override vote at the next regular meeting (9 of 15 needed; the ordinance passed 11-4). Oct 27, 2026 |
2026-09-25 |
| Boston, MA (City Council) | Order regarding a text amendment to the Boston Zoning Code to prohibit data centers in all zoning districts — docket # not reported |
In plain EnglishThis is a proposal to ban new data centers anywhere in Boston. It is only filed so far.
|
Introduced — Not Adopted | Committee consideration (no date reported). | 2026-09-16 |
| Palm Beach County, FL (Board of County Commissioners) | ULDC amendment — large-scale data center definition and one-year moratorium (ordinance # not reported) |
In plain EnglishPalm Beach County has paused new hyperscale data centers for a year.
|
Adopted — Sept. 24, 2026 (unanimous) | A one-year study period, with the county leaning toward a consultant. Candidate rules: 50 MW cap, end-user disclosure, water, noise and heat limits. | 2026-09-24 |
| Prince William County, VA (Board of County Supervisors) | Zoning text amendment eliminating by-right data center use — ZTA # not reported |
In plain EnglishIn the country's No. 2 data center market, new projects outside set zones now need a public permit hearing, and a planned substation was blocked.
|
Adopted — Sept. 22, 2026 (8-0), 90-day grace period | The 90-day grace period runs, then SUPs are required outside opportunity zones. Exact end date not reported. | 2026-09-22 |
| Idaho PUC | IPC-E-26-07 |
In plain EnglishIdaho regulators are rethinking how Idaho Power prices service to new large loads such as data centers.
|
Open | Proceeding continues. Order No. 37125 (IPC-E-26-08, Aug. 11, 2026) also directed Idaho Power to open a separate docket, coordinated with this case, to re-evaluate the marginal-cost methodology behind Schedule 20 (Speculative High-Density Load). | 2026-08-11 |
| Calexico, CA (City Council) | Zoning code amendment prohibiting data centers — ordinance # not reported |
In plain EnglishCalexico has banned data centers outright.
|
Adopted — Sept. 2026 (3-0) | None; permanent zoning prohibition. | 2026-09-23 |
| Buffalo, NY (Common Council) | Proposed two-year data center ban — item # not reported |
In plain EnglishBuffalo may ban data centers for two years. The vote is Tuesday.
|
Resolution Approved Sept. 29, 2026 — Local Law Pending; Mayor Reviewing | Council consideration of a local law amending the city code (next meeting, about two weeks out). Mayor Ryan is reviewing with Corporation Counsel. Oct 13, 2026 (past) |
2026-09-29 |
| Oakland, CA (City Council) | Proposed 45-day urgency data center moratorium — item # not reported |
In plain EnglishOakland could pause data centers for 45 days.
|
Adopted — 45-day moratorium approved unanimously Oct. 6, 2026 | 45-day moratorium runs; watch for extension or permanent rules. | 2026-10-06 |
| Illinois General Assembly | Data center regulation package — Stakeholder Workgroup, no bill # yet |
In plain EnglishIllinois may pass data center cost and siting rules this fall. There is no bill yet.
|
Drafting — Legislative Working Group | Veto session Nov. 17-19 and Dec. 1-3, 2026. Nov 17, 2026 |
2026-09-25 |
| Maryland (Governor / Data Center Task Force) | Executive order signed Sept. 23, 2026 — EO number not shown in sources reviewed |
In plain EnglishMaryland's state gate for big data centers. It is not a ban, but a 'Not Aligned' grade could cut off state help.
|
Signed — In Effect; Task Force Standing Up | Task Force to publish review rules and launch the monthly Data Center Dashboard; tax-exemption repeal bill expected in the 2027 General Assembly session. | 2026-09-23 |
| Wayne County, MI (County Executive / Commission) | Project Cannoli incentive package & community benefits agreement — resolution # not reported |
In plain EnglishThe county blocked Google's tax break. Watch whether the commission tries to override.
|
Vetoed by County Executive Sept. 25, 2026 | County Commission response (override attempt or revised package) not yet reported. Related MPSC U-22058 contracts still pending. | 2026-09-25 |
| Milwaukee, WI (City Plan Commission / Common Council) | One-year data center moratorium ordinance — file # not reported |
In plain EnglishTwo more votes before Milwaukee's pause takes effect.
|
Approved by City Plan Commission Sept. 28, 2026 — Not In Force | Zoning, Neighborhoods & Development Committee vote Oct. 6; Common Council Oct. 13. Oct 6, 2026 (past) |
2026-09-28 |
| Sioux County, IA (Board of Supervisors) | Amendment to County Ordinance No. 1 — data center application standards |
In plain EnglishNot a pause. It sets a high bar for data center applications in this rural Iowa county.
|
Public Hearing Sept. 29, 2026 — First Reading Pending | First reading after the Sept. 29 hearing; second reading Oct. 13; third Oct. 27. Sep 29, 2026 (past) |
2026-09-28 |
| Texas PUCT | Docket No. 60332 |
In plain EnglishThe Texas Panhandle utility's plan to make data centers pay for their own grid build-out. It is waiting on regulators.
|
Filed — Pending PUCT Review | Intervention and procedural schedule; decision expected in 2027 | 2026-09-29 |
| Saginaw, MI (City Council) | Data center zoning ordinance — ordinance # not reported |
In plain EnglishSaginaw ended its pause and now allows data centers under strict rules.
|
Adopted Sept. 28, 2026 (8-0) — Effective Oct. 9, 2026 | Ordinance takes effect Oct 9, 2026 (past) |
2026-09-28 |
Curated from primary-source dockets (PUCT Interchange, ERCOT, SCC Virginia, NY PSC, PA PUC, Ohio PUCO, Georgia PSC, FERC eLibrary, CAISO/SPP). Verify current status against the linked source before relying on it for a filing deadline.
National moratorium & construction-ban tracker — every municipal, county and state data-center pause we track. 348 currently active across 44 states; 453 total records. Source data as of 2026-09-28.
State-level policy posture — all 50 states, classified by how restrictive state-level policy currently is.
Local & state actions — sortable census of individual moratoria, bans, and failed votes.
| Jurisdiction | Level | Date | Duration | Status | Scope | Reason / notes | Source |
|---|---|---|---|---|---|---|---|
| Manatee County Florida |
County | 2026-10-08 | 12 months | Active | DC development applications + other high utility-demand facilities | Commissioners unanimously directed staff to draft moratorium ordinance over electrical, water and wastewater strain; Planning Commission Sept; board votes Sept 22 / Oct 6 | Edged research |
| Oakland California |
City | 2026-10-06 | 45 days | Active | New data centers | Full council vote Oct. 6 | Edged research |
| San Francisco California |
City | 2026-10-06 | 45 days | Active | New data centers and expansion of existing facilities | Interim zoning moratorium pending Planning Commission study; extendable to 22 months | Edged research |
| Palm Beach County Florida |
County | 2026-09-24 | 1 year | Active | New hyperscale (50 MW+) data centers | Draft regulations; water, noise, Everglades impacts | Edged research |
| Americus Georgia |
City | 2026-09-24 | 30 days | Active | Data centers | Draft ordinance amendment | Edged research |
| St. Bernard Ohio |
Village | 2026-09-24 | 12 months | Active | New data center applications (pending 24 MW Ivorydale application grandfathered) | Zoning review | Edged research |
| Woodbury Minnesota |
City | 2026-09-23 | 1 year | Active | New data centers and expansions; building, electrical, ROW permits | Water and power study | Edged research |
| Marshall County Iowa |
County | 2026-09-23 | 6 months | Active | Data center, AI computing, data mining, crypto applications | Draft county ordinance | Edged research |
| Pima County Arizona |
County | 2026-09-22 | 120 days | Active | New data centers where site-improvement permits have not been submitted | Pause while zoning code text is drafted (closed-loop cooling, noise, design standards; draft due Dec. 15); adopted 3-2; Project Blue (under construction) outside scope, Project Gravel contested | Edged research |
| Prince William County Virginia |
County | 2026-09-22 | — | Restrictions Added | By-right data center use eliminated countywide; SUP required outside opportunity zones (90-day grace) | Land use, grid/substation impacts | Edged research |
| Calexico California |
City | 2026-09-22 | — | Permanent Ban | Zoning code prohibits data centers | Began as a moratorium proposal in June | Edged research |
| North Mankato Minnesota |
City | 2026-09-22 | 1 year | Active | Data centers | Study | Edged research |
| Zionsville Indiana |
Town | 2026-09-22 | 1 year | Active | Data centers, solar, wind, battery storage | No permitted category in zoning code | Edged research |
| Fayette County Ohio |
County | 2026-09-22 | ~8 months | Active | Data centers in seven townships | Township requests; zoning gaps | Edged research |
| Kershaw County South Carolina |
County | 2026-09-22 | 1 year | Active | Data centers, crypto mining, data processing | Study | Edged research |
| Raton New Mexico |
City | 2026-09-22 | — | Rejected | Commission rejected 3-2 | Edged research | |
| Buffalo New York |
City | 2026-09-22 | 2 years | Proposed | Data centers | Council vote Sept. 29 | Edged research |
| Texas (statewide — Governor directive to TCEQ) Texas |
— | 2026-09-21 | Until ERCOT/PUCT and TWDB audits complete | Active | All TCEQ permits sought by data center projects; other state agency approvals also held | Gov. Abbott directive letter (not an EO) extending the Aug. 3 ERCOT interconnection audit gate to environmental permits; TCEQ compliance update due Oct. 19 | Edged research |
| Galesburg Illinois |
City | 2026-09-21 | 180 days | Active | New data center permits (to Apr. 3, 2027) | Await state legislation | Edged research |
| Raleigh North Carolina |
City | 2026-09-16 | 6 months | Proposed | New data centers larger than 10,000 square feet | Review of land, water and electricity demands; public hearing and possible vote Oct. 6, 2026 | Edged research |
| Santa Cruz County California |
— | 2026-09-16 | — | Rejected | Board rejected a proposed voter-approval requirement for AI data centers, directing a study session instead; sponsor may pursue a ballot petition | Edged research | |
| Beaufort County North Carolina |
County | 2026-09-14 | 1 year (proposed) | Proposed | Accepting, processing or approving applications for data center developments county-wide | Board of Commissioners held an informal public hearing Sept. 14, 2026 but postponed the vote; the final public hearing, board discussion and official vote are now set for Oct. 5, 2026. County officials say no data center is currently planned and the pause would give time to consider how to address future development | Edged research — WITN / WCTI |
| Johnstown Ohio |
City | 2026-09-10 | Permanent ban on the Jan 5, 2027 special election ballot | Proposed | Charter amendment barring data centers with combined monthly demand above 25 MW from any energy source | Grassroots petition drive over energy demand and land use: residents gathered signatures (133 of 180 validated) but council could not muster a quorum in the two-day window after certification, missing the Nov. 3 ballot, so at a special meeting it set a January special election at roughly $15,000 cost; mirrors the 25 MW template used in other Ohio communities | The Reporting Project |
| Escambia County (moratorium) Florida |
— | 2026-09-10 | — | Rejected | Commission took no action on hearings for a 12-month moratorium on mid-sized (10-50 MW) data centers after the county attorney advised the Land Development Code and August ordinance already ban them outright; a moratorium was seen as weakening the existing ban | NorthEscambia.com | |
| Boone County (IA) Iowa |
County | 2026-09-09 | Up to 1 year | Active | Establishment, construction or permitting of new data centers in Boone County, Iowa | Board of Supervisors adopted a pause of up to one year to give county leaders time to study impacts and put data center ordinances in place; distinct from Boone County, Indiana, which adopted its own one-year moratorium June 15, 2026 | Edged research — We Are Iowa |
| Lake County (IL) Illinois |
County | 2026-09-08 | 8 months (extendable by 4 months) | Active | New data center applications and development in unincorporated Lake County; the approved T5 campus in Grayslake is municipal and unaffected | Water, energy, land use, noise and infrastructure, plus the absence of any data center definition in the county code: the board formalized June's administrative deferral into an ordinance after more than 1,200 public comments and two hours of testimony driven by backlash to the Grayslake campus; grassroots pressure converted into official action | Daily Herald |
| Foley Alabama |
City | 2026-09-08 | 6 months | Active | Applications for data centers, Bitcoin and cryptocurrency mining facilities, server farms and similar technically-oriented uses | Proactive Baldwin County pause adopted on final reading Sept. 8, 2026 with no data center proposed in the Foley area; the city will study water resources, air pollution and noise impacts and review outcomes in other Alabama cities before writing ordinances and guidelines | Edged research — WKRG / Gulf Coast Media |
| Woodford County Kentucky |
County | 2026-09-08 | Permanent | Permanent Ban | All data centers county-wide; the same ordinance also bans landfills and large battery energy storage systems | Farmland and rural land use: the Fiscal Court chose an outright ban over a moratorium after hearing near-universal resident opposition, citing preservation of Thoroughbred horse farms, historic agriculture and a finite land supply, and pointing to the divisive hyperscale fight in nearby Burgin as what it wanted to avoid; grassroots-driven sentiment, enacted proactively by officials | Kentucky Lantern |
| Levy County Florida |
County | 2026-09-08 | ~12 months (effective Oct 1, 2026) | Active | Data centers, large-scale data centers and large load customer facilities in unincorporated areas; telecom, public safety and previously approved projects exempt | Electricity and water demand on a county wholly dependent on the Floridan Aquifer, plus noise, vibration, lighting, heat, construction traffic, roads and emergency services; commissioners directed staff in June to draft the pause (official-led) against a backdrop of a resident petition, with a water and infrastructure study due back by Aug. 2027 | Citrus County Chronicle |
| Putnam County (FL) Florida |
County | 2026-09-08 | ~1 year | Active | Medium-scale (2,000-5,000 servers, 5-49 MW) and large-scale (50 MW or more monthly peak load) data centers | Energy and infrastructure scale: commissioners first adopted a definition of medium- and large-scale data centers, then paused them so the county can write zoning and land use rules; a reversal of the board's July decision to rely on a 72-hour disclosure policy instead of a pause, after continued resident pressure | Palatka Daily News |
| Christiansburg Virginia |
Town | 2026-09-08 | Permanent regulations | Restrictions Added | All data center proposals; ends by-right approval in general industrial zones | Zoning and land use, energy demand and ratepayer bill impacts: staff-recommended zoning text amendment requiring a conditional use permit for every data center, citing JLARC findings on construction impacts, limited long-term jobs and incompatibility near homes; official-led, and no pause is in effect, though the mayor said it could slow applications to a halt | Cardinal News |
| Jasper County South Carolina |
County | 2026-09-08 | 1 year (first reading; two more readings required) | In Process | New applications, permits, rezonings and incentives for data centers, cryptocurrency mining and data-processing facilities in unincorporated areas | Water, electricity, noise and environmental impacts, plus a zoning gap that currently permits data centers in several commercial and industrial districts; official-led and explicitly pre-emptive, with strong resident support for preserving the county's rural character, and the pending ordinance doctrine adopted alongside to stop a rush of filings | WTOC |
| Gallatin Tennessee |
City | 2026-09-08 | 12 months (advanced; formal vote pending) | In Process | New data centers city-wide; follows a 60-day application pause adopted July 28, 2026 | Noise complaints from neighbors of the Meta campus and water and electric utility impacts, plus the need to distinguish server closets and edge facilities from hyperscale projects in the zoning code; council-led with resident support, after the planning commission recommended the pause 5-2 | FOX 17 (WZTV) |
| Fort Wayne Indiana |
City | 2026-09-08 | 1 year (introduced; substantive vote pending) | Proposed | Council actions supporting data centers: rezonings, annexations, property sales, contracts and tax abatements; city planning staff work and the existing Google campus are unaffected | Public health, environmental, infrastructure and resource demands raised by residents of the southeast-side district that hosts the Google campus; a councilwoman's ordinance pairs the pause with a nine-member Community Infrastructure and Environmental Review Commission, and a rival task-force proposal was withdrawn in its favor | Journal Gazette |
| Grant County New Mexico |
County | 2026-09-08 | 1 year (proposed; commission consideration Sept 24, 2026) | Proposed | Large data centers county-wide; the disclosed project is 32 natural gas engines totaling about 300 MW near Hachita and Playas | Air quality, emissions, water and energy, compounded by secrecy: residents only learned of the gas-fired project through an air-permit legal notice in the local paper, and a commissioner responded by proposing a pause modeled on Socorro County's ordinance; grassroots-triggered, with the state environment secretary also criticizing the developer's minimal community engagement | Santa Fe New Mexican |
| Fort Madison Iowa |
City | 2026-09-08 | Permanent regulations (in drafting) | Exploring | A tiered 'High Infrastructure Impact Development' framework keyed to electricity, water, wastewater, road and emergency-service demand, with annual projected-versus-actual usage reporting | Infrastructure capacity, water and energy: council directed the planning and zoning commission to keep developing an impact-based ordinance rather than a pause, deliberately written around infrastructure demand rather than naming the industry, while the city separately weighs extraterritorial zoning up to two miles out; official-led following a public input process on AI data centers. No moratorium is in effect | The Hawk Eye |
| Orange County (FL) Florida |
County | 2026-09-05 | 1 year (proposed; commission discussion Sept 15, 2026) | Proposed | New AI data center applications county-wide; the land development code has no data center language, so they are implicitly allowed under industrial zoning | Water and energy: the vice mayor's report cites a projected 96-million-gallon-per-day groundwater shortfall by 2045 for a utility wholly dependent on groundwater, plus AI facility power draw comparable to 100,000 homes and up to 5 million gallons of water a day, and the land footprint of typical campuses; official-led, framed as a timeout to write zoning rules rather than an anti-business measure | WKMG ClickOrlando |
| Heath Ohio |
— | 2026-09-04 | — | Rejected | City rejected citizen petitions for a 25 MW data center ban charter amendment over signature validity and refused a refile before the Sept. 4 ballot deadline; organizers say 276 of 220 required signatures were verified and must now restart the drive | The Reporting Project | |
| Mattoon Illinois |
City | 2026-09-03 | 1 year (auto-renewing annually) | Active | New data centers over 21,780 sq ft, citywide plus 1.5-mile extraterritorial zoning jurisdiction | City Council voted 5-0 to pause large-scale data center development while zoning standards are developed. Renews annually by default; affirmative Council action required to modify or terminate. Existing operations may continue. | Edged research |
| Fresno California |
City | 2026-09-03 | 10-year ban (directed, text amendment pending) | In Process | Citywide prohibition on data centers including AI facilities; would apply to land now in the city and to future annexations | Water and electricity consumption for very few jobs, argued by Mayor Jerry Dyer and Councilmember Richardson; official-led, with council directing staff to draft and define a 10-year prohibition in the Development Code and a parallel push to make data center nondisclosure agreements public | GV Wire |
| Trenton Ohio |
City | 2026-09-03 | Permanent ban on the Nov 3, 2026 ballot | Proposed | Charter amendment banning construction of new data centers city-wide | Grassroots petition drive: five residents circulated a charter-amendment petition over land use and utility concerns, council rejected their signature count, and the Ohio Supreme Court ruled unanimously on Sept. 1 that voters must decide, after which council passed an emergency ordinance placing it on the ballot | Journal-News |
| Springhill Township Pennsylvania |
Township | 2026-09-03 | Stopgap until the Sept 17, 2026 meeting; superseded by adopted ordinances Sept 17, 2026 | Active | New data center and fossil-fuel power plant applications township-wide; only 52 parcels are zoned heavy or light industrial. UPDATE (Sept. 17, 2026): the Board of Supervisors unanimously adopted both detailed ordinances, making data centers and accompanying fossil-fuel power facilities conditional uses in the heavy and light industrial districts (Edged research, Herald-Standard Sept. 19, 2026) | Noise, setbacks and land use compatibility: supervisors tabled two detailed ordinances to meet state notice requirements and adopted a resolution barring any data center or power plant application in the interim so nothing could be filed in the gap; official-led drafting triggered by Nadara's land deal, with about 40 residents attending in opposition | Herald-Standard |
| Newton Falls Ohio |
Village | 2026-09-02 | 12 months | Active | All permits for data centers in the village | Regulatory and zoning gap amid Ohio's rapid data center buildout; council proactively paused permits to study what village rules should be in place, framing it as preparation rather than a stance against the industry | Tribune Chronicle |
| Raritan Township New Jersey |
Township | 2026-09-02 | Permanent ban — ADOPTED as Ordinance 26-32 (Edged research, Sept. 15, 2026) | Permanent Ban | All data centers across the township's 38 square miles; accessory server rooms inside existing buildings still permitted up to 10% of floor space or 2,000 sq ft. UPDATE: Ordinance 26-32 cleared planning board review and public hearing Sept. 15, 2026 and was adopted by the Township Committee, adding data centers to the list of prohibited uses in every zoning district (Edged research, WRNJ Radio) | Land use and industrial scale: officials withdrew an earlier ban ordinance and reintroduced it as Ordinance 26-32 after the planning board asked for an accessory server room definition, keeping data centers defined separately from warehouses and barring flex space or research buildings from conversion; official-led, following a non-binding resolution opposing data centers that attorneys said carried no legal weight | TAPinto Flemington/Raritan + Edged research (WRNJ Radio) |
| Miamisburg Ohio |
City | 2026-09-01 | 9 months | Active | All new data center development citywide | Council voted 6-0 following community concern over a proposed large-scale data center at the former DP&L Hutchings Power Station. City Manager framed it as proactive, to have zoning rules and development standards in place before an application is filed. | Edged research |
| Mendocino County California |
County | 2026-09-01 | 45 days (extendable to 2 years under Cal. Gov. Code 65858) | Active | All new data centers in the unincorporated county | Board of Supervisors voted 5-0 to adopt an interim urgency ordinance effective on adoption. First county-level use in California of the urgency-ordinance route taken by Coachella, Indio, Palm Springs and Eureka. Runs to approx. Oct. 16 unless extended. | Edged research |
| Escondido California |
City | 2026-09-01 | 45 days (extendable up to ~1 year) | Active | New AI data centers and expansions; no applications currently on file | Adopted as a public health and safety urgency ordinance to close a zoning gap: staff will develop land use and zoning regulations limiting impacts on public safety, city services, energy and water; proactive, with findings due Oct. 10 | The Coast News |
| Harpersville Alabama |
Town | 2026-09-01 | 6 months | Active | All data center development town-wide | Proactive, official-led pause adopted after learning nearby towns had already been contacted by developers; the town will hold monthly public information sessions while it studies energy, water and zoning impacts | ABC 33/40 |
| Rowan County (KY) Kentucky |
County | 2026-09-01 | 2 years | Active | Large-scale data centers county-wide | Complete regulatory gap: the judge-executive said the county has no zoning rules to review a data center if one arrived, so the Fiscal Court paused development while it builds oversight rules covering energy and water impacts | LEX18 |
| Winchester Kentucky |
City | 2026-09-01 | 1 year | Active | Data center development within city limits (does not extend to the rest of Clark County) | Commission proactively paused development to study energy, water and land use impacts and gather public input before any project is permitted | LEX18 |
| Port Angeles Washington |
City | 2026-09-01 | 6 months (directed, not yet adopted) | In Process | New data center applications city-wide; the former McKinley Paper mill site is zoned heavy industrial | Electric rates, water use, industrial land supply, noise and environmental quality; council directed staff to draft a moratorium to close a filing window before new rules take effect, with Planning Commission and Utility Advisory Committee input | Peninsula Daily News |
| Michigan City Indiana |
City | 2026-09-01 | TBD | Exploring | Future data centers; the Google-backed $832M 'Project Maize' would be exempt | Residents raised air quality, chemical and health impacts and said the existing project was approved without adequate research; grassroots pressure prompted the Common Council to discuss pausing future development | ABC57 |
| West Hempfield Township Pennsylvania |
Township | 2026-09-01 | Permanent regulations | Restrictions Added | Data centers; limits on facility size and proximity to residential and agricultural land | Land use compatibility near homes and farmland after strong resident pressure; supervisors adopted permanent zoning limits on size and setbacks, with noise and water amendments still before the planning commission. No pause is in effect | WGAL |
| Indiantown Florida |
— | 2026-09-01 | — | Rejected | Village Council voted 4-1 against a moratorium on hyperscale data center applications, saying it wanted new legal counsel to draft language that could survive a court challenge; the council then fired the village manager and removed the village attorney the same night as residents pressed for safeguards on 'Project Growler' and 'Project Beskar' | CBS12 | |
| Zeeland Charter Township Michigan |
Township | 2026-09-01 | 1 year | Active | Data centers and energy facilities township-wide; no application pending | Zoning and local control: the board repealed its earlier data-center-only moratorium and adopted a broader one covering energy facilities so it can finish updating the master plan and renewable energy ordinance, explicitly to defend local planning authority against state preemption under PA 233; official-led, reinforced by organized resident opposition to the neighboring solar project | FOX 17 (WXMI) |
| Mount Pleasant South Carolina |
Town | 2026-08-31 | 120 days (proposed) | Proposed | All data centers; would redefine 'data center' so small in-building server rooms are excluded | Groundwater capacity-use area limits and water supply, energy demand, noise and closing a by-right zoning loophole; Planning Committee recommended the pause to the full council | Post and Courier |
| North Port Florida |
City | 2026-08-31 | 18 months (proposed, retroactive) | In Process | 896,000 sq ft of buildings within a 282-acre 'Deep Park' development | Water contamination and supply, air quality, land impacts and noise, with no data center standards in the land development code; hundreds of residents in 'No Data Centers' shirts spoke over a six-hour hearing | WINK News |
| Jefferson Texas |
City | 2026-08-31 | Resolution (no permit pause) | Exploring | All data center development inside city limits | Resolution opposing data centers citing utility systems, infrastructure and community character; residents warned of water use and ecosystem disruption, and the council called for further impact studies | Marshall News Messenger |
| Forest Park Georgia |
City | 2026-08-31 | 90 days | Active | All new data centers (previously permitted by right) | Zoning and land use gap: by-right approval let a data center be built with no review, so council paused to define the use, set residential buffers and add accountability provisions; an advisory committee will gather public input while staff draft the rules | Clayton News-Daily |
| Mead Colorado |
Town | 2026-08-31 | 12 months | Active | New data center applications town-wide | Water use, infrastructure capacity and setbacks; proactive, official-led pause so staff can study impacts and draft zoning regulations before applications are accepted, and it can end early if the review finishes sooner | Berthoud Weekly Surveyor |
| Savannah Georgia |
City | 2026-08-27 | 155 days | Active | Data centers 10 MW or greater; conversion of industrial/warehouse buildings 200,000 sq ft or larger | Study water, wastewater and stormwater capacity, electric grid load, roads and noise; city zoning code has no data center standards; mayor-led proactive pause before large projects arrive | The Current GA / WTOC |
| Lancaster County Nebraska |
County | 2026-08-27 | 12 months (proposed) | Proposed | Data centers in areas under county jurisdiction (excludes incorporated cities and villages) | Water and electricity usage and a complete zoning gap, plus impacts on natural resources and resident well-being; introduced by Commissioner Schulte after constituent complaints from southern Lancaster County | KLIN |
| New Jersey (statewide proposal) New Jersey |
— | 2026-08-27 | — | Rejected | Gov. Mikie Sherrill rejected calls for a statewide moratorium, saying municipalities already have authority to impose local restrictions, and instead signed a data center transparency law requiring semiannual electricity and water reporting to the BPU for three years. Thirty-eight NJ municipalities have banned data centers locally. | parsippanyfocus.com | |
| Cary North Carolina |
Town | 2026-08-27 | 18 months | Active | All data center development (approvals, rezonings, development plans, building permits); exempts enterprise/co-located equipment under 1 MW | Power demand and grid capacity, water consumption, noise and vibration, site design and buffering | WRAL |
| Coachella California |
City | 2026-08-26 | Permanent (Ordinance 1231) | Permanent Ban | All data centers in every zoning district (accessory server rooms exempt) | Strained electric infrastructure, water supply, noise, public health and safety and loss of employment land for few permanent jobs; months of resident organizing framed the project as an environmental-justice sacrifice zone; second California city to ban data centers | KVCR / NPR |
| Palm Springs California |
City | 2026-08-26 | 45 days (urgency ordinance) | Active | All data center applications, permits and entitlements citywide | Electricity and water demand and desert cooling loads; council-led urgency ordinance during the citywide zoning update, following pauses in Desert Hot Springs, Indio and Coachella | KESQ |
| Orangetown New York |
Town | 2026-08-25 | 180 days | Active | Data storage facilities and battery energy storage systems town-wide (applications filed before July 1, 2026 exempt) | Emissions, water usage and proximity to the Lake Tappan drinking water reservoir and wildlife habitat, plus a zoning code gap; residents protested outside Town Hall over the DataBank carve-out | News 12 Hudson Valley / Westfair |
| Garfield Township Michigan |
Township | 2026-08-25 | 12 months (extendable to 18) | Active | All data centers and cryptocurrency mining facilities, including small-scale | Water use and quality, energy use, noise and infrastructure strain; residents packed July zoning meetings and sent voluminous comment; first moratorium issued under a new formal process built to survive legal challenge | The Ticker / Michigan Advance |
| Jackson Township (NJ) New Jersey |
Township | 2026-08-25 | Permanent | Permanent Ban | All data centers township-wide (no size threshold) | Electric grid and clean water strain plus protection of the Pinelands National Reserve; CRAN-organized residents backed Councilman Pollak's ordinance; 38th New Jersey municipality to ban data centers | Jersey Shore Online / Insider NJ |
| Lubbock Texas |
City | 2026-08-25 | 18 months (sought) | In Process | High water use and high energy use data centers; underlying project ~27 MW on ~100 acres | Water use, grid load and secrecy around the land deals; a roughly 3,000-signature citizen petition from Citizens of Lubbock Against Data Centers was verified sufficient, triggering a Sept 8 hearing | KCBD |
| Martin County Florida |
County | 2026-08-25 | 1 year (proposed) | In Process | Hyperscale data centers county-wide | Water supply, grid infrastructure and electric rate impacts, air quality, noise, property values and rural character; residents urged the board to act before hyperscale projects advance | WQCS |
| Wixom Michigan |
— | 2026-08-25 | — | Lifted | Council repealed its six-month moratorium 7-0 (Resolution 2026-47) to coincide with a new ordinance making data centers a special land use in M-1/M-2 only, with residential setbacks, noise limits and decommissioning rules. Wixom Industrial One LLC's federal suit over the pause (filed Aug 7) remains active. | www.wixomgov.org | |
| San Antonio Texas |
City | 2026-08-25 | 90 days (sought); no vote scheduled | Exploring | Concept plans, site development plans and permits for data centers and office data processing facilities | Water and aquifer protection, energy demand and land use near homes and schools: three council members' memo sought a pause, but a special session left the council split four for, three undecided and four against, with staff recommending Unified Development Code amendments instead; the active track prohibits data centers over the Edwards Aquifer Recharge Zone and imposes 500-foot setbacks from schools, daycares, hospitals and homes | Texas Public Radio |
| Carlton County Minnesota |
County | 2026-08-24 | 1 year (interim use ordinance) | Active | Data centers, cryptocurrency mining and AI operations in county townships | Water usage, electric rates, noise, air pollution and decommissioning costs; requested by resident group The Land Stewards, 80+ residents packed the hearing and all 16 speakers backed it | KAXE |
| Durham County North Carolina |
County | 2026-08-24 | 9 months | Active | New data centers and expansions over 100,000 sq ft (smaller closed-loop, no-diesel facilities exempt) | Water and energy use, noise and potential air and water pollution while the county drafts zoning amendments; dozens of residents spoke against data centers; coordinated with the City of Durham's parallel pause | WUNC / Duke Chronicle |
| Stafford Township New Jersey |
Township | 2026-08-24 | Permanent | Permanent Ban | All data centers township-wide (Ordinance 2026-22) | Electricity and water demand, pollution and infrastructure impacts with few permanent jobs; grassroots CRAN campaign; first Ocean County municipality to ban data centers | Patch / ROI-NJ |
| North Brunswick New Jersey |
Township | 2026-08-24 | Permanent | Permanent Ban | All data centers township-wide; trigger site was the 87-acre 100 Fidelity Plaza redevelopment | Watershed and drinking water protection, electricity demand, utility bill increases and pollution with few permanent jobs; residents canvassed and packed meetings with Food & Water Watch NJ and CRAN | Insider NJ / ROI-NJ |
| East Brunswick New Jersey |
Township | 2026-08-24 | Permanent | Permanent Ban | All data centers in commercial, business and industrial districts (Ordinance 26-21) | Rising utility costs, noise, air and water pollution, electricity and water consumption and grid strain; planning board-led ordinance adopted after a public hearing | Patch |
| Davidson County North Carolina |
— | 2026-08-24 | — | Rejected | A staff-drafted six-month moratorium failed on a 3-3 tie with one commissioner absent, after residents spoke in favor citing water, electrical infrastructure and noise; opponents argued a pause would close off economic opportunity. No data center project is currently targeting the county. | www.davidsonlocal.com | |
| Washington County (FL) Florida |
County | 2026-08-20 | 1 year | Active | Data centers and large-scale data processing facilities in unincorporated county | Land Development Code and Comprehensive Plan do not address data center infrastructure, water, electricity and public safety impacts; residents at the hearing pressed for permanent regulations rather than a delay | Washington County News |
| Piedmont Oklahoma |
City | 2026-08-20 | Temporary (length unspecified) | Proposed | ~630-acre agricultural-to-PUD rezoning; developer proposes a 75,000 gal/day water cap | Water strain on a small agricultural system, noise, traffic and lighting; residents gathered signatures on three citizen initiative petitions including a temporary moratorium paired with impact studies | KOKH FOX 25 |
| Salix Iowa |
— | 2026-08-20 | — | Rejected | City Council voted down a one-year moratorium, clearing the way for a Google data center on ~900 annexed acres after the Salix Guardian Alliance and 100+ residents pushed for impact studies; a councilmember flipped after Google was named. Woodbury County's suit over the annexation remains pending. | www.iowapublicradio.org | |
| Spokane County Washington |
County | 2026-08-19 | 4 months | Active | New data centers, unincorporated county | Commissioners adopted a four-month pause after proposing a nine-month version in July, citing grid capacity and land use review needs | KREM |
| Calvert County Maryland |
County | 2026-08-18 | 6 months | Active | Data center site plan approvals county-wide | Land use, infrastructure and community impacts; commissioners want to revisit zoning that treats data centers as a permitted use, after sustained opposition to the Calvert Cliffs project and a primary that ousted three incumbents | Calvert County / Southern Maryland News Net |
| Winnebago County Wisconsin |
County | 2026-08-18 | 12 months | Active | New data centers, unincorporated county | County board enacted the 12-month pause it voted to pursue in June, citing water, energy and land use review needs | WTAQ |
| Westover Alabama |
City | 2026-08-18 | 6 months | Active | All data centers citywide; 437-acre project on Highway 280 at Cheshire Drive | Land and environmental impacts and gaps in zoning and development regulations after residents packed public comment opposing a 437-acre by-right project; ordinance tabled once before passing | ABC 33/40 |
| Anniston Alabama |
City | 2026-08-18 | 12 months | Active | All new data centers in the city's regulatory jurisdiction (existing facilities grandfathered) | Electrical demand, water and wastewater capacity, stormwater, transportation, emergency services, noise and cooling systems; Planning Commission-recommended proactive pause (Resolution 26-R-97) | Calhoun Journal / WBRC |
| Nye County Nevada |
County | 2026-08-18 | Permanent (Basin 162) | Permanent Ban | All data centers in the Pahrump Valley groundwater basin (Basin 162), 500,000+ acres | Outright ban in one of Nevada's most over-appropriated water basins; a 3,400-signature citizen petition and hundreds of residents at hearings drove the bill after an earlier ban motion died for lack of a second | Nevada Current |
| Tulare County California |
County | 2026-08-18 | 45 days (extendable 10 months 15 days) | Active | Large-scale data centers in unincorporated areas | Groundwater scarcity and SGMA limits, electricity demand, land use and backup generator noise; strong public outcry, and supervisors also sent letters opposing data centers in any jurisdiction in the county | The Sun-Gazette / SJV Water |
| Jackson County (NC) North Carolina |
County | 2026-08-18 | 12 months | Active | Data center zoning, development, building and demolition permits and rezonings (SIC 73/7374/7379) | Quality-of-life impacts on nearby residents weighed against tax base benefits; planning staff set a benchmark schedule of public hearings and expert testimony before drafting regulations | The Sylva Herald |
| Greensboro NC |
Municipal | 2026-08-18 | 180 days | Active | New data center development | City Council adopted a 180-day pause 8-0 pending development of data center zoning and land-use standards. | Edged research |
| North Berwick Maine |
Town | 2026-08-18 | Permanent ban on the Nov 3, 2026 ballot | Proposed | Zoning amendment prohibiting any facility with an aggregate data center area of 25,000 sq ft or larger | Land use and industrial scale: the select board deliberately skipped a temporary moratorium in June, reasoning a straight zoning prohibition could take effect sooner, and approved ballot language defining and banning data centers; official-led with no recorded opposition from residents or officials, alongside a companion comprehensive plan growth-area amendment | Portland Press Herald |
| Hastings Minnesota |
City | 2026-08-17 | 1 year | Active | All data centers (no size threshold) | City code does not define or regulate data centers; proactive council and staff pause after a public hearing raised municipal water supply concerns; no project pending | KDWA / Hastings Journal |
| Madison County (AR) Arkansas |
County | 2026-08-17 | 3 years (emergency clause) | Active | Data centers, digital asset mining and large-scale server operations | Quorum Court pause to study the costs and benefits of data centers and develop regulations; two public hearings held beforehand; no project pending | Madison County Record / KATV |
| Pataskala Ohio |
City | 2026-08-17 | Permanent ban on the Nov 3, 2026 ballot | Proposed | Charter amendment banning data centers above 25 MW peak load | Energy and grid supply questions the developer could not answer, plus zoning and scale concerns; a grassroots petition with 500+ signatures was certified for the November ballot after months of organizing | The Reporting Project / WSYX |
| Visalia California |
City | 2026-08-17 | TBD | Exploring | Data centers with significant water net loss and/or electrical demand | Drought and groundwater water loss plus electrical demand, and the argument that data centers are not job creators; resident-driven and carried by Councilmember Poochigian, who directed staff to return with a moratorium | The Sun-Gazette |
| Alamance County NC |
County | 2026-08-17 | 1 year | Active | New data center development | Board of Commissioners adopted a one-year pause 5-0 while county land-use rules for data centers are drafted. | Edged research |
| Louisville Kentucky |
City | 2026-08-13 | 6 months | Active | Rezonings, conditional use permits and plan applications for telecom hotels & data centers | Metro Council approved the pause 24-1 on Aug 13 after months of resident pressure over energy and water demand; blocks planners from approving new data center proposals until comprehensive zoning rules are adopted | Louisville Public Media / WKYT |
| Bellevue Wisconsin |
Village | 2026-08-12 | 1 year | Active | All data center development village-wide | Board-requested proactive pause to review public health, land use, environmental constraints and general welfare before any proposal; trustees may extend six months and are weighing a permanent prohibition | WFRV Local 5 / FOX 11 |
| Eastport Maine |
City | 2026-08-12 | 180 days | Active | Data centers and AI computing facilities, including submerged/underwater facilities | Marine environment and ocean health, failures of tribal consultation and community character; ECHO citizen petitions drove the pause and the Planning Board unanimously recommended a permanent ban on Aug 24 | The Maine Monitor / Maine Public |
| Mount Vernon Washington |
City | 2026-08-12 | 6 months | Active | New data center permit applications city-wide | Council paused permit acceptance while planning staff draft data center code language, citing electricity and water demand, city capacity for large facilities, stormwater and sewer planning, and the city's location in the Skagit River 100-year floodplain; follows Skagit County and La Conner | Cascadia Daily News |
| Waxhaw North Carolina |
Town | 2026-08-11 | 12 months | Active | Data centers, cryptocurrency mining, data storage/processing and related telecom infrastructure in the town's zoning jurisdiction | Proactive board-led pause to close zoning and land use loopholes in the land development code before any application arrives | WBTV |
| Nicholasville Kentucky |
City | 2026-08-11 | 6 months | Active | New data centers city-wide | Residents turned out asking the commission to pause and study impacts on electric bills, property taxes and water usage before any facility is approved | WKYT |
| Charlestown Rhode Island |
Town | 2026-08-11 | Permanent | Permanent Ban | All data centers and battery energy storage systems (BESS) | Second Rhode Island town to prohibit data centers; council cited total reliance on well water and septic systems, groundwater contamination and fire risk, and the land, electricity and water demands of data centers | ecoRI News |
| Fort Worth Texas |
City | 2026-08-11 | 90 days (earliest start Feb 16, 2027) | In Process | New data center construction city-wide | Council unanimously started the legal process for a temporary pause after neighborhood pushback over noise and infrastructure; an 11-member Data Center and Infrastructure Commission reports Nov 3 ahead of a possible Feb 16 vote | Fort Worth Report |
| Tucson Arizona |
City | 2026-08-11 | Permanent regulations | Restrictions Added | Facilities over 25,000 sq ft or 20 MW | First large-scale data center rules after a year of review driven by resident water concerns: half-mile residential setback, 50-foot height cap, energy source disclosure, potable water limits and mayor-and-council approval of every project | The Cool Down |
| Conneaut Ohio |
— | 2026-08-11 | — | Rejected | City Council voted 2-4 against a one-year data center moratorium on its third reading despite months of resident pressure; a separate ballot measure capping data centers at 25 MW advances to a third reading and possible special election | Star Beacon | |
| Indianapolis (Marion County) Indiana |
City | 2026-08-10 | Through Dec 31, 2027 | Active | High-impact / hyperscale DCs; new data center construction city-wide | City-County Council voted 23-1 on Aug 10 to pause new data center construction through Dec 31, 2027 while councilors finalize noise, water management and electrical capacity rules; three previously approved projects unaffected; Metropolitan Development Commission ratification Aug 19 | Mirror Indy / WTHR |
| Independence County Arkansas |
County | 2026-08-10 | 5 years | Active | All data centers and crypto mines county-wide | Longest pause in Arkansas; quorum court cited water supply and power strain plus few jobs or revenue, acting proactively after a wind-turbine developer used pre-existing contracts to bypass local review | Arkansas Advocate / White River Now |
| Queen Anne's County Maryland |
County | 2026-08-10 | 12 months | Active | All data center applications, approvals and processing county-wide | Proactive pause so the county can evaluate impacts of large-scale facilities and develop zoning regulations and performance standards; sixth Maryland county to act | Queen Anne's County / CBS Baltimore |
| Cherokee Nation Oklahoma |
Tribal Council | 2026-08-10 | Indefinite | Permanent Ban | All hyperscale data centers on tribally owned and trust land | Task force report cited energy and water consumption, air quality, noise and light pollution, infrastructure strain and cultural resource protection; survey of nearly 1,600 citizens found 64% opposed. Projects on non-tribal reservation land now require early tribal consultation | KGOU / KOSU |
| Helena Alabama |
City | 2026-08-10 | 180 days (proposed) | In Process | New data centers, gas stations and auto businesses along several highway corridors | First reading of a corridor pause giving the city time to review zoning regulations and land use standards before new applications arrive | ABC 33/40 |
| Lincolnton North Carolina |
City | 2026-08-10 | 1 year (proposed) | Proposed | New data centers city-wide; $600M project proposed at 232 Car Farm Road | Council delayed a decision on the proposed one-year pause after the developer argued the project would ease the city budget gap; public hearing on zoning and land use impacts rescheduled to September | Lincoln Times-News |
| Palm Beach County Florida |
County | 2026-08-06 | 1 year (recommended) | In Process | New large-scale data center applications county-wide | Zoning Commission unanimously recommended a one-year pause and tougher regulations after resident testimony on water and energy use; final County Commission consideration set for September | CBS12 |
| Escambia County Florida |
County | 2026-08-06 | Permanent | Permanent Ban | Large-scale data centers in unincorporated Escambia County, outside the City of Pensacola and the Town of Century; accessory server rooms at hospitals, universities and employers remain allowed | Water and energy demand and land use incompatibility: commissioners passed an outright ordinance ban on top of a July resolution memorializing that the Land Development Code already excludes data centers, after more than two dozen residents asked them to harden the language against legal challenge; a follow-on 12-month moratorium was abandoned on Sept. 10 when the county attorney advised it would weaken, not strengthen, the existing ban | NorthEscambia.com |
| Gage County Nebraska |
County | 2026-08-05 | 8 months | Active | Conditional and special use permits for data centers in the unincorporated county | Water and electricity consumption, farmland loss, property values and rural community character; grassroots-driven, with residents packing hearings and now pressing supervisors to extend the pause to the 18 months the planning commission recommended | Nebraska Public Media |
| Denton Texas |
City | 2026-08-04 | TBD (adoption vote Dec 2) | In Process | New data centers city-wide | Council voted to begin moratorium process and weigh stricter development rules on water and grid impacts; public hearings Sept 22 and Oct 27 | KERA News |
| Ormond Beach Florida |
City | 2026-08-04 | 18 months | Active | All data centers city-wide | Pause while staff drafts comprehensive plan and land development code amendments toward a total data center ban | Ormond Beach Observer |
| Salem Oregon |
City | 2026-08-03 | 120 days | In Process | New AI data center land-use applications | Residents packed special meeting opposing Verrus DC over water and land use; council unanimously voted to halt future data center applications; 45-day notice to state land agency due Aug 10 | Salem Reporter |
| Jeffersonville Indiana |
City | 2026-08-03 | 1 year | Active | New data centers city-wide (Meta River Ridge project exempt) | Residents packed hearings over noise, pollution, tax breaks and proximity to homes; craft Special Data Center Overlay District zoning with berms and buffers | Louisville Public Media |
| Town of Tonawanda New York |
Town | 2026-08-03 | 1 year | Active | Data centers with peak demand of 20 MW or more (stricter than NY state's 50 MW threshold); excludes Village of Kenmore | Local Law 2-2026 mirrors and tightens the statewide pause so no developer can slip through; board to write zoning regulations addressing grid demand and land use during the year | WKBW / Buffalo Toronto Public Media |
| Cle Elum Washington |
City | 2026-07-31 | 6 months | Active | Large computing facilities; 100,000 sq ft Blue Fern proposal pending | Emergency pause to study electricity, water, fire protection, noise and economic impacts after surprise data center proposal | Seattle Times / KOMO News |
| Harwinton Connecticut |
Town | 2026-07-30 | TBD | Exploring | Data centers, battery storage and solar facilities | Developer inquiries with no zoning rules in place; zoning commission weighing a pause; discussion continues at August meeting | NBC Connecticut |
| DeSoto County Florida |
County | 2026-07-29 | 1 year | Active | New DC applications (exempts Roan St-area project that could exceed 1,000 acres) | Unanimous 1-year pause after public backlash; planning commission wanted 2 years covering the DCIP project, but county attorney urged shorter exempted version to limit legal risk | WGCU / WINK News |
| Harrison County Kentucky |
County | 2026-07-29 | TBD | Proposed | New data centers countywide | Standing-room-only forum with near-unanimous resident opposition ahead of fiscal court moratorium vote set for Aug 11 | WKYT |
| Janesville (Town of) Wisconsin |
Town | 2026-07-29 | 12 months (proposed) | Proposed | New data centers (tech company concept at N Polzin/W Fenrick Rds) | Overflow crowd at public meeting; Planning & Zoning Committee recommended yearlong moratorium to Town Board (vote as soon as Aug 3) | WMTV 15 News / GazetteXtra |
| Hillsboro Oregon |
City | 2026-07-28 | 4 months (120 days) | Active | All new data centers + battery storage systems | Emergency pause called with one day's notice to head off application rush; weigh permanent limits; scrutiny of $84M/yr property tax breaks and energy/land use | OregonLive |
| La Conner Washington |
Town | 2026-07-28 | 6 months (minimum) | Active | Data center permit applications (none received to date) | Proactive pause on accepting data center permit applications so staff can revise land use regulations and decide whether any data center would be appropriate; planning director cited the town's proximity to a large water source, and no applications had been received. Follows Skagit County's June 1 moratorium | Skagit Valley Herald (goskagit.com) |
| Paulding County Georgia |
County | 2026-07-28 | ~5 months | Active | New DC applications, zoning requests and civil plan reviews | Update county development codes before accepting new data center projects | FOX 5 Atlanta |
| Mercer County (KY) Kentucky |
County | 2026-07-28 | TBD | In Process | New data centers county-wide | First reading of moratorium ordinance after public forum showed overwhelming resident opposition; second reading pending | The Harrodsburg Herald |
| Pulaski County (Quorum Court) Arkansas |
— | 2026-07-28 | — | Rejected | 12-month moratorium failed twice: May 27 attempt fell short after a vote-tally error (corrected 8-6-1); weakened version exempting AVAIO Digital's Wrightsville project rejected 10-3 on Jul 28 after critics called the carve-out a 'free pass'; amendment to close it also failed. Project remains unregulated. | Arkansas Times / Arkansas Advocate | |
| Marshalltown Iowa |
City | 2026-07-27 | 4 months (ordinance adopted Aug 24, 2026) | Active | New data centers (none formally proposed) | Council reversed course 5-2 in July for a four-month pause and formally ordained it Aug 24, 2026, to study electrical demand, water consumption, wastewater discharge and other environmental impacts; no data center formally proposed | Marshalltown Times-Republican |
| Cherry Hill New Jersey |
Township | 2026-07-27 | Permanent | Permanent Ban | Large-scale AI/cloud data centers (small business server rooms exempt) | Proactive zoning ban before any application; land, water and energy use inconsistent with master plan garden-suburb goals | Philadelphia Inquirer |
| Cherokee County (GA) Georgia |
County | 2026-07-21 | 30 days + 180-day extension (adopted Aug 18, 2026) | Active | New data center development | Commissioners voted unanimously at an Aug 18, 2026 public hearing to more than double the original 30-day pause by 180 days so staff can draft a data center ordinance; eleven residents spoke, none in favor, several asking for a permanent ban | WSB-TV |
| Lochbuie Colorado |
Town | 2026-07-21 | 5 years | Active | All new data centers town-wide | Longest pause in Colorado; trustees cited water scarcity, grid strain and preserving small-town character, acting proactively with no application filed | Rocky Mountain PBS |
| Yankton County South Dakota |
County | 2026-07-21 | 6 months (extendable 6 more) | Active | Data centers and bitcoin mining operations | Commission paused data center and crypto mining approvals to study water, power and land use and write zoning standards | Yankton Press & Dakotan |
| Nashville-Davidson Tennessee |
Metro Government | 2026-07-21 | Permit pause through Dec 1, 2026 | Active | New data center permits; paired zoning caps facilities at 500,000 sq ft | Metro Council passed BL2026-1448 pausing permits while adopting zoning caps, after residents raised grid demand and land use concerns | Nashville Banner |
| Chesapeake Virginia |
City | 2026-07-21 | 8 months or until policy adopted | Active | New data center applications city-wide (Resolution 26-R-042) | Council placed an eight-month hold on data center applications while a citywide data center policy on land use and utility impacts is developed | VPM / WHRO |
| Pasco Washington |
City | 2026-07-20 | 6 months | Active | Data centers, crypto mining, AI computing and high-density computing facilities | Pause permits and business licenses to study impacts of high-density computing projects | NBC Right Now |
| Springfield (MO) Missouri |
City | 2026-07-20 | 120 days | Active | Data centers (administrative delay) | Gather information, evaluate best practices and establish a regulatory framework | Ozarks First |
| Cottage Grove Wisconsin |
Village | 2026-07-20 | 12 months (+6 mo intended) | Active | New data center development | Proactive: review zoning codes, ordinances and comprehensive land plan before proposals arrive | WMTV 15 News |
| Monument Colorado |
Town | 2026-07-20 | 6 months | Active | New data centers town-wide (Ordinance 18-2026) | Board paused applications while staff draft land use regulations addressing water and energy demand | Colorado Springs Gazette |
| Surry County North Carolina |
County | 2026-07-20 | 2 years | Active | New data center development county-wide | Commissioners enacted a two-year pause, among the longest in North Carolina, to study water and grid impacts and write zoning rules | WFDD |
| Sheboygan Wisconsin |
City | 2026-07-20 | 12 months | Active | Data center facilities over 10,000 sq ft | Council pause to study grid demand, water use and land use while questions about siting remain unresolved | Seehafer News |
| Dougherty County Georgia |
County | 2026-07-20 | 45 days, extended 180 days Aug 31, 2026 | Active | Data center zoning applications county-wide | Protect pristine aquifers and local water supply; zoning code does not address data centers; review prompted by resident questions and extended unanimously just before expiry | WALB |
| Hall County Georgia |
County | 2026-07-16 | 180 days | Active | New DC rezoning/permit applications (also covers detention centers) | Adjust development code on industrial permitting; impacts on county services, infrastructure and residents | AccessNorthGA / WSB-TV |
| New Albany Indiana |
City | 2026-07-16 | Up to 1 year | Active | DCs/campuses >100,000 sq ft | Review impacts on infrastructure, utilities, environmental resources and noise | News and Tribune |
| Cleveland Ohio |
City | 2026-07-16 | 3 months (+3 mo ext possible) | Active | New standalone principal-use data centers and expansions | Zoning code lacks data center definition; revise zoning; mayor shortened proposed 1-year pause to 3 months | City of Cleveland / Signal Cleveland |
| Woodland Park Colorado |
City | 2026-07-16 | 18 months | Active | New data centers city-wide | Council paused applications to study water supply limits and electrical capacity and write zoning standards | Colorado Springs Gazette |
| Brookhaven New York |
Town | 2026-07-16 | 18 months | Active | New data centers town-wide | Board approved an 18-month pause after a heated meeting driven by public pushback over energy demand and neighborhood impacts | South Shore Press |
| Hamilton County Tennessee |
County | 2026-07-15 | 1 year | Active | New data centers in unincorporated areas | Proposed by Mayor Weston Wamp June 30; time for planning department rules; energy and water concerns | Chattanooga Times Free Press / WDEF |
| Mansfield Township New Jersey |
Township | 2026-07-15 | Permanent | Permanent Ban | All data centers (prohibited by name in zoning code) | Council drafting zoning revision prohibiting data centers by name to foreclose legal challenges; proactive protection of rural character | Burlington County Times / Yahoo News |
| Austin County Texas |
County | 2026-07-15 | Countywide pause | Active | New AI data centers and battery energy storage systems | Commissioners court adopted a countywide pause on AI data centers and BESS citing grid, water and rural land use concerns | Austin County |
| Jackson Mississippi |
City | 2026-07-14 | 183 days (effective ~Aug 13) | Active | All data centers citywide (permits, rezonings, special/conditional use) | First Mississippi city moratorium; council to identify appropriate sites and study impacts; effective in 30 days due to non-unanimous vote | Mississippi Today / WLBT |
| Pasco County Florida |
County | 2026-07-14 | 1 year | Active | Large data centers | Joins regional Florida moratorium wave; water and energy use, noise, environment | WUSF / Fox 13 |
| Clay County Florida |
County | 2026-07-14 | 12 months | Active | Large-scale DC applications, permitting and rezoning | Final approval July 14; study impacts; resident concerns over water, energy, noise | Florida Politics |
| Hernando County Florida |
County | 2026-07-14 | 12 months (proposed) | In Process | Large-scale DC applications, permitting and rezoning | Advanced July 14 (date approx.); final adoption vote expected ~July 28 | Florida Politics |
| Lake County Florida |
County | 2026-07-14 | 12 months (proposed) | In Process | Large-scale DC applications, permitting and rezoning | Advanced July 14 (date approx.); final adoption vote expected ~July 28 | Florida Politics |
| Haring Township Michigan |
Township | 2026-07-14 | 6 months | Active | All new data center construction | Standing-room crowd largely favored outright ban (not allowed under state law per township attorneys); time to draft regulations | Cadillac News |
| Marietta Georgia |
City | 2026-07-14 | ~6 months (through Dec 31, 2026) | Active | All new data center projects | Packed community opposition to Powers Ferry Place rezoning (decision tabled); pause on all new DC projects while rules studied | Marietta Daily Journal |
| Broken Bow Nebraska |
City | 2026-07-14 | 6 months (extendable +12 months) | Active | New data center applications | Draft formal data center regulations before accepting applications | Sandhills Express |
| Caroline County Maryland |
County | 2026-07-14 | 1 year | Active | New data centers in unincorporated areas (Federalsburg proposal outside county authority) | Commissioners cited energy supply strain, noise and water usage while zoning standards are developed; county authority does not reach incorporated towns | Star Democrat / WBOC |
| Russellville Arkansas |
City | 2026-07-14 | 6 months | Active | New data center approvals city-wide | Council halted new approvals while staff develop zoning regulations covering water, power and noise impacts | River Valley Radio |
| Lawrence Kansas |
City | 2026-07-14 | 24 months | Active | Large-scale data centers city-wide | Residents packed the commission meeting (about 50 attending, overflowing into the City Hall lobby) over water and electricity strain, noise pollution and neighborhood character; the land development code allowed massive data centers by right in several zoning districts with no public objection process. Commission doubled the proposed one-year pause to two years and initiated a land development code text amendment | The Lawrence Times / Lawrence Journal-World |
| Flagler County Florida |
County | 2026-07-14 | 12 months | In Process | New data centers in unincorporated county | First reading of a 12-month pause to study water, energy and land use impacts in unincorporated areas | Palm Coast Observer |
| Minneola Florida |
City | 2026-07-14 | 1 year (proposed) | In Process | New data centers city-wide | City advanced moratorium policy in step with Lake County while zoning standards for water and power use are drafted | GrowthSpotter |
| Lansing Michigan |
City | 2026-07-14 | 182 days | Active | New data centers city-wide (effective July 27, 2026) | Council pause after resident pushback over electricity demand, water use and neighborhood impacts while zoning standards are drafted | WKAR |
| Wheeler Township Michigan |
Township | 2026-07-14 | 1 year | Active | New data centers township-wide | Board adopted a one-year pause to study land use and utility impacts and draft zoning regulations | Wheeler Township |
| Wrightstown Wisconsin |
Village | 2026-07-14 | Extended to 1 year | Active | New data centers village-wide | Village extended its pause to a full year as a real estate firm explored a potential site; residents later voted in a nonbinding referendum on data center development | WFRV Local 5 |
| Leon County Florida |
County | 2026-07-14 | 18 months | Active | Large-scale data centers | Water usage and environmental effects; staff directed to spend 12 months developing regulations; extended from 12 to 18 months at Commissioner Proctor's suggestion so it runs through 2027 | WCTV / WFSU |
| Marysville Washington |
City | 2026-07-14 | 6 months | Active | All buildings whose principal use is management or transmission of digital data (incidental servers exempt) | Council paused development to complete water and sewer master plans and rate studies and determine whether regulatory changes are needed, so residents and developers know what is permitted; concern focused on impacts to water and sewer rates | HeraldNet (Everett Herald) |
| Stokes County North Carolina |
— | 2026-07-14 | — | Rejected | Commissioners voted down proposed 6-month moratorium on new DC proposals while weighing Project Delta (January rezoning voided by court in April over defective public notice; developer to resubmit) | WFMY News 2 | |
| Putnam County Florida |
— | 2026-07-14 | — | Rejected | Commission declined a data center moratorium and adopted a 72-hour disclosure policy for data center proposals instead, promoting transparency without pausing development | Palatka Daily News | |
| York County South Carolina |
County | 2026-07-13 | 9 months | Active | New DC site plans, special exceptions, conditional use permits in unincorporated county | Third reading passed July 13, effective immediately; study impacts on utility rates, energy, water, noise and nearby properties; extension allowed | WRHI / Fort Mill Sun |
| St. Charles County Missouri |
County | 2026-07-13 | 6 months | Active | DCs >100,000 sq ft or >5 MW, county-wide | Overwhelming public opposition; study impacts with outside experts; enacted under county health department authority | St. Louis Public Radio |
| Boyle County Kentucky |
County | 2026-07-13 | 1 year | Active | New data center development county-wide | One-year pause to develop data center zoning regulations amid wave of proposals across Kentucky | The Advocate-Messenger |
| Valparaiso Indiana |
City | 2026-07-13 | TBD | In Process | New data centers city-wide | First reading of a data center pause while the city drafts zoning standards on noise, water and power | NWI Times |
| Neptune Township New Jersey |
Township | 2026-07-13 | Permanent | Permanent Ban | All data centers township-wide | Became the 25th New Jersey municipality to ban data centers, prohibiting them by zoning amendment amid statewide resident mobilization over energy costs and land use | ROI-NJ |
| Greenville Wisconsin |
Village | 2026-07-13 | 1 year (extendable 6 months) | Active | Data center facilities 10,000 sq ft or larger | Village board pause to study land use, water and electricity impacts and draft zoning standards | WFRV Local 5 |
| Girard Ohio |
City | 2026-07-13 | 12 months | Active | New AI data centers city-wide | Energy demand and public safety impacts of AI data centers plus the absence of zoning guidelines; council proactively paused to develop zoning standards, framing it as solidarity with neighboring Niles, Lordstown, Cortland and Hubbard, which had already acted | Tribune Chronicle |
| Newfield New York |
Town | 2026-07-09 | 1 year | Active | Data centers and cryptocurrency mining townwide | Preemptive pause to develop regulations | Tompkins Weekly |
| Boyd County Kentucky |
County | 2026-07-09 | 6 months | Active | New data centers county-wide (TeraWulf 1 GW EastPark project exempt) | Study environmental impacts, utility capacity, economic benefits and best practices; update local regulations and standards | The Daily Independent |
| Missoula County Montana |
County | 2026-07-09 | 1 year (interim zoning) | Active | New data centers, unincorporated county | Interim zoning adopted after a public hearing to study water, energy and land use impacts and craft permanent regulations | KGVO |
| Walker County Georgia |
County | 2026-07-09 | 30 days, extended to 180 days on Aug 6, 2026 | Active | Any data-center-related application or permit request in unincorporated Walker County | Zoning and land use compatibility, water and electricity demand, noise, lighting, buffers and setbacks; official-led, with a Data Center Development Standards Study Committee meeting every other Thursday before drawing more than 40 residents, weighing closed-loop cooling, water caps and distance from homes, with zoning amendments expected in early 2027 | Chattanooga Times Free Press |
| Warren Maine |
Town | 2026-07-08 | 180 days | Active | All data centers (none proposed) | Heavy water and power use concerns; overflow special town meeting crowd of ~60 residents | Midcoast Villager |
| Sarasota County Florida |
County | 2026-07-08 | 12 months | Active | Hyperscale DCs (50 MW+) | Water use and utility infrastructure strain; environmental degradation; some commissioners favor permanent ban | Suncoast Searchlight |
| Prince George's County Maryland |
County | 2026-07-07 | 2 years (or until zoning framework adopted) | Active | New hyperscale data centers county-wide (county has 5 existing DCs) | Council approved two-year hyperscale moratorium July 7, 2026 after nearly an hour of public testimony; longest pause in Maryland; shields residents from AI boom impacts while zoning/siting legislation drafted | Maryland Matters |
| Broomfield Colorado |
City | 2026-07-07 | 18 months | Active | New/expanded DCs with 10 MW+ projected load | Power demand, water use and community impacts amid infrastructure strain; comprehensive review to develop regulations (Ord. 2313) | Colorado Politics |
| Greenup County Kentucky |
County | 2026-07-07 | 6 months | Active | New data centers county-wide (TeraWulf 1 GW EastPark project exempt) | Officials set guardrails on noise, lights and siting rules before new projects; effective immediately (date approximate) | The Herald-Dispatch |
| Knoxville Tennessee |
City | 2026-07-07 | 1 year (emergency ordinance) | Active | Data centers of 10 MW or greater | Emergency ordinance pausing large data centers while the city writes permanent rules on grid capacity, water and noise | City of Knoxville |
| Chester County South Carolina |
County | 2026-07-06 | 6 months | Active | New data center applications | Final approval early July 2026 (date approx.) after June 15 first reading; public workshops planned on community, economic and environmental impacts | QC News / SC Public Radio / WFAE |
| Franklin North Carolina |
Town | 2026-07-06 | 1 year | Active | All new data centers (preemptive; no live proposal) | No zoning safeguards for data centers; explore controls including utility/infrastructure requirements; packed public hearing | Smoky Mountain News |
| Hazle Township Pennsylvania |
Township | 2026-07-06 | 180 days (curative amendment) | Active | 1,300-acre, 15-building 'Project Hazelnut' campus | Curative amendment pausing DC applications while zoning rules rewritten after county court ruling; packed resident opposition | Fox56 / Penn Capital-Star |
| Delta County Michigan |
County | 2026-07-06 | 12 months (pending county board Aug 27) | In Process | Data center and cryptocurrency mining construction | Planning Commission approved; craft ordinances addressing electrical infrastructure, natural resources and tourism concerns | WLUC TV6 |
| Springville Alabama |
City | 2026-07-06 | 1 year | Active | Data center proposals citywide | Proactive: develop planning and zoning regulations; officials cited that data centers don't create jobs | St. Clair News-Aegis |
| Westfield Massachusetts |
City | 2026-07-06 | 12 months (365 days) | Active | New data centers citywide | Residents packed meetings over electricity demand and water fears; draft siting, environmental and transparency rules | MassLive / The Cool Down |
| Davie County North Carolina |
County | 2026-07-06 | 1 year | Active | New data centers county-wide | Commissioners adopted a one-year pause to study water, energy and land use impacts and update the development code | WFDD |
| Linn County Iowa |
County | 2026-07-01 | 18 months | Active | EU-3 large-scale DC rezoning in unincorporated county; ~3,500 acres already tied to DC development | Regional water study (Stantec est. ~17 months); comprehensive plan update; ratepayer legislation push; packed board room incl. Save Morgan Valley opposition to 720 MW gas plant | Corridor Business Journal |
| Paris Tennessee |
City | 2026-07-01 | ~1 year (study period) | Active | Data processing centers within city limits | Time to study zoning and community impacts (~1 year); residents backed pause but sought firm end date and stronger zoning | Radio NWTN |
| Little Rock Arkansas |
City | 2026-07-01 | Until Jan 1, 2027 (proposed) | Proposed | New large-scale data centers (follows June 2 regulations; $1B Google-led port project) | Directors Webb and Peck requested moratorium until electricity cost, water resiliency, environmental exposure and tax revenue questions answered; board deferred measure July 7 to August | Arkansas Democrat-Gazette |
| Frederick County Maryland |
County | 2026-07-01 | 6 months | Active | New data center applications/permits | Community divided over data center growth; former state hub of DC development pauses to set rules | NBC4 Washington |
| Ohio (ballot initiative) Ohio |
— | 2026-07-01 | — | Rejected | Proposed constitutional amendment to ban data centers over 25 MW failed to qualify for the 2026 ballot, gathering ~70,000 of 413,488 signatures needed by the July 1 deadline; backers plan a 2027 retry | Data Center Bans tracker | |
| Santa Fe County New Mexico |
County | 2026-06-30 | 18 months | Active | All data centers >=1 MW (threshold lowered from 100 MW) | First proactive moratorium in NM; study water consumption, electrical demand, grid reliability, environmental impacts, land-use compatibility; stakeholder input for future regulations | Santa Fe New Mexican |
| Somerville Alabama |
Town | 2026-06-30 | 18 months | Active | All data centers (triggered by proposed bitcoin mining facility near Union Road) | Organized resident pushback over bitcoin mine; town has no zoning laws; confirming legal authority with Alabama League of Municipalities | WZDX / Rocket City Now |
| Union County Arkansas |
County | 2026-06-30 | 1 year (July 10, 2026-July 9, 2027) | Active | New DC development; Paradox Data 8 MW crypto facility expansion (Z Squared LOI) on hold | Emergency Quorum Court meeting drew largest crowd ever hosted (public turnout); infrastructure, utilities, public safety concerns; emergency clause skipped waiting period | El Dorado News-Times / KTVE |
| San Marcos Texas |
City | 2026-06-30 | Permanent ban | Permanent Ban | All data centers citywide (zoning code amendment; first Texas city to ban) | Water and energy concerns; Sen. Bettencourt threatens challenge under HB 2559 and 2023 'Death Star' law; experts say zoning change (not moratorium) may survive | Temple Daily Telegram |
| Washington County (MD) Maryland |
County | 2026-06-30 | 12 months | Active | New data center applications | Resident testimony on groundwater drought and well impacts, electric grid capacity and infrastructure cost-shift concerns | Maryland Daily Record |
| Logan Utah |
City | 2026-06-30 | 180 days | Active | New data centers city-wide (Ord. 26-12, effective July 1) | Council imposed a 180-day pause in near-record time to study water and power demand and write zoning standards | Cache Valley Daily |
| Delaware (statewide proposal) Delaware |
— | 2026-06-30 | — | Rejected | Seven-month statewide DC moratorium proposal voted down on session's final day; legislature instead passed HB 233 (DCs first cut off in blackout), HB 445 (developers must self-supply power within 10 years), SB 326 (Delmarva Power billing limits and audits) | Newark Post / Spotlight Delaware | |
| Clay New York |
Town | 2026-06-29 | 1 year | Active | Zone changes and special permits for large-scale DCs, AI computing, crypto mining | Preemptive as town prepares for Micron campus growth; paired with new battery energy storage law; no DCs proposed yet | Syracuse.com |
| Burien Washington |
City | 2026-06-29 | 1 year (emergency) | Active | All new data centers (emergency ordinance, effective immediately) | Proactive; no staff data center expertise (definition borrowed from Seattle); study resource use, water, energy and job creation | B-Town Blog |
| Greenwood County South Carolina |
County | 2026-06-29 | 12 months | Active | Future data center development | Second reading of Ordinance 2026-19 approved 4-3 on July 14 after tense meeting; council also advanced ordinance barring DCs from zoning districts; third/final reading approved July 21 | Index-Journal / WYFF |
| Snohomish County Washington |
County | 2026-06-29 | 6 months | Active | New data center applications (unincorporated areas) | Pause to develop zoning regulations addressing energy, water and land use impacts | Snohomish County Tribune |
| East Fishkill New York |
Town | 2026-06-26 | 3 years | Active | Data centers over 20 MW | Months of community opposition; freeze until July 2029 | WAMC / Data Center Dynamics |
| Forsyth Township Michigan |
Township | 2026-06-25 | TBD | Active | Data centers | Passed at crowded board meeting; time to develop regulations | Upper Michigan's Source |
| Henry County (IL) Illinois |
County | 2026-06-25 | 12 months | Active | New data centers, unincorporated county | Board pause to develop zoning standards after residents raised farmland, water and grid concerns | Quad-City Times |
| Xenia Ohio |
City | 2026-06-25 | 1 year | Active | New data centers city-wide (effective July 25, 2026) | Council pause to study land use, noise and utility demand while permanent regulations are drafted | Xenia Gazette |
| La Crosse County Wisconsin |
County | 2026-06-25 | 18 months | Active | New data centers, unincorporated county | County board adopted an 18-month pause to study water, energy and land use impacts and develop regulations | WXOW |
| Brookville Pennsylvania |
Borough | 2026-06-24 | 180 days | Active | Data center development (2 proposed centers ~2.4M gal/day water) | Time to finalize data center rules; water-supply concerns | WPSU / Pennsylvania Capital-Star |
| Bethlehem New York |
Town | 2026-06-24 | 1 year | Active | New data centers town-wide | Board adopted a one-year pause to study grid capacity, water use and land use before applications are accepted | Rockefeller Institute |
| Norman Oklahoma |
City | 2026-06-23 | ~1 year | Active | New data center applications citywide | Protect water resources; evaluate environmental, utility and infrastructure impacts; develop regulations before any data center locates in Norman (applications suspended until June 9, 2027; Sooner Mall tax rebate also rejected) | OU Daily |
| Asheville North Carolina |
City | 2026-06-23 | 1 year | Active | New data center development | Power/water demand, noise, heat concerns; develop regulations | WLOS / Blue Ridge Public Radio |
| Woodbury County Iowa |
County | 2026-06-23 | 1 year | Active | New DCs in unincorporated areas (existing/approved applications untouched; Salix site exempt via annexation) | Proactive; no ongoing projects known in unincorporated areas; time to develop zoning regulations | The Cool Down / Woodbury County |
| Sparta Township New Jersey |
Township | 2026-06-23 | Permanent ban | Permanent Ban | Data centers prohibited in all zoning districts (Ordinance 26-11) | Not in keeping with rural/residential character; undue burden on water and electricity supply; noise concerns; council drafted rules proactively | TAPinto Sparta |
| Cache County Utah |
County | 2026-06-23 | 180 days | Active | DC applications on unincorporated land | County code lacks clear definitions/regulations; preemptive pause after Box Elder controversy; time for permanent code text amendments | Salt Lake Tribune |
| Medford Township New Jersey |
Township | 2026-06-23 | Permanent | Permanent Ban | All data centers within town limits | Proactive council-led ban amid AI data center debate; protect water, energy and community character | Philadelphia Inquirer |
| Morgan County Alabama |
County | 2026-06-23 | 12 months | Active | Bitcoin mining data center project | Commission blocked a bitcoin mining data center after residents complained of noise and power draw; pause allows zoning regulations to be drafted | Decatur Daily |
| Carbondale Illinois |
City | 2026-06-23 | 1 year | Active | New data centers city-wide | Council pause to study electricity and water demand and write land use regulations | The Southern |
| East Greenwich Township New Jersey |
Township | 2026-06-23 | Permanent | Permanent Ban | All data centers township-wide | Township adopted a zoning prohibition on data centers amid a wave of South Jersey bans driven by resident opposition to land, power and water demands | NJ.com / GovTech |
| Knox County Tennessee |
County | 2026-06-23 | 1 year | Active | New data centers, unincorporated county | Commission adopted a one-year pause to develop land use standards on power, water and noise | WVLT |
| Jackson County (FL) Florida |
County | 2026-06-23 | Permanent | Permanent Ban | Large-scale data centers and large-load customer facilities | Water and cooling demand, protection of waterways and springs and grid load; a packed board room drove commissioners to drop a one-year moratorium in favor of a permanent ban over the county attorney's warnings | WCTV |
| Spokane Washington |
City | 2026-06-22 | 1 year | Active | New computer data center building permits (citywide) | One-year pause to study energy, water and infrastructure impacts (Spokane Valley-Rathdrum aquifer, rates, noise, diesel backup); develop data center regulations. Tied to Avista 125-500 MW nonbinding deal; Councilman Cathcart opposed over aerospace carve-out (Ord. C36887) | City of Spokane / Spokesman-Review |
| Cullman Alabama |
City | 2026-06-22 | 1 year | Active | All new data centers (server farms, hyperscale, colocation) | Enforceable (daily violations, nuisance abatement); review infrastructure/water/noise; 4th AL city | AL.com / Yellowhammer News |
| Texas Township Michigan |
Township | 2026-06-22 | 12 months | Active | Data center developments | Study farmland preservation, rural zoning, grid/water capacity, noise/heat/light | WWMT |
| Spartanburg County South Carolina |
County | 2026-06-22 | 12 months (extendable) | In Process | All future DC development incl. pending unfinalized applications | First reading unanimous ~June 22; staff to identify appropriate areas; hundreds packed DES hearing on Valara air permits | SC Daily Gazette |
| Homewood Alabama |
City | 2026-06-22 | 12 months (+6 mo ext possible) | Active | New data center applications | Proactive: study zoning, buffering, infrastructure capacity, utility demands and preservation of city character | WBRC |
| Dodge County Wisconsin |
County | 2026-06-22 | 18 months | Active | Data centers countywide; Meta $1B Beaver Dam campus announced | Resident concerns over groundwater and wells, property values, noise, farmland, energy demand and transparency | Watertown Daily Times |
| Jackson County Missouri |
County | 2026-06-22 | 180 days | Active | Data center and battery energy storage (BESS) land-use applications | No county code on safety regulations or proximity to homes; evaluate long-term impacts with municipalities and residents | KCTV5 |
| Clinton Iowa |
City | 2026-06-22 | 6 months | Active | New data centers city-wide | Council reversed course and approved a six-month hold two weeks after rejecting a 120-day pause 5-2, following sustained resident pressure over power and water use | Courier News |
| Logan County Illinois |
— | 2026-06-18 | — | Lifted | The 12-month moratorium approved 6-4 on May 19 was declared invalid by the state's attorney on June 18 because it skipped the Zoning Board of Appeals advisory vote and public hearings, after Hut 8 Corp. threatened legal action; the county accepted Hut 8's applications for the $5B, 500 MW Logan Prairie Data Center and a data center zoning ordinance failed 5-6 the same day | Illinois Times | |
| Warren Township (NJ) New Jersey |
Township | 2026-06-18 | Permanent | Permanent Ban | All data centers township-wide | Committee prohibited data centers by zoning amendment, citing land use incompatibility and energy and water demand | NJ.com / GovTech |
| Holyoke Massachusetts |
City | 2026-06-17 | Permanent (zoning ban, all districts) | Permanent Ban | All new data centers citywide | Protests and packed hearings against $200M Water Street DC; zoning ordinance bans data centers in every district; first MA city to prohibit them outright | WAMC / Western Mass News |
| Carroll County (AR) Arkansas |
County | 2026-06-17 | 1 year | Active | Data centers and other high-intensity digital infrastructure facilities | Quorum court pause to study water and electricity demand and land use impacts of high-intensity digital infrastructure; proactive move with no project proposed | KY3 |
| Luther Oklahoma |
Town | 2026-06-17 | Through Dec 31, 2026 | Active | New data centers town-wide | Residents packed town hall to debate a proposed data center; board paused approvals through year end to study water and grid impacts | OKC FOX |
| Suffolk Virginia |
City | 2026-06-17 | Until permanent regulations adopted | Active | New data centers city-wide | Council directed an interim prohibition on data centers until permanent regulations addressing land use and utility demand are adopted | WHRO |
| Baltimore City Maryland |
City | 2026-06-16 | 1 year | Active | Data centers of 10 MW or greater | Council passed the pause in May and the mayor signed it June 16; halts large data centers while the city studies grid capacity, water use and land use | Baltimore Fishbowl / dcmap |
| Imperial County California |
County | 2026-06-16 | 45 days + extension; set aside by court Aug 28, 2026 | Lifted | All new/pending DC permits & entitlements in unincorporated areas (urgency interim ordinance) | Imperial County Superior Court set the urgency moratorium aside on Aug 28, 2026, finding the county failed to identify the current and immediate threat to public health, safety or welfare that state law requires; developer Sebastian Rucci brought the challenge. County staff are drafting a replacement moratorium addressing the court's findings | KPBS / The Desert Review |
| Superior Wisconsin |
City | 2026-06-16 | 1 year | Active | New data centers citywide (referred to Plan Commission) | Pre-emptive; define/classify DC uses, zoning, environmental/utility/infrastructure impacts | Superior Telegram / WPR |
| Versailles Kentucky |
City | 2026-06-16 | Through Dec 31, 2026 | Active | All data center permits, approvals, and development plans | Resolution 2026-8; modeled after Lexington; time for Planning Commission to review | LEX18 / WKYT |
| Merrillville Indiana |
Town | 2026-06-16 | 1 year | Active | All data centers | Effective June 1, 2026-May 31, 2027; study infrastructure, utilities, traffic, noise; learn from nearby project | NWI Times / NW Indiana Business |
| Henderson Nevada |
City | 2026-06-16 | 180 days (proposed) | Proposed | 180-day ban on conditional-use-permit applications for data centers (Bill 3927) | Introduced June 16; referred to July 21 council meeting; review energy/water/air/heat; early-lift provision to be added | Las Vegas Review-Journal / Nevada Independent |
| Fort Payne Alabama |
City | 2026-06-16 | 6 months | Active | All new data centers (M2 heavy industrial proposed) | Proactive; drafting zoning (conditional-use, 1,000-ft setback) before any proposal | Yellowhammer News / Times-Journal |
| Archuleta County Colorado |
County | 2026-06-16 | 6 months | Active | All data centers | Power and water draw concerns; county infrastructure and water cannot support a data center (Resolution 2026-47) | Pagosa Springs Sun |
| Madison County Indiana |
County | 2026-06-16 | 6 months (12-month extension pending Aug 4) | Active | All new data center development | Halt development while new zoning regulations are created; dozens of citizens backed extension; planning commission recommends extending to 12 months | Indiana Public Radio |
| Coweta County (2026) Georgia |
County | 2026-06-16 | 180 days | Active | New DC applications; 5 pending projects vested/exempt; $17B Project Sail campus | Review data center ordinance; organized neighbor opposition and 1,750-signature petition against Project Sail | Newnan Times-Herald |
| Garden City Georgia |
City | 2026-06-16 | 6 months | Active | New data centers citywide | Review impacts and consider zoning ordinance amendments before new projects arrive | The Current GA |
| Holly Springs North Carolina |
Town | 2026-06-16 | 12 months | Active | New data centers, data processing facilities and crypto mining (town limits + extraterritorial jurisdiction) | Council-led pause to study UDO amendments; water consumption, energy demand, traffic and noise impacts near residential areas; no new applications accepted | Town of Holly Springs / WRAL |
| Chikaming Township Michigan |
Township | 2026-06-16 | Moratorium (two ordinances) | Active | New data centers township-wide | Board adopted two moratorium ordinances to pause development while zoning standards on land use and utilities are written | Harbor Country News |
| Summit New Jersey |
City | 2026-06-16 | Permanent (proposed) | In Process | All data centers city-wide | Council took up a controversial ordinance prohibiting data centers, citing land use and utility impacts | TAPinto |
| North Tonawanda New York |
City | 2026-06-16 | Extended 1 year | Active | AI data centers city-wide | Council extended its existing pause another year while zoning standards on power and noise are developed | WIVB |
| Urbana Ohio |
City | 2026-06-16 | Permanent | Permanent Ban | Data centers removed as a permitted use in M-1 zoning | Council reversed an earlier zoning change (Ord. 4635-26), removing data centers as a permitted industrial use after resident opposition | Peak of Ohio |
| Desert Hot Springs California |
City | 2026-06-16 | 45 days + 22.5-month extension | Active | New data centers and high-intensity computing uses | Electrical demand, utility infrastructure, cooling, water consumption and public safety with no regulatory framework in city code; staff-led pause with resident support pushing for a full ban | KESQ |
| Bowling Green Kentucky |
— | 2026-06-16 | — | Rejected | City Commission again voted down a 6-month data center moratorium and gave final approval to data center regulations after a 4.5-hour, standing-room-only meeting June 16. | Bowling Green Daily News | |
| Boone County Indiana |
County | 2026-06-15 | 1 year | Active | All DCs in unincorporated areas + town of Advance; $10B Meta Lebanon LEAP campus unaffected (annexed) | APC recommended 6-0 May 6 (reaffirmed June 3 after public hearing); commissioners unanimously approved June 15, effective June 16; land use, infrastructure, utilities, agriculture, rural character study | Boone County IN / WTHR |
| Cumberland County North Carolina |
County | 2026-06-15 | 6 months | Active | Data center projects in unincorporated areas | Time to study impacts and develop regulations | CityView |
| Orion Township Michigan |
Township | 2026-06-15 | 6 months | Active | Data centers (not a ban; ordinance silent on use) | Time to draft zoning amendments (water/power); board can extend | Lake Orion Review |
| Roselle Park New Jersey |
Borough | 2026-06-15 | Permanent | Permanent Ban | All data centers (removed as permitted use) | Borough banned data centers by zoning amendment after residents pressed for answers on a neighboring Kenilworth project; cited land use and utility burden | TAPinto |
| Sayreville New Jersey |
Borough | 2026-06-15 | 18 months (proposed) | In Process | New data centers borough-wide | Council introduced an 18-month pause to study power demand, noise and land use before any application proceeds | MyCentralJersey |
| Broken Arrow Oklahoma |
City | 2026-06-15 | 6 months (extendable) | Active | New data centers city-wide | Council paused approvals through year end to study water, power and noise impacts and draft zoning standards | NewsOn6 |
| Anderson County Tennessee |
County | 2026-06-15 | 2 years | Active | New data centers county-wide | Commission adopted a two-year pause to write zoning regulations covering water, energy and noise impacts | WBIR |
| Wakulla County Florida |
County | 2026-06-15 | Permanent | Permanent Ban | Permitting, construction and operation of data centers county-wide | Depletion of local water and the power grid and protection of Wakulla Springs; a packed hearing applauded the vote after residents cited water use and environmental concerns | WCTV / Florida Politics |
| Montgomery County Maryland |
County | 2026-06-13 | 18 months (extended from 6 on Jul 28) | Active | New data centers county-wide (Expedited Bill 19-26) | Executive order pause in June extended by the council to 18 months on July 28 as a compromise between 6-month and 2-year proposals; cites environmental and community impacts and the need to get regulation right before facilities are built | Montgomery County Council |
| Lincoln Township Michigan |
Township | 2026-06-11 | 10 months | Active | Possible data centers | Planning commission to study noise, water and electrical consumption impacts | WSBT / WSJM |
| Center Township Pennsylvania |
Township | 2026-06-11 | TBD | Active | Data center development | Pause while developing regulations | Butler Eagle |
| Edmonson County Kentucky |
County | 2026-06-11 | 1 year | Active | New data centers, AI facilities and crypto mining operations | Fiscal court enacted a one-year pause covering data centers, AI facilities and crypto mining while zoning regulations are drafted | Edmonson Voice |
| Red Bank New Jersey |
Borough | 2026-06-11 | Permanent | Permanent Ban | All data centers borough-wide | Council banned data centers and called on the state to pause construction elsewhere, citing energy demand and ratepayer costs | ROI-NJ |
| Allegany New York |
Town | 2026-06-11 | Permanent | Permanent Ban | Data centers and crypto mining facilities in all zoning districts | Local Law 3 prohibits data centers and crypto mining town-wide, citing grid strain, noise and rural character | Olean Times Herald |
| Socorro County New Mexico |
County | 2026-06-10 | 1 year | Active | 10,000-acre Green Data Center proposal (Project Jupiter) | Commission unanimously approved 1-year moratorium June 10 after 2+ months of opposition; 80+ residents applauded | Albuquerque Journal |
| Box Elder County Utah |
County | 2026-06-10 | 180 days | Active | New DCs and DC power plants on unincorporated land (Stratos project exempt via MIDA) | Study zoning and development standards for data centers and power infrastructure; resident opposition to Stratos project (Ord. 654) | Salt Lake Tribune |
| Harford County Maryland |
County | 2026-06-10 | Permanent | Permanent Ban | All data centers county-wide (zoning code prohibition) | First Maryland county to ban data centers outright; county lacks electrical capacity for hyperscale load and officials cited energy price impacts on residents; grassroots group Our Land, Our Home, Our Harford organized opposition after a golf-course site was floated | Baltimore Sun / Harford County |
| Tallahassee Florida |
— | 2026-06-10 | — | Rejected | City Commission voted down a one-year moratorium on large-scale data centers and a companion definition ordinance, with the majority accepting staff's view that the land development code already bars data centers. Leon County unanimously adopted an 18-month moratorium a month later. | www.tallahassee.com | |
| Seattle Washington |
City | 2026-06-09 | 1 year (+6 mo extension possible) | Active | New or expanded DCs >20 MVA (~16,000 homes) | Enacted June 9 via CB 121214 (unanimous); 98,000+ emails, 50+ testified with none in favor; grid/water/rate/equity concerns; largest US city to pause data centers | Seattle City Council / GeekWire |
| Lexington Kentucky |
City | 2026-06-09 | Through Oct 31, 2026 | Active | New DC approvals (permits, dev plans, zone changes) | Fast-tracked resolution (rules suspended); ratepayer, water, energy concerns | Kentucky Lantern / WUKY |
| Charlotte North Carolina |
City | 2026-06-08 | 150 days | Active | New data centers (already-approved projects exempt) | 11-0 vote June 8 after May 11 reversal of mayoral block; electric/water cost concerns; time to draft siting rules | WBTV / WFAE |
| Edmond Oklahoma |
City | 2026-06-08 | Through end of 2026 | Active | All new data centers within city limits | Unanimous pause to study water supply, electrical infrastructure, zoning; 3 town halls planned | Oklahoma Energy Today / KFOR |
| Leeds Alabama |
City | 2026-06-08 | 1 year | Active | New data centers + expansions (Ordinance 2026-06-02) | Energy/water use, noise, environmental impacts, land-use compatibility | WBRC / ABC 33/40 |
| Nassau County Florida |
County | 2026-06-08 | Up to 12 months | Active | All DC/data processing/crypto mining applications (Ordinance 2026-044) | Water supply, power grid, environment; fact-finding committee formed | First Coast News / News4Jax |
| Flint Michigan |
City | 2026-06-08 | 12 months | Active | All data center permits, site plans and construction | Public outcry at hearings; study effects and review zoning codes and ordinances to recommend regulations | Flint Beat / Crain's Detroit |
| West Haven Connecticut |
City | 2026-06-08 | 1 year | Active | New data centers city-wide | Council paused applications to study energy demand, noise and land use and develop zoning standards | New Haven Register |
| Dane County Wisconsin |
County | 2026-06-04 | 18 months | Active | Hyperscale DCs (5,000+ servers, 10,000+ sq ft) in county-zoned towns | Study environmental, economic, health and safety implications; water usage, utility demand, noise and farmland protection | Isthmus / WisPolitics |
| Perth New York |
Town | 2026-06-04 | 1 year | Active | New data centers town-wide | Board adopted a one-year pause to study energy and water demand and write zoning regulations | Leader-Herald |
| Hill County Texas |
— | 2026-06-04 | — | Lifted | First Texas county moratorium (enacted May 12, 3-2) rescinded unanimously June 4 after RCM Hill LLC filed a $100M federal suit (May 27) alleging the county exceeded its lawful powers and threatened grid interconnection; county adopted a developer review checklist (water, traffic, noise, public notice) instead. Federal suit remains active. | Texas Tribune / KWTX | |
| McMinnville Tennessee |
City | 2026-06-03 | 18 months | Active | New DCs; Hixson Data Center (96,000 sq ft, 25 MW, Nvidia GB200) | ~3,000-signature petition; water/energy concerns; requires impact studies | WSMV / The UC Now |
| Imperial (City of) California |
City | 2026-06-03 | 45 days, extended through May 2027 | Active | New DCs + high-energy industrial/tech developments | Interim urgency ordinance No. 834 extended in July 2026 under Gov. Code 65858, freezing data center, battery storage and high-energy industrial approvals while the city reviews its general plan and land use classifications; driven by a wave of nearby proposals and resident concern over energy, water and health | KPBS Public Media |
| Scarborough Maine |
Town | 2026-06-03 | 180 days | Active | Scarborough Technology Park (52 acres) + new DCs; retroactive to Apr 1 applications | After Gov. Mills' statewide veto; water/wildlife/environmental concerns; zoning review | Portland Press Herald / WGME |
| Indio California |
City | 2026-06-03 | 45 days + 10.5-month extension | Active | All new data centers citywide | Coachella Valley opposition wave; extended July 15; Planning Commission recommends permanent ban (expected Oct/Nov 2026) | KESQ / The Indio Post |
| Holmes County Florida |
County | 2026-06-03 | 1 year + separate ban draft | In Process | AI data centers county-wide | Commission advanced a one-year pause and a separate ban draft citing water consumption and protection of rural land | WJHG |
| Brown County Wisconsin |
— | 2026-06-03 | — | Rejected | County committee declined to pursue a data center moratorium after being advised of legal limits on county zoning authority; residents continue pushing for action. | Daily Reporter | |
| Cortland Ohio |
City | 2026-06-03 | 1 year | Active | All zoning permits and applications for data centers | Zoning and land use gap: the city's zoning regulations predate data centers, so council proactively gave emergency passage to a pause while the planning and zoning department reviews and rewrites the rules | Tribune Chronicle |
| Newberry County South Carolina |
County | 2026-06-02 | TBD | Active | Data centers county-wide | Enacted after residents raised concerns and council voted down land sale to data center developer | WIS TV / SC Daily Gazette |
| Boulder County Colorado |
County | 2026-06-02 | Up to 6 months | Active | Data centers (and detention centers), unincorporated county | Land Use Code lacks definitions/regulations for data centers; natural resource and climate impacts; staff drafting code amendments | Boulder County |
| Augusta (Richmond County) Georgia |
City | 2026-06-02 | ~4 months (60-day extension Jul 21) | Active | New data centers (Hayne's Station project underway exempt) | Commissioners shelved draft DC rules after resident pushback on utility costs, water quality and a rushed process; extended pause 60 days for more community input | WRDW / The Augusta Press |
| Gorham Maine |
Town | 2026-06-02 | 180 days (extendable) | Active | New data centers town-wide | Council pause to study energy demand, noise and land use before zoning rules are adopted | The Cool Down |
| Filer Township Michigan |
Township | 2026-06-02 | 1 year | Active | New data centers township-wide | Board pause to develop zoning standards addressing land use, noise and utility demand | Michigan's Thumb |
| Virginia Beach Virginia |
City | 2026-06-02 | Ongoing | In Process | Future large-scale data centers city-wide | Council unanimously passed a resolution rejecting future large-scale data centers to resident applause; requires planning commission review and a final vote | WTKR |
| Ashwaubenon Wisconsin |
Village | 2026-06-02 | 12 months | Active | Hyperscale data center development | Plan Commission paused hyperscale development for a year to study land use, water and power impacts | NBC26 |
| Cedar Hill Tennessee |
City | 2026-06-01 | 2 years | Active | Data centers + cryptocurrency mining facilities | Electrical/water/wastewater, traffic, noise; protect rural character | WSMV / Main Street Media |
| Chesterfield County South Carolina |
County | 2026-06-01 | TBD | Active | Data centers county-wide | Ordinance enacted early June 2026 (exact date approx.); time to set local standards | SC Daily Gazette |
| Brunswick Maine |
Town | 2026-06-01 | 180 days | Active | Data centers 1 MW or greater | Study impacts and set regulations after Gov. Mills vetoed statewide data center pause | Portland Press Herald |
| Westbrook Maine |
City | 2026-06-01 | 180 days | Active | New and expanded data centers | Study power grid, environmental and quality-of-life impacts after state moratorium veto | Portland Press Herald |
| Skagit County Washington |
County | 2026-06-01 | 6 months (extendable +6) | Active | Unincorporated county; DCs >2,000 sq ft or >2 MW load | Protect farmland and water resources while drafting permanent regulations; farm groups testified in support | goskagit.com / Seattle Times |
| Howard County Maryland |
County | 2026-06-01 | Through Nov 2027 (CB31-2026) | Active | New data centers county-wide | Council pause covering energy, water and zoning while the county develops permanent standards | Fox Baltimore |
| Hillsborough North Carolina |
Town | 2026-06-01 | 60 days | Expired | New AI data centers town-wide | Short pause while the town assessed land use and utility impacts of AI data centers | Chapelboro |
| Hubbard Ohio |
City | 2026-06-01 | 12 months (emergency) | Active | New data centers city-wide | Council bypassed second and third readings to enact an emergency one-year pause amid resident concern over power and water demand | WFMJ |
| Grove City Ohio |
City | 2026-06-01 | 1 year | Active | New data centers city-wide | Council approved a one-year pause after a packed meeting, with residents citing noise, power demand and proximity to homes | ABC6 On Your Side |
| Braceville Township Ohio |
Township | 2026-06-01 | 6 months | Active | Permits and applications for data centers | Trustees proactively paused permits over noise and the electricity and water use of data centers raised across neighboring Trumbull County townships; no project had been proposed | Tribune Chronicle |
| Daviess County Kentucky |
County | 2026-05-29 | 12 months | Active | All DC applications and permits | Fiscal Court unanimously approved May 29 after first reading May 14; Owensboro Metropolitan Zoning Ordinance lacked DC provisions; resident testimony cited concerns | 14 News / Owensboro Times |
| Andover Township New Jersey |
Township | 2026-05-29 | Permanent ban | Permanent Ban | All DCs township-wide; 97-acre former Newton Airport site (248 Stickles Pond Rd) triggered action | Reversed prior support after chaotic May 7 meeting (police forcibly removed resident); standing ovation at ban vote | News 12 NJ / NJ1015 |
| Walton County Florida |
County | 2026-05-28 | Permanent ban sought | In Process | AI data centers county-wide | Commission directed staff to draft an outright ban after residents raised water use and environmental concerns; first reading held June 9 | WJHG |
| Madison Township Michigan |
Township | 2026-05-28 | 12 months | Active | New data centers township-wide | Trustees approved a one-year pause to write zoning rules on noise, water and power after resident concern | Daily Telegram |
| Huron County Michigan |
County | 2026-05-27 | 3 years (36 months) | Active | All data centers countywide | Planning Commission amended proposed 6-month to 36-month after public hearing; residents cited farmland preservation, resource use; ~20th Michigan community to pause DCs | Huron County View / Stateline |
| Bloomington Illinois |
City | 2026-05-26 | 6 months | Active | Data centers >5 MW capacity | Approved May 26 unanimously after 14 public commenters in support; potential hyperscale site near Central Illinois Regional Airport | Pantagraph / WGLT |
| Iron County Utah |
County | 2026-05-26 | 180 days | Active | New/incomplete DC proposals (Pronghorn exempt; BrightNight Red Butte paused) | Commissioners cited nonstop public calls/emails; max 180 days under Utah law; first Utah county to pause | Salt Lake Tribune / KSL |
| Dubuque County Iowa |
County | 2026-05-26 | 12 months | Active | All new data center proposals in unincorporated county | Supervisor McDonough amended proposed 120-day pause to 1 year after packed Zoning Board meeting brought out hundreds | KCRG / Telegraph Herald |
| Wright County Minnesota |
County | 2026-05-26 | 1 year (emergency) | Active | New data centers, unincorporated county | Emergency pause adopted to study water, energy and land use impacts ahead of anticipated proposals | Monticello Times |
| Otoe County Nebraska |
County | 2026-05-26 | Up to 1 year | Active | New data centers, unincorporated county | Board pause to study water and grid impacts and develop county zoning standards | Lincoln Journal Star |
| Harlingen Texas |
City | 2026-05-26 | 120 days | Expired | Potential data center projects city-wide | Council paused to study water, power and land use impacts of potential data centers before applications arrived | KRGV |
| Morris Connecticut |
Town | 2026-05-25 | 2 years | Active | New data centers; farmland sites | Planning & Zoning Commission pause to protect farmland and study water and energy impacts before zoning rules are written | New Haven Register |
| Washington Township (MI) Michigan |
Township | 2026-05-23 | 6 months | Active | New data centers township-wide | Board pause to study land use, noise and utility impacts and draft zoning standards | Detroit News |
| Minneapolis Minnesota |
City | 2026-05-21 | 6 months | Active | DCs >350,000 sq ft (downtown core and smaller DCs exempt) | Environmental impacts, permitting constraints, utility infrastructure; interim ordinance bypasses mayor | Star Tribune / KARE 11 |
| Cave City Kentucky |
City | 2026-05-20 | 12 months | Active | All DC applications/permits/expansions; associated high-impact industries | Strain on power grid and water resources; second reading passed special-called meeting | WBKO / WCLU Radio |
| Jefferson County Colorado |
County | 2026-05-19 | 10 months | Active | New DC applications in unincorporated areas (already-zoned PDs with 1,500-ft setback excluded) | Gather community input and develop policies; environmental impact amid Colorado drought | Jefferson County / Denver7 |
| Millville New Jersey |
City | 2026-05-19 | Permanent ban | Permanent Ban | 2.6M sq ft / 1.4 GW 'Millville Energy & Data Center Campus' on former Wheaton Industries glass factory site | CRAN-led grassroots campaign; 1.4 GW power load, billions of gallons of cooling water annually; brownfield reuse | News 12 NJ / ROI-NJ |
| St. Charles Missouri |
City | 2026-05-19 | Permanent ban | Permanent Ban | $1B CRG Cumulus DC proposal (Hwy 370 site); zoning code amendment | Made permanent the fall 2025 1-year moratorium; defines DCs in code and lists them as non-permitted in all districts; 4th permanent ban in US, 1st in Midwest | St. Louis Public Radio / KSDK |
| Meridian Township Michigan |
Township | 2026-05-19 | 6 months | Active | All data centers and battery storage facilities | Board adopted moratorium to study impacts; part of wave of Michigan township pauses | WKAR Public Media |
| Sanford Maine |
City | 2026-05-19 | 91 days (emergency) | Expired | Mousam River data center project | Emergency pause halting the Mousam River project while the city studied water withdrawal and river impacts | Portland Press Herald |
| Niles Ohio |
City | 2026-05-19 | 180 days (emergency) | Active | New data centers city-wide | Emergency pause adopted to study grid demand, water use and land use before applications proceed | Tribune Chronicle |
| Mount Carmel Township Pennsylvania |
Township | 2026-05-19 | 180 days | Active | New data center proposals township-wide | Supervisors paused proposals to upgrade zoning after residents raised land use and utility concerns | The News-Item |
| Lowell Township Michigan |
— | 2026-05-19 | — | Rejected | Township board rejected a proposed six-month moratorium; residents threatened a recall campaign in response | MLive | |
| Denver Colorado |
City | 2026-05-18 | 1 year | Active | Citywide (CoreSite construction exempt; subsequent phases halted) | Zoning, water, energy, affordability; Globeville/Elyria-Swansea community concerns | Denver7 |
| Normal Illinois |
Town | 2026-05-18 | 6 months | Active | All data centers (no inquiries yet) | Town Council unanimously passed May 18; preemptive moratorium following Bloomington-area DC interest | WGLT |
| Reno Nevada |
City | 2026-05-14 | Initial 30 days; extended through Aug 2027 | Active | New or expanded DCs; 4 pipeline projects exempt | First Nevada local government to pause DCs; council voted 6-1 on June 1, 2026 to extend through Aug 2027; cannot lift until new regulations adopted | Nevada Independent / KUNR |
| Porter Township Michigan |
Township | 2026-05-13 | 1 year (extendable +1 year) | Active | All data centers | Establish guidelines preemptively; protect water, farmland, light, noise; MI law bars outright bans | WNDU / ABC57 / WSBT |
| Penn Township Michigan |
Township | 2026-05-12 | 1 year (extended from 30-day interim) | Active | All DC development (rumored project) | Initial 30-day interim ban May 12; Planning Commission unanimously recommended 1-year non-zoning moratorium; Diamond Lake Association requested 2-year ban | WSBT / WNDU |
| Calipatria California |
City | 2026-05-12 | 5 years (interim urgency; hearing scheduled) | Proposed | Large-scale DC facilities (Salton Sea region) | Would be first Imperial County jurisdiction; council voted 3-2 on July 14, 2026 to bring permanent data center ban back for a final vote | Calexico Chronicle / KESQ |
| Union Township New Jersey |
Township | 2026-05-12 | Permanent ban (proposed) | Proposed | AI data centers in all zoning districts (in response to adjacent CoreWeave Kenilworth project) | Reaction to neighboring CoreWeave AI DC at former Merck property; first reading passed unanimously; second reading pending | TAPinto Union |
| Mansfield Massachusetts |
Town | 2026-05-12 | Permanent | Permanent Ban | Near-total ban on data centers town-wide | Town Meeting residents voted a near-total zoning ban, first in Massachusetts, over power and water demands | The Boston Globe |
| Rockdale County Georgia |
County | 2026-05-12 | 180 days + extension; lapsed Sept 8, 2026 | Expired | Data centers and battery energy storage systems | The data center and battery storage pause, adopted in January and extended in May, reached its Sept. 8 end date while the permanent replacement rules were not ready: commissioners deferred the second reading of Unified Development Ordinance Part 2, which carries the data center provisions, to Sept. 22 with the planning director calling the rewrite about 90% complete and the county still weighing a data center overlay district. No further extension was reported (unconfirmed) | Rockdale Citizen |
| Jackson Township (OH) Ohio |
Township | 2026-05-12 | 1 year | Active | New data centers township-wide (Res. 2026-049) | Trustees paused approvals to study land use, noise and utility impacts and develop zoning standards | 10TV |
| Inver Grove Heights Minnesota |
City | 2026-05-11 | 1 year | Active | 5 MW closed-loop DC; ~55,000 sq ft (5890 Carmen Ave) | Study suitable locations, zoning, regulations; UAE-linked Mubadala ownership concerns | CBS Minnesota / DCD |
| Smithfield Rhode Island |
Town | 2026-05-07 | Permanent ban | Permanent Ban | All data centers; zoning amendment lists DCs as 'not permitted' in all districts | Concerns over water, grid, health, economy; developer threatened lawsuit | WPRI / Ocean State Media |
| EBCI (Cherokee) North Carolina |
Tribal Council | 2026-05-07 | Indefinite | Permanent Ban | All data centers on EBCI lands (Ordinance No. 158 (2026)) | Sparked by nearby Marble DC; tribal water/fishing concerns; coordinated with Indigenous Environmental Network | Cherokee One Feather / WHQR |
| Tazewell County Illinois |
County | 2026-05-07 | Until new ordinance adopted | Active | Large-scale data centers, unincorporated county | Board paused approvals while crafting a data center zoning ordinance covering water and energy demand | 25 News Now |
| Lysander New York |
Town | 2026-05-07 | 6 months | Active | New data centers town-wide | Board pause after residents spoke out against a project proposal, citing grid demand, noise and rural land use | InformNNY / Syracuse.com |
| Camdenton Missouri |
City | 2026-05-05 | 1 year (up to 12 months) | Active | All data center approvals | Time for comprehensive review (zoning, grading, site plan, conditional use, utility cost recovery) | ABC17 / Lake News Online |
| Camden County Georgia |
County | 2026-05-05 | 6 months | Active | Unincorporated county only (cities exempt) | First Georgia coast county to adopt; Navy Sub Base Kings Bay commander expressed concern | WABE / GPB |
| Colleton County South Carolina |
County | 2026-05-05 | 6 months (proposed) | In Process | Large DCs; reconsidering zoning that enabled 1 GW ACE Basin proposal | First reading May 2026 (date approx.); protect environmentally sensitive ACE Basin | Bluffton Today / SC Daily Gazette |
| Bulloch County Georgia |
County | 2026-05-05 | Extension through Dec 31, 2026 | Active | New data centers county-wide | Commissioners extended the existing pause while debating a full ban; residents raised water and power supply concerns | WSAV |
| Harnett County North Carolina |
County | 2026-05-04 | 1 year | Active | All data centers | Allow staff to research and update UDO; preempt by-right development under conditional zoning | Sanford Herald / Daily Record |
| Northampton County North Carolina |
County | 2026-05-04 | 32 months | Active | Data centers, crypto mining, high-impact data processing | Petition with 300 signatures pushed for longer pause; advisory committee to be established; study impacts and draft ordinance | NC Health News |
| Durham North Carolina |
City | 2026-05-04 | 12 months (extended from 60 days) | Active | All data centers, data processing, cryptocurrency mining | Time to study impacts; extended from 60 days to 12 months June 15, 2026; Durham County weighing separate county moratorium (earliest vote July 13) | WRAL / Indy Week |
| Spring Hope North Carolina |
Town | 2026-05-04 | 1 year | Active | All data centers within town limits and ETJ (Resolution 2026-01) | Mayor cited intense energy use, limited local jobs; out-of-state contractors | Spring Hope Enterprise |
| Waite Park Minnesota |
City | 2026-05-04 | 1 year | Active | New data centers city-wide | Council pause to study water and electricity demand and write zoning standards before applications arrive | KNSI |
| Lonsdale Minnesota |
City | 2026-04-30 | 1 year | Active | All data centers within city limits | Unanswered questions on water/energy impacts; NDA-related transparency concerns; 'we need to do this right' | Southern Minn |
| Oliver County North Dakota |
— | 2026-04-30 | — | Lifted | 180-day moratorium enacted Mar 10, 2026; commissioners unanimously repealed at special meeting Apr 30 (~50 days into 180-day term). Applied Digital filed rezoning application May 2. | KFYR-TV | |
| Maine (LD 307) Maine |
— | 2026-04-29 | — | Rejected | Gov. Mills vetoed first-in-nation statewide moratorium on Apr 24; Legislature failed to override (House 72-65, short of 2/3) on Apr 29. Bill would have banned >20 MW DCs until Nov 2027. | Maine Morning Star | |
| Apex North Carolina |
Town | 2026-04-28 | 1 year | Active | 250 MW (Natelli project withdrew) | Establish data center regulations; developer withdrew 250 MW project after community opposition | WUNC / WRAL |
| Manitowoc County Wisconsin |
County | 2026-04-28 | 18 months | Active | Data centers >1 petabyte storage | Petition by Two Creeks, Two Rivers, Mishicot; environmental impact, farmland loss | Wisconsin Public Radio |
| Boardman Township Ohio |
Township | 2026-04-28 | 1 year | Active | All data center development township-wide | Proactive, official-led zoning pause: trustees cited noise, energy use and rising water and electricity costs, and wanted land-use rules written before a project could be shoehorned in | The Vindicator |
| Calhoun Georgia |
City | 2026-04-27 | 90 days + extension to Jan 1, 2027 | Active | All new data centers (preemptive) | Preemptive moratorium extended ~6 months to assess zoning ordinances; 500,000 sq ft / 11-acre DC proposal off Hwy 53 pending despite moratorium | Northwest Georgia News / Gordon Gazette |
| Weaverville North Carolina |
Town | 2026-04-27 | Permanent ban | Permanent Ban | Data centers and crypto mining (classified as noxious uses) | Limited resources; classified as noxious uses harmful to health/environment | WLOS |
| Lake Township Ohio |
Township | 2026-04-27 | 6 months | Active | All new data centers | Response to potential DC site advertised at Latcha/Tracy Rd; need DC section in zoning resolution | The Press (Press Publications) |
| Ypsilanti Comm. Utilities Auth. Michigan |
Special District | 2026-04-22 | 12 months | Active | Hyperscale, AI, HPC facilities (water/sewer) | Water supply, wastewater, infrastructure capacity; township resolution 2026-08 request | WEMU / Planet Detroit |
| Monroe Township New Jersey |
Township | 2026-04-22 | Permanent ban | Permanent Ban | ~1M sq ft proposed DC (application denied) | Two ordinances prohibiting DCs adopted Apr 22; effective May 13 | CBS Philadelphia / Pinelands Alliance |
| Swain County North Carolina |
County | 2026-04-21 | 12 months | Active | All new data centers | 140-resident public hearing; community concerns over water, electricity, character | Blue Ridge Public Radio |
| Orange County North Carolina |
County | 2026-04-21 | 1 year | Active | Large-scale data centers (AI, processing, crypto mining) | Air/noise pollution, water and power consumption costs; staff time to draft regulations | WRAL / WUNC |
| Rosemount Minnesota |
City | 2026-04-21 | 1 year | Active | All new DCs (existing Meta UMore Park campus exempt) | 1-year max under MN state statute; study impacts and create regulations | Sun This Week / DCD |
| Oklahoma City Oklahoma |
City | 2026-04-21 | Through end of 2026 | Active | All new DC construction/expansion (rezoning); 2 pending cases exempt | Rapid growth; community concerns over electricity, water; staff to develop regulations | KGOU / City of OKC |
| Rowan County North Carolina |
County | 2026-04-20 | 1 year | Active | New data centers (existing project exempt) | 100+ residents opposed; re-ratified May 4 (quorum issue); water/power concerns | Salisbury Post / WFAE |
| Clyde North Carolina |
Town | 2026-04-16 | 12 months | Active | All new data centers (preemptive) | Following Canton public hearing; concerns over electricity, water; preemptive action | Smoky Mountain News |
| Cassville (Town of) Wisconsin |
Town | 2026-04-16 | Up to 2 years | Active | All data centers in township | Property values, well contamination, electric bills; rural opposition | Wisconsin Watch |
| Twinsburg Ohio |
City | 2026-04-14 | 1 year | Active | All new data centers | Council enacted a 12-month pause on data center zoning and occupancy permits after extensive public comment, citing energy demand, water use, infrastructure and environmental impacts while zoning is evaluated | City of Twinsburg (Ord. 2026-065) |
| Olyphant Pennsylvania |
Borough | 2026-04-14 | 180-day curative amendment window | Superseded | Roughly 1,000 acres of CM-2 land near Triboro Industrial Park, about 29% of the borough | Grassroots opposition over transparency, health, water, wildlife, property values and utility costs, organized as Stop Olyphant Data Centers with more than 1,600 members: council rejected a data center zoning amendment 4-3 and declared a curative amendment giving it 180 days to rewrite the zoning, but the window ended early when council voted 6-0 on June 9 to settle a developer lawsuit and stipulate that its initial vote had validly adopted the zoning | FOX 56 (WOLF) |
| Bangor Maine |
City | 2026-04-13 | 6 months (180 days) | Active | All new data centers | Council needs time to develop data center regulations; water and power concerns | Bangor Daily News |
| Athens-Clarke County Georgia |
— | 2026-04-09 | — | Lifted | Emergency moratorium adopted Dec 2025, extended Mar 2026; lifted Apr 9, 2026 and replaced with permanent regulations (closed-loop cooling required; on-site clean energy for >5 MW centers) | WUGA | |
| Massillon Ohio |
City | 2026-04-06 | 180 days | Active | All new data centers citywide | Add data center rules to zoning code; heavy-industrial-only siting and 400-ft residential setbacks under study (Aug 3 zoning vote) | Massillon Independent / The Cool Down |
| Tulsa Oklahoma |
City | 2026-03-26 | 9 months | Active | All new hyperscale data centers | Zoning review; noise, water, energy impacts | KJRH |
| Adair County Iowa |
County | 2026-03-25 | Indefinite | Active | 200 MW proposed; all DCs in unincorporated areas | Community opposition; Applied Digital 200 MW proposal | Creston News |
| Boone North Carolina |
Town | 2026-03-24 | 1 year | Active | All data center development | Community concerns | WFDD |
| Washington County Tennessee |
County | 2026-03-24 | ~15 months | Active | Data centers and crypto mines | Forbids construction, operation, permitting | SuperTalk 92.9 |
| Dunn County North Dakota |
County | 2026-03-24 | 12 months | Active | Data centers, solar farms, battery storage | Permit ordinance development; land use study | KFYR TV |
| Wixom Michigan |
City | 2026-03-24 | 6 months (ended early Aug 25, 2026) | Lifted | Contested project: 519,400 sq ft on 54-55 acres (Midwinds Park) | Zoning gap on power, water and noise; ended early and replaced with permanent zoning making data centers a special land use in M-1/M-2 only, with residential setbacks, sound studies and decommissioning rules, while a federal lawsuit challenges the pause | City of Wixom / Detroit News |
| Detroit Michigan |
City | 2026-03-17 | 2 years (proposed) | Proposed | All data centers | No DC zoning ordinance; grid stability, water, noise, economic impacts | Planet Detroit |
| East Lansing Michigan |
City | 2026-03-17 | 6 months | Active | All data centers (no proposals pending; preemptive) | No existing DC zoning ordinance; proactive community protection; city staff to craft regulations | WKAR |
| Lowell Massachusetts |
City | 2026-03-10 | 1 year (+180-day extension possible) | Active | All data centers (targets Markley 352,000 sq ft facility) | Diesel generators, water towers, noise; state's first DC moratorium | NBC Boston |
| Oliver County North Dakota |
County | 2026-03-10 | ~50 days (repealed early) | Lifted | All data centers | REPEALED Apr 30, 2026 unanimously at special meeting; Applied Digital filed rezoning May 2 | KFYR-TV |
| Prince William County Virginia |
County | 2026-03-04 | Ongoing | Partially Enacted | 22M sq ft Digital Gateway | Environmental, Manassas Battlefield | InsideNova |
| Mercer County North Dakota |
County | 2026-03-04 | 1 year | Active | 530+ acres (NextEra/Boulevard Associates NDA-shrouded land) | Lack of transparency; NDA-shrouded land purchases; landowner protection concerns | Bismarck Tribune |
| Fulton County Indiana |
County | 2026-03-03 | 1 year | Active | 500 MW; 300-acre campus | Water/electricity strain | WNDU |
| Ypsilanti Michigan |
City | 2026-03-03 | 60-day emergency + 365-day resolution | Active | All data centers (preemptive) | No existing DC zoning; preemptive community protection; 57 resident emails in support | WEMU |
| Birmingham Alabama |
City | 2026-03-03 | 6 months; replaced by permanent zoning ordinance | Restrictions Added | >20 MW data centers (DC Blox & Nebius AI Factory exempt) | Six-month pause expired Sept. 3, 2026 and was replaced by the zoning ordinance council approved 6-3 on June 9: 20 conditions billed as Alabama's toughest, banning on-site power generation, requiring closed-loop cooling to limit water use, adding lighting rules and a 500-foot residential setback. No pause remains in effect | Birmingham Watch |
| Franklin County Missouri |
— | 2026-03-01 | — | Lifted | Six-month pause lifted | Sierra Club | |
| Dearborn County Indiana |
County | 2026-02-24 | Up to 1 year | Active | Data centers, solar, battery storage | Rezoning moratorium | Good Jobs First |
| Cobb County Georgia |
County | 2026-02-24 | 180 days + 6-month extension (Aug 11, 2026) | Active | New data center applications (unincorporated areas) | Study noise pollution, air quality from cooling systems and backup generators; commissioners voted unanimously on Aug 11, 2026 to extend six months while data center rules are folded into the proposed Unified Development Code, the 1972 code giving no consideration to this modern land use | East Cobb News |
| Pemberton Township New Jersey |
Township | 2026-02-20 | Permanent ban | Permanent Ban | All data centers (Ord. 10-2026) | First NJ municipality to ban | Common Dreams |
| Champaign County Illinois |
County | 2026-02-19 | 12 months | In Process | 10,000+ sq ft processing area | Task force for zoning standards | IPM Newsroom |
| South Dakota (SB 232) South Dakota |
— | 2026-02-18 | — | Rejected | One-year hyperscale DC moratorium tabled in committee; SD SB 135 (local control + infrastructure requirements) signed instead | Legiscan / Route Fifty | |
| New Brunswick New Jersey |
— | 2026-02-18 | — | Rejected | 27,000 sq ft AI DC at 100 Jersey Ave unanimously killed by City Council after CRAN-led campaign and hundreds at meeting; site to become public park + 600 apartments + small business warehouses | Patch / Common Dreams | |
| Eagan Minnesota |
City | 2026-02-17 | 1 year | Active | >20 MW or within 500 ft of residential | First MN city moratorium; size + proximity-based; study water, noise, electrical, PUC role | Star Tribune / KARE 11 |
| Chatham County North Carolina |
County | 2026-02-11 | 12 months | Active | DCs, data processing, crypto mining | Study impacts; develop zoning | WRAL |
| Hood County Texas |
— | 2026-02-10 | — | Rejected | 3-2 vote; state senator threatened legal action | Texas Tribune | |
| Sterling Heights Michigan |
City | 2026-02-04 | 1 year | Active | All data centers | Zoning ordinance from 1978; need resource and noise impact study | CBS Detroit |
| Muhlenberg Township Pennsylvania |
Township | 2026-02-03 | 12 months | Active | Pacifico Energy DC + power plant | 700+ petition signatures; pending state legislation | Circleville Herald / DCD |
| Mason (City) Michigan |
— | 2026-02-03 | — | Lifted | Moratorium enacted Jan 6, 2026; lifted Feb 3 after M-3 Technology Innovation District zoning adopted 5-2. Ordinance later suspended by citizen petition (755 signatures) on March 2. | WILX | |
| Canton North Carolina |
Town | 2026-02-01 | 1 year | Active | All data center projects | Described as 'threat to community' | Fox Carolina |
| Cincinnati Ohio |
City | 2026-02-01 | Extended through Dec 31, 2026 | Active | All new data center construction (downtown, industrial, manufacturing zones) | Zoning study; no existing DC classification in city code; 22,000+ parcels under review | WCPO / WVXU |
| Marengo Township Michigan |
Township | 2026-02-01 | 1 year (extendable) | Active | All data centers (preemptive) | Increasing data center developments across MI; need for regulations; Ordinance 2026-1 | Marengo Township |
| New Orleans Louisiana |
City | 2026-01-28 | 1 year | Active | All data center projects citywide | Data centers not defined in city code | WWNO |
| Larimer County Colorado |
County | 2026-01-27 | Extended to Feb 25, 2027 | Active | All data center facilities in unincorporated county | No data center definitions in the land use code; commissioners extended the pause on July 13, 2026 from August 2026 to February 2027 to give staff more time to draft definitions and standards covering water, electricity and noise. No site-specific application has been filed | KUNC / Larimer County |
| Pontiac Michigan |
City | 2026-01-21 | 6 months | Expired | All data centers | No existing zoning; public health, utility and infrastructure concerns. The six-month council moratorium, expressly extendable, lapsed around July 21, 2026 with no extension or replacement zoning ordinance located | Detroit News |
| Monterey Park California |
City | 2026-01-21 | 1 year (extended from 45-day) | Active | 250,000 sq ft; 15.8-acre hyperscale (Saturn Park) | Environmental impacts; community opposition; ballot measure for permanent ban pending | Data Center Dynamics |
| Sedgwick County Kansas |
County | 2026-01-15 | ~8 months (2x extended) | Active | 1,000+ acres proposed | Zoning regulation review | KWCH |
| Baltimore County Maryland |
County | 2026-01-15 | 90 days + study | Active | 42-acre Woodlawn site; 150 MW | Grassroots opposition; conversion of vacant building | The Banner |
| Harvey County Kansas |
County | 2026-01-13 | ~3 years | Active | Unincorporated areas | Regulations research | KWCH |
| Madison Wisconsin |
City | 2026-01-13 | 1 year | Active | Telecom facilities >10,000 sq ft (incl. potential $15B Vantage/OpenAI/Oracle campus) | Pause to study impacts and develop permitting procedures | Captimes / Spectrum News |
| Springfield Twp. Michigan |
Township | 2026-01-07 | 180 days | Expired | 84-acre proposed campus; 2-3 250k sq ft buildings | Township 'unprepared'; no zoning standards for data centers. The 180-day pause lapsed in mid-2026 with no extension resolution located and no permanent ordinance adopted; the planning commission's draft framework was still in progress | Detroit News |
| Northville Michigan |
City | 2026-01-06 | 12 months | Active | All data centers (preemptive) | Preemptive protection; infrastructure impacts | Planet Detroit |
| Jerome Township Ohio |
Township | 2026-01-01 | 9 months | Active | All new data centers | Renewed zoning review | 10TV |
| Lordstown Ohio |
Village | 2026-01-01 | Temporary | Active | All data centers | Legal battle with developer | Tribune Chronicle |
| DeKalb County Georgia |
County | 2025-12-16 | ~13 months (4x extended) | Active | 1M sq ft on 95 acres | Health and cost concerns; residents opposition; extended July 7, 2026 through early 2027 (4th extension) with more departments directed to study impacts; weighing SLUP for 2M sq ft Ellenwood facility | Decaturish |
| Starke County Indiana |
County | 2025-12-15 | 12 months | Active | Hyperscale data centers | Light pollution, environmental impacts | Inside Indiana Business |
| Gates County North Carolina |
County | 2025-12-01 | 12 months | Active | All data center approvals | Community opposition | Albemarle Observer |
| Howell Township Michigan |
Township | 2025-11-21 | 6 months | Expired | $1B Meta hyperscale campus (1,000+ acres proposed) | Community opposition; 1,000+ acre agricultural rezoning | Michigan Advance |
| Johnson County Iowa |
County | 2025-11-07 | 1 year | Active | All DCs in unincorporated areas | Power and water usage concerns; zoning development | Radio Iowa |
| Coweta County Georgia |
— | 2025-11-03 | — | Expired | Moratorium expired; drafting permanent ordinance | GPB News | |
| Putnam County Indiana |
County | 2025-11-01 | 1 year | Active | Wind, solar, data centers, SMRs | Water, land use, transparency | Ink Free News |
| White County Indiana |
County | 2025-10-20 | Temporary | Active | Hyperscale data centers | Water availability; developer transparency concerns | Daily Journal |
| Jerome Township Ohio |
Township | 2025-09-03 | 9 months | Expired (renewed in 2026) | Up to 4 data center projects | Rapid growth concerns | WOSU |
| Prince George's Co. Maryland |
County | 2025-09-01 | 180 days | Expired (led to regulations) | $5B Landover project | Community blindsided by approval; 460-page task force report | NBC Washington |
| Pike County Georgia |
County | 2025-09-01 | Temporary | Active | All data centers | Part of GA county restriction wave | GPB News |
| Lamar County Georgia |
County | 2025-09-01 | Temporary | Active | All data centers | Part of GA county restriction wave | GPB News |
| Troup County Georgia |
County | 2025-09-01 | Temporary | Active | All data centers | Part of GA county restriction wave | GPB News |
| LaGrange Georgia |
City | 2025-09-01 | Temporary | Active | All data centers | Part of GA county restriction wave | GPB News |
| Warrenton Virginia |
Town | 2025-07-01 | Permanent ban | Permanent Ban | 220,000 sq ft on 42 acres | Voter-driven opposition | Fauquier Now |
| Johnson City Tennessee |
City | 2025-06-05 | 1 year (extended to Dec 3, 2026) | Active | Data centers and bitcoin mines; land use applications and building permits in I-2 heavy industrial district | Moratorium extended unanimously in May 2026 while a task force of city staff and residents drafts noise caps and residential setbacks; a city survey found over 5,000 of 6,000 respondents 'extremely concerned' about a data center | WJHL / Johnson City Press |
| Ypsilanti Michigan |
— | 2025-05-03 | — | Expired | 60-day emergency moratorium expired | Eastern Echo | |
| Loudoun County Virginia |
County | 2025-03-18 | Ongoing | Restrictions Added | Eliminated by-right development | Long community opposition; eliminated by-right development | Holland & Knight |
| Ypsilanti Michigan |
City | 2025-03-03 | 60 days (initial) | Expired (renewed in 2026) | U of Michigan / Los Alamos DC | $100M state grant; community opposition | Eastern Echo |
| Marshall County Indiana |
County | 2025-02-01 | 1 year | Expired | Hyperscale data centers | First in Indiana; concerns from Amazon 2,250 MW proposal nearby | Inside Indiana Business |
| Coweta County Georgia |
County | 2024-11-01 | ~1 year | Expired (drafting ordinance) | All data centers | Community opposition | GPB News |
| Atlanta (Beltline) Georgia |
City | 2024-10-01 | Ongoing | Restrictions Added | 22-mile Beltline radius; 730 MW usage | 211% growth; water scarcity; special use permits required | GPB News |
| St. Charles (2023) Missouri |
City | 2023-08-22 | 1 year (then permanent ban proposed) | Superseded | 440-acre 'Project Cumulus' | Construction dust, energy, wildlife, water pollution | KSDK |
| Chandler Arizona |
City | 2023-01-05 | Ongoing restrictions | Restrictions Added | Limits DCs to planned developments only | Noise, limited job creation, community opposition | Chandler AZ Gov |
Aggregated from Interconnected Capital — US Data Center Moratorium Tracker · datacenterbans.com — State-level legislation tracker. Refreshed weekly (Mondays). Local moratoria change fast and are frequently extended, shortened, repealed, or litigated — confirm against the linked source and the jurisdiction's own ordinance before relying on any single row.
Oct. 16 morning refresh: no new verified developments found since the Oct. 15 update; prior items stand. Outcome of San Antonio UDC vote (Oct. 15) not confirmed from a primary source (KSAT Oct. 14 preview only). Watch: Memphis vote Oct. 20. PJM RBP re-timing and SEPA DELTa Q3 release still not located. Prior: Oct. 15 morning refresh: no new verified developments found since the Oct. 14 update; prior items stand. Outcomes of Oct. 13 local votes (Fort Wayne, Leon County FL, Buffalo) and the TWDB Oct. 14 compliance report still not confirmed from primary sources. Watch today: San Antonio UDC vote (Oct. 15); Memphis vote Oct. 20. PJM RBP re-timing and SEPA DELTa Q3 release still not located. Prior: Oct. 14 morning refresh: no new verified developments found since the Oct. 13 update; prior items stand. Outcomes of Oct. 13 local votes (Fort Wayne, Leon County FL, Buffalo) and the TWDB Oct. 14 compliance report not confirmed from primary sources. Watch: San Antonio UDC vote Oct. 15; Memphis vote Oct. 20. SEPA DELTa Q3 release still not located. Prior: Oct. 13 morning refresh: no new verified developments found since the Oct. 12 update; prior items stand. Watch today: Fort Wayne, Leon County FL and Buffalo local votes (Oct. 13); TWDB compliance report due Oct. 14; San Antonio UDC vote Oct. 15; Memphis vote Oct. 20. SEPA DELTa Q3 release still not located. Prior: Oct. 12 morning refresh: Oakland and San Francisco each approved 45-day data center moratoriums on Oct. 6 (unanimous; SFist); Manatee County, Fla. approved a one-year moratorium unanimously (reported Oct. 8; MySuncoast). Still unconfirmed from primary sources: Milwaukee outcome, Grant County NM Oct. 8 vote, PJM RBP timing after Oct. 7 MIC, SEPA DELTa Q3 release (not located). Memphis vote rescheduled Oct. 20. Prior: Oct. 9 morning refresh: Raleigh, N.C. council approved a six-month data center moratorium 7-1 on Oct. 6 (Axios Raleigh); Memphis moratorium vote was halted amid protests and moved to Oct. 20 (WSMV). Still unconfirmed from primary sources: Manatee, Oakland, Milwaukee Oct. 6 outcomes, Grant County NM Oct. 8 vote, PJM RBP timing, SEPA DELTa Q3 release. Prior: Oct. 8 morning refresh: no new verified developments found since the Oct. 7 update; prior items stand. Still unconfirmed from primary sources: outcomes of Oct. 6 votes (Memphis, Raleigh, Manatee, Oakland, Milwaukee), PJM RBP timing update (Oct. 7 MIC), SEPA DELTa Q3 release. Prior: Oct. 7 morning refresh: new local moratoria reported - Anne Arundel County, Md. (15 months) and Delphos, Ohio (18 months); details unverified. Outcomes of Oct. 6 votes in Memphis, Raleigh, Manatee, Oakland and Milwaukee not yet confirmed from a primary source. PJM RBP timing update still pending (MIC Oct. 7); PJM Inside Lines shows no new RBP item. SEPA DELTa Q3 release still not located. Prior: Oct. 6 morning refresh: no new verified developments found since the Oct. 2 update; prior items stand. Watch today: Memphis, Raleigh, Manatee, Oakland, Mendocino and Milwaukee committee votes; PJM MIC RBP timing update Oct. 7. SEPA DELTa Q3 release still not located. Prior: Oct. 2 morning refresh: Pennsylvania PUC approved (Oct. 1) a Tentative Order on emergency load control that would curtail large new loads lacking secured capacity before other customers (Docket M-2026-3064961; final order targeted Jan. 28, 2027). No other new verified developments found. Prior: Oct. 1 evening spot-check: Senate failed 57-43 (60 needed) to advance the House-passed Ratepayer Protection Act (H.R. 9340) on Sept. 30; bill stalled. Oct. 1 morning refresh: no new verified developments found since the Sept. 30 update; prior items stand. Sept. 30 (evening): FERC approved most of PJM's Reliability Backstop Procurement (ER26-3380) on Sept. 29 but suspended it for five months; PJM said the Sept. 30 bid window will not open, new timing TBD (update Oct. 7 MIC). Earlier Sept. 30: Buffalo's Common Council approved a resolution for a two-year pause on new data centers and a nine-member task force (Sept. 29). It is a resolution, not yet a local law; the mayor is reviewing it with Corporation Counsel. Pulaski County, Ark.'s county judge vetoed the Quorum Court's data center ordinance (Sept. 25; backfill), and an override vote is expected. Saginaw, Mich. adopted special-land-use rules effective Oct. 9. Xcel's SPS filed a large-load tariff at the PUCT (Docket 60332). Watch: PJM governance deadline and RBP window open today, MISO parallel-study filing due today, FL/TVA/WA/PA deadlines Oct. 1. SEPA DELTa Q3 release still not posted on the last day of Q3. — additions since Sep 1–Oct 16 (last 45 days)
MySuncoast (Oct. 8, 2026) reports a unanimous vote for a one-year moratorium on new data center projects; the article gives the vote as 'Thursday' (Oct. 8) rather than the Oct. 6 date previously tracked, and states no ordinance number or tally. Ordinance 26-42 linkage is from earlier coverage.
SFist (Oct. 7, 2026): SF measure (Supervisors Walton, Chan, Fielder, Chen) effective immediately and unanimous; Oakland council moratorium (Councilmember Fife) unanimous. Neither article gives a numerical tally or ordinance number; dates inferred from 'Tuesday' in an Oct. 7 article.
Raleigh: Axios Raleigh (Oct. 7, 2026) reports council approved the moratorium 7-1 (Christina Jones opposed), expiring April 6, 2027; ordinance number and effective date not stated. Memphis: WSMV (Oct. 7, 2026) reports the council halted its Oct. 6 meeting after disruptions and delayed the vote to Oct. 20; ordinance scope not described in that report. Other Oct. 6 votes (Manatee, Oakland, Milwaukee) remain unconfirmed.
Per local headlines: Anne Arundel County Council approved a 15-month data center moratorium (Baltimore Sun, Oct. 5, 2026); Delphos City Council approved an 18-month moratorium (WLIO/Hometown Stations, Oct. 5-6, 2026). Vote counts, bill/ordinance numbers and effective dates were not retrievable (Baltimore Sun blocks automated fetch; Delphos item is a video story) and are carried as unverified. Not yet in the national moratorium census; will reconcile at the Monday census refresh.
At its Oct. 1, 2026 public meeting the PA PUC approved a Tentative Order (reported 4-0; the Sept. 2026 directing motion was 5-0) revising emergency electric load control regulations under Docket M-2026-3064961 (docket number per PA Environment Digest; PUC primary page not retrieved). Under the proposal, certain large new loads that have not secured sufficient new capacity would be curtailed before other customers when further reductions are needed. Initial comments are due 30 days after Pennsylvania Bulletin publication, replies 15 days later; Final Order anticipated Jan. 28, 2027. Vote and docket verified from secondary sources only.
On Sept. 30, 2026 the Senate held a cloture vote on the motion to proceed to the House-passed Ratepayer Protection Act and it failed 57-43, three votes short of the 60 required (Roll Call, CNN, The Hill and others report the tally; per Daily Signal, four Democrats — Hassan, Klobuchar, Warnock and Ossoff — voted with Republicans). The House passed the bill 417-3 on Sept. 16. The bill directs state commissions to consider federal large-load cost-allocation standards (PURPA Sec. 111(d)) for data centers; it does not mandate any particular standard. Roll Call reports it remains stalled as senators leave Washington to campaign. Not law.
On Sept. 29, 2026, FERC issued an order in Docket ER26-3380 accepting the bulk of PJM's one-time Reliability Backstop Procurement while suspending implementation for five months (effective date Feb. 28, 2027, subject to refund and further proceedings) as it examines whether several elements are just and reasonable. Utility Dive reports FERC flagged three issues: cost allocation (suggesting updated load forecasts), transmission-owner exit cost assignment, and load-serving-entity collateral requirements. FERC Chair Laura Swett was quoted criticizing the filing as a 'mess' and an 'eleventh-hour' mechanism. PJM said the RBP 'will not begin on Sept. 30' and actual timing is to be determined, with an update promised at the Oct. 7 Market Implementation Committee meeting. The previously tracked Sept. 30-Oct. 21 offer window and early-December results date are therefore no longer operative.
On Sept. 29, 2026, the Buffalo Common Council approved North District Council Member Joe Golombek's resolution calling for a two-year moratorium on new data centers and no expansions of existing data processing centers, while the city updates zoning, property tax and other codes. An amendment adds a nine-member data center task force. Mayor Sean Ryan said he shares the concerns and supports the state's Responsible Data Center Development Act, and is reviewing the resolution with Corporation Counsel before deciding how to proceed. City lawyers and council members are expected to draft a local law amending the city code, with council consideration at its next meeting in about two weeks. This sits on top of New York's one-year statewide pause on new hyperscale data centers.
Southwestern Public Service Co. (SPS), Xcel Energy's Texas–New Mexico subsidiary, filed a proposed large-load tariff with the Public Utility Commission of Texas in Docket 60332 (reported Sept. 29, 2026). Large customers such as data centers would pay the incremental cost of transmission, substations, interconnection upgrades and new generation built to serve them. They would generally commit for at least 15 years, post financial security, pay minimum monthly charges on infrastructure built for them even while load ramps, and pay exit and termination charges if a project is delayed, downsized or abandoned. PUCT approval is required; coverage expects a decision timeline into 2027. Xcel says it will file a similar tariff with the New Mexico PRC. SPS serves the Texas Panhandle and South Plains, which sit in SPP rather than ERCOT.
On Sept. 28, 2026, Saginaw City Council voted 8-0 to adopt a 10-page data center ordinance. Data centers become special land uses allowed only in light and general industrial districts, needing zoning administrator review and Planning Commission approval. Applicants must file reports on water use (yearly, monthly, daily and peak), wastewater, energy demand, noise, tree preservation, heat mitigation, emergency response and decommissioning, and pay for any needed public water or wastewater capacity. Facilities must generally sit 500 feet from residential districts and homes, with noise capped at 55 dBA at the nearest residential property line. The rules take effect Oct. 9, replacing the moratorium that ran through end-2026. No project is currently proposed in the city.
On Sept. 25, 2026, Pulaski County Judge Barry Hyde vetoed the data center regulatory ordinance the Quorum Court passed 11-4 on Sept. 22. In a letter to County Clerk Terri Hollingsworth, he cited questions under state law and property rights, appeal procedures, the county's inability to administer the regime, potential costs, and personal-liability litigation risk. The ordinance would have required electrical load analyses, water and wastewater plans, land-use suitability studies and decommissioning plans, without capping water or power use. A three-fifths vote (9 of 15) overrides the veto; sponsor JP Julie Blackwood says members will seek an override at the next regular meeting. The fight centers on AVAIO Digital Partners' proposed $6B campus in unincorporated south Pulaski County. Earlier runs missed the veto.
Cheyenne, Wyo. City Council voted 8-2 on Sept. 28 to annex and zone the 1,259.91-acre Cox Ranch property, clearing the way for SkyBox Data Centers and ViaWest Group. Evanston, Ill. City Manager Luke Stowe told council on Sept. 28 that a proposed small data center at 1265 Hartrey Ave. does not appear to be a permitted use, a 'de facto moratorium'; council took no formal action. Fairfield County, S.C. published the schedule for its 12-month moratorium (approved Sept. 14): town halls Oct. 22, Jan. 7 and Jan. 21, a Planning Commission hearing March 25, and council votes by June. Davidson County, N.C. commissioners advanced a proposed four-month moratorium, with a public hearing set for Oct. 26. St. Louis signed a community benefits agreement with TerraWatt for its 120 MW Midtown project, with revenue-shortfall penalties; TerraWatt has since sued the city. Caveat: these come from the Strisker 9/29 digest and local press, not minutes. The Davidson County item rests on a single reporter's social post.
On Sept. 28, 2026, Milwaukee's City Plan Commission voted unanimously to approve an ordinance pausing new data center development for one year while the city writes zoning rules. City code has no data center use category today. The pause ends early if new zoning is adopted. The Zoning, Neighborhoods and Development Committee votes Oct. 6, then the Common Council Oct. 13.
On Sept. 28, 2026, the Evansville City Council held first reading of a 180-day moratorium recommended by the Area Plan Commission. The pause can be extended. The council chose not to form its own study committee because Vanderburgh County already has one and has adopted its own moratorium. The second reading is scheduled for October; the exact date was not reported.
On Sept. 25, 2026, Wayne County Executive Warren Evans vetoed the proposed tax incentives (reported at $125 million) and the community benefits agreement for the Panattoni-developed Google hyperscale campus in Van Buren Township. The project is reported at about 1 GW and at least 2 million gallons of water a day. Evans called the process rushed, saying Google pressed the county to act in about two weeks. This is a county executive veto of an incentive package, not a zoning or utility action. The related DTE/Google special contracts (MPSC U-22058) still show no public order in sources reviewed. Any county commission response to the veto has not been reported.
On Sept. 23, 2026, Gov. Wes Moore signed an executive order (the EO number was not shown in sources reviewed). Every data center of 25 MW or more that seeks any state action (permit, incentive or letter of support) gets one standard, one review and one public record. Projects are judged on five principles: ratepayer and grid protection, economic benefit, community voice, environment, and transparency. A Maryland Data Center Task Force in the Governor's Office (MEA, Commerce, Labor, MDE, DNR, Agriculture, Planning) issues a written public determination: Aligned, Conditionally Aligned or Not Aligned. A monthly dashboard will list developer, parent, anchor tenant, peak power and water use. Moore also said he will ask the 2027 General Assembly to repeal the 2020 data center sales and use tax exemption. Instrument confirmed via the Governor's press release: an executive order, not a signed bill.
Tulare County, Calif. supervisors voted 3-2 on a formal position opposing most data center development in the county (enterprise data centers exempt), in addition to the already-tracked moratorium extension. Jasper County, S.C. passed second reading of a one-year unincorporated-area moratorium on Sept. 21 (third reading at the next meeting); the pending-ordinance doctrine applies. Osage Nation Congresswoman Angela Pratt introduced ONCA 26-70, requiring hyperscale proposals to go before the tribal Congress (tied to Google's Project Spring in Sand Springs, Okla.); committee action was postponed. Sioux County, Iowa holds a Sept. 29 hearing on data center standards (second reading Oct. 13, third Oct. 27). Rep. Mike Lawler asked NYPA to disclose ReCharge NY discounts for Orangeburg data centers. Instrument caveat: drawn from the Strisker Sept. 28 digest and its linked reports, not checked against minutes.
On Sept. 24, 2026 FERC denied Oklo's Aug. 28 complaint (eLibrary accession 20260924-3089). It found Oklo had not shown PJM violated its tariff when it withdrew the project in early August, and that Oklo had not cured the deficiencies PJM staff identified. FERC pointed Oklo to two options: fix the application and resubmit in the next cycle, or use PJM's Expedited Interconnection Track, which is open until Dec. 31, 2027. It also urged PJM to work more closely with developers before, during and after the application process. The project combines 150 MW of advanced nuclear, 300 MW of fuel cells and 300 MW of gas, interconnecting at Dominion's Possum Point and Ladysmith substations in Virginia. Oklo says missing this cycle means a delay of at least 18 months. Five similar complaints against PJM Cycle 01 withdrawals are still pending: Advantage Capital Renewables, Agilitas, Current Hydro, Lanyard Power and RWE. Correction: earlier Edged records described the site as Ohio; the complaint and FERC coverage place it in Virginia. _source: Utility Dive, Sept. 25, 2026.
On Sept. 24, 2026 the Palm Beach County Commission gave final approval, unanimously, to a one-year moratorium. It adds a large-scale data center use definition to the Unified Land Development Code and pauses new facilities that meet it. The threshold follows the state's 50 MW hyperscale definition, and some residents argued for a lower one. It follows the July denial of Project Tango near Arden. Rules under study include a 50 MW power cap, end-user disclosure, water, noise and heat limits, and a standing task force; the commission leaned toward hiring a consultant. Instrument check: this is an adopted ordinance amendment, not a resolution. _source: WFLX/WPTV, Sept. 24, 2026.
On Tuesday, Sept. 22, 2026 the Prince William County Board of Supervisors voted 8-0 to eliminate by-right approval for data centers, with a 90-day grace period as proposed by Brentsville Supervisor Tom Gordy. Facilities outside designated opportunity zones will now need a Special Use Permit. The board also unanimously rejected Dominion Energy's proposed gas-insulated substation expansion on Vint Hill Road in Nokesville, which would have served up to seven proposed buildings. Earlier runs missed this item. _source: WTOP / InsideNova / Prince William Times, Sept. 22-23, 2026.
On Friday, Sept. 18, 2026 the PUCT adopted its PURA 37.0561 (SB 6) large-load interconnection standards for loads of 75 MW or more in ERCOT. Changes from the March proposal: (1) the $50,000/MW non-refundable interconnection fee is gone, replaced by a flat $100,000 study fee regardless of size, which the Commission may revisit as study-cost data comes in; (2) the TDSP must now notify ERCOT of non-utilized capacity after a 24-month slip in the energization schedule as a whole, not six months per milestone; (3) within 60 days of that notice, financial security is applied to amounts owed and the balance is returned to the customer, replacing the proposed 20/80 split. Source discrepancy: a White & Case alert says developers must post $50,000/MW before studies. Utility Dive's corrected story says that figure was the proposed non-refundable fee and was eliminated. It is unresolved whether a per-MW financial-security posting remains; check the adopted rule text in Interchange item 58481. Earlier runs missed this item. _source: Utility Dive, Sept. 21, 2026 (corrected); PUCT Interchange 58481.
Calexico, Calif.: council voted 3-0 to amend the zoning code to prohibit data centers, the third California city to do so. Wakulla County, Fla.: unanimous ordinance formalizing a countywide prohibition in unincorporated areas; staff said it was already the effect of the zoning code. North Mankato, Minn.: one-year moratorium and study. Zionsville, Ind.: one-year moratorium on data centers, solar, wind and battery storage. Fayette County, Ohio: roughly eight-month moratorium covering seven townships. Americus, Ga.: 30-day moratorium, 5-1, on Sept. 24. Raton, N.M.: commission rejected a pause 3-2. Upcoming: Buffalo, N.Y. Common Council vote on a two-year ban Sept. 29 (mayoral signature uncertain); Oakland, Calif. full council vote on a 45-day moratorium Oct. 6 after committee approval. Enforcement: New Jersey fined DataOne's Vineland facility $1.07M for 62 unpermitted gas generators, the state's largest data center enforcement action. Instrument check: all adoption claims come from a secondary digest that links to local outlets. None were checked against municipal minutes. _source: Strisker Weekly Briefing, Sept. 25, 2026; Americus Times-Recorder, Sept. 24, 2026.
On Thursday, Sept. 24, 2026, Grant County commissioners approved a notice of intent to consider a one-year data center moratorium. The text is modeled on Socorro County's resolution and was proposed by Commissioner Nancy Stephens; Commissioner Tom Shelley was the only no vote. The moratorium itself is set for a vote on Oct. 8. The trigger is Site Layer 1 LLC's gas-fired project near Hachita and Playas (about 2.3 million cubic feet of gas per hour, roughly 250-400 MW of behind-the-meter generation). The developer's public notice said it would file an NMED air permit application by Oct. 1, and Environment Secretary James Kenney criticized its lack of community engagement in a Sept. 18 letter. The same day, Lea County commissioners agreed to consider more than $134 billion in industrial revenue bonds for a Google/Excelsior Energy Capital hyperscale campus: two 900,000 sq ft buildings on 1,890 acres, paired with a 2 GW solar field 3 miles away, with the developers pledging to cover 100% of new generation costs. Instrument check: Grant County's action is a notice of intent, not an adopted moratorium. Lea County's is a vote to consider IRBs, not a bond issuance. _source: Santa Fe New Mexican / Las Cruces, Sept. 24, 2026.
On Sept. 24, 2026, the St. Bernard Village Council (Hamilton County, inside the Cincinnati metro) voted unanimously for a 12-month moratorium on data centers, effective immediately. CAI Investments' pending application to put a 150,000 sq ft, 24 MW data center in the vacant P&G Ivorydale / St. Bernard Soap Co. building filed before the vote, so it will still go to the Board of Zoning Appeals as a conditional use. The village will not accept new applications. Separately, Warren County, Ohio commissioners directed the prosecutor's office on Sept. 22 to draft a temporary moratorium resolution; a public hearing will be scheduled once it is drafted. This adds to Cincinnati, Butler County and Mt. Orab. _source: WVXU, Sept. 24, 2026; Warren County Post.
On Sept. 23, 2026, the Woodbury City Council and mayor voted unanimously for an interim study-and-moratorium ordinance on data centers and other high-volume public infrastructure users, lasting up to one year. Before the vote, the council widened it to cover building, electrical and right-of-way permits as well as rezonings, comprehensive plan amendments, CUPs, variances and new applications. It cannot apply retroactively. The existing IronGate and Medtronic facilities keep their current approvals, and a site already using 19 of its 20 MW can reach that approved capacity. The city has no active data center applications. _source: Woodbury News Net, Sept. 24, 2026.
On Wednesday, Sept. 23, 2026, the Marshall County Board of Supervisors unanimously adopted a resolution placing a six-month moratorium on applications for data centers, AI computing facilities, data mining and cryptocurrency mining. The final version removed the cap on how many times it can be extended. The zoning commission will hold monthly ordinance work sessions. _source: Times-Republican, Sept. 2026.
On Sept. 22, 2026, the Tulare County Board of Supervisors voted 5-0 to extend its 45-day urgency moratorium on new data center development in unincorporated areas by another 10 months, so staff can draft permanent zoning rules. Staff says the options still include zoning standards, conditional use permits or an outright ban. _source: The Sun-Gazette, Sept. 23, 2026.
On Tuesday, Sept. 22, 2026, the Pulaski County (Little Rock) Quorum Court voted 11-4 for an ordinance regulating high-density digital infrastructure. It covers electrical demand, water and wastewater capacity, noise, roads, emergency response, neighboring property monitoring, decommissioning and long-term public costs. This follows five months of fighting over the AVAIO data center project. The ordinance goes to County Judge Barry Hyde, and sponsors asked for prompt signature so it can take effect as an emergency ordinance. If he vetoes it, the court could try an override on Oct. 27. Instrument check: this is a siting and regulatory ordinance, not a moratorium, and it is not in force until signed. _source: Arkansas Democrat-Gazette, Sept. 22, 2026; THV11.
On Sept. 8, 2026, Gov. Maura Healey signed Executive Order No. 658, 'Establishing Requirements for Responsible Data Center Development and Operations in Massachusetts.' Under the order, state permitting agencies will not advance a data center project unless it has local approval, including a community benefits agreement with the host community that meets state standards. Projects with peak demand above 25 MW must show they comply with the administration's Data Center Framework before getting state permits. That means bringing their own clean energy supply, paying the full cost of the energy infrastructure they need, and protecting water, air and public health. The order sets up a Ratepayer Protection Fund: data centers that do not fully cover their electricity costs with their own clean supply pay a fee that goes back to ratepayers. It also bars NDAs between state agencies and data centers. This builds on Healey's earlier summer 2026 halt to data center tax incentives. Local follow-on: on Sept. 16, Boston Councilor Miniard Culpepper filed a zoning text amendment to ban data centers in every Boston zoning district (introduced only). Instrument check: this is a signed executive order, not legislation. Earlier runs missed it; it predates as_of but is material as a statewide gate. _source: Mass.gov press release and EO No. 658, Sept. 8, 2026; WBUR; GBH.
On Sept. 23, 2026, Mayor Brandon Johnson and a group of alders introduced an ordinance for a 12-month moratorium on new data center development in Chicago. The pause would give the mayor's Data Centers Task Force time to build a comprehensive regulatory framework on air, water, noise and grid demand. The city counts 39 active data centers. Ald. Marty Quinn (13th) used a parliamentary maneuver to keep the ordinance from going to its intended committee, which is likely to stall it. Ald. Bill Conway (34th) is pushing a competing ordinance that would apply zoning, community and environmental review right away. The Data Center Coalition said the proposal signals Chicago is 'closed for business.' This follows Johnson's August 2026 executive order creating enhanced regulatory review of data centers. Instrument check: the ordinance has been introduced, not adopted, and no ordinance number has been reported. _source: Axios Chicago, Sept. 23, 2026; CBS Chicago; The Real Deal.
The Pima County Board of Supervisors adopted a resolution on the night of Sept. 22, 2026 by a 3-2 vote (Supervisors Rex Scott and Steve Christy opposed; Scott cited County Attorney legal advice). The resolution imposes a 120-day moratorium on permits and advancement of new data center projects while staff write a zoning code text. The July memo lists possible requirements: closed-loop cooling, noise limits and design standards. A draft code is expected by Dec. 15. The moratorium covers 'future development of new data centers where permits have not been submitted for site improvements.' Project Blue is already under construction, so it is outside the pause. The effect on Project Gravel, a proposed 160-acre data center in Sahuarita, is unclear because its developers say the land is already zoned industrial. The board also voted to consider extending the ban. No resolution number has been reported. _source: AZPM, Sept. 23, 2026.
On Sept. 22, 2026, the Lubbock City Council voted 5-2 to begin the procedure for a 90-day moratorium on 'the acceptance, processing, and/or approval of any applications for rezoning, building permits, or any request for annexation related to the development of large-scale data centers.' Councilmen Tim Collins and Tim Green voted no. The Save Lubbock citizen-petition ordinance for an 18-month moratorium died for lack of a second. Under Texas law the moratorium needs two public hearings before it takes effect, which KTTZ reports will take about 90 days. It can then be extended one time for another 90 days. Collins argued the city should hold its only tool until after the 2027 legislative session. The mayor said no new projects are realistic in the next year anyway, given Gov. Abbott's Aug. 3 grid-audit pause and Sept. 21 TCEQ permit halt. _source: KTTZ/TPR, Sept. 23, 2026.
Kershaw County Council voted unanimously on Tuesday, Sept. 22, 2026 to pass third and final reading of an ordinance setting a one-year moratorium on data centers, cryptocurrency mining operations and data processing facilities. First reading was Aug. 25 and second reading was Sept. 8. Colleton and Fairfield counties are weighing the same approach. No ordinance number has been reported. _source: South Carolina Public Radio, Sept. 23, 2026; WIS.
North Port city commissioners voted 3-2 on Sept. 22, 2026 for an 18-month moratorium on accepting and approving data center applications. Commissioner Stokes, Commissioner Langdon and Mayor Emrich voted yes. Commissioners Petrow and Duval voted no because they wanted the pending project covered too. The measure excludes a roughly 896,000 sq ft data center filed July 20 inside the 282-acre Deep Park development near I-75. Staff can process that application, but approval still requires a commission vote. The city attorney warned that including it could invite litigation. The ordinance also allows 'extraordinary hardship' exceptions. _source: WINK News, Sept. 22-23, 2026; Sarasota Magazine.
On Sept. 22, 2026, Fort Wayne City Council held Councilwoman Rohli Booker's one-year data center moratorium for three weeks after several amendments were proposed. The council is scheduled to take it up again Oct. 13. The measure would block council approval of new data center projects for a year and direct Planning Services to draft development standards. It would not affect Google's existing southeast Fort Wayne campus. _source: WPTA 21Alive, Sept. 22, 2026.
On Monday, Sept. 21, 2026, Gov. Greg Abbott sent a letter to TCEQ Executive Director Kelly Keel directing the agency to halt all permits sought by data center projects until the ERCOT/PUCT and TWDB audits are complete. The letter says: 'no other state agency shall move forward with regulatory approvals related to data centers until this information is acquired.' TCEQ must report its compliance to the governor by Monday, Oct. 19, 2026. Abbott also said he will work with the 2027 Legislature to eliminate data center financial incentives. Instrument check: this is a gubernatorial directive letter to an agency head. It is not an executive order, statute or TCEQ rule, and the Sept. 18 spot-check was right to reject earlier reports of a 'statewide construction freeze.' In practice, it closes the gap the Aug. 3 ERCOT audit left open. Behind-the-meter projects and sites outside the ERCOT footprint (El Paso, the Panhandle/SPP, East Texas/MISO) now face the same gate through air and water permits. Earlier runs missed this; it predates as_of but is material. _source: Texas Tribune, Sept. 21, 2026; Office of the Texas Governor press release; Houston Public Media; CNBC; Foley & Lardner.
The Ferguson City Council voted 4-3 on Sept. 23, 2026 to approve the revived Emerson Electric headquarters redevelopment led by Next Revolution Technologies LLC (James Onder), authorizing up to $1.5 billion in tax incentives and up to $22 billion in industrial revenue bonds for the 217-acre site, with a potential 300 MW data center component. The approved package also includes a $700,000 community impact/emergency-services payment to the city, a $250,000 environmental mitigation fund, and $7.5 million over 10 years to the Ferguson Neighborhood Improvement Program. The vote reverses the council's May 2026 rejection (3-3 with one abstention) of an earlier version of the deal. Nearly all public commenters at the meeting opposed the measure. _source: St. Louis Public Radio (STLPR), Sept. 23, 2026; KBIA, Sept. 23, 2026.
All seven council members (four Democrats, three Republicans) sponsored and voted Sept. 22, 2026 to extend the moratorium approved in January 2026, which had been set to expire Jan. 1, 2027. The pause now runs through Dec. 31, 2027. Council members cited a rapidly evolving industry and broad constituent opposition. _source: WYPR, Sept. 22, 2026; WMAR, Sept. 22, 2026.
On Sept. 22, 2026 the council adopted, 6-3, a resolution directing the Area Plan Commission to draft zoning amendments prohibiting hyperscale data centers in unincorporated St. Joseph County and the definitions needed to implement a ban. The resolution itself does not prohibit anything. The Area Plan Commission will work out treatment of existing projects; the ordinance is expected back before the full council within about 60 days for a final vote. Opposed: Diana Hess (D), Mark Catanzarite (D), Dan Schaetlze (R). Resolution number not reported. _source: WVPE / ABC57 / WNDU coverage, Sept. 22-23, 2026.
Adopted Sept. 21, 2026 after a public hearing. Mayor Julie Hoy, Council President Linda Nishioka and councilors Tigan, Matthews, Brown, Nordyke and Varney voted in favor. The moratorium bars the city from approving any data center development regardless of size, capacity or purpose, and expires Jan. 19, 2027 unless extended (roughly six more months is possible). A new Data Center Task Force reports recommendations to council in December. On Sept. 22 the city attorney said the moratorium means Verrus cannot build until it expires. _source: Salem Reporter, Sept. 21-22, 2026; KATU.
Galesburg City Council voted unanimously on Sept. 21, 2026 to bar accepting, processing or approving data center permits through April 3, 2027, with a limit or ban possibly to follow. The city has received no applications. The same night Normal Town Council voted 6-1 to extend its existing moratorium to May 31, 2027. _source: TSPR, Sept. 22, 2026; WGLT, Sept. 22, 2026.
Per ERCOT market notice M-A080326-04, ERCOT completed its first Batch Zero screening Thursday Sept. 3, 2026, after missing the Aug. 31 target. It privately sorted large loads (>=75 MW) into conditional inclusion, studied-load or excluded. Applicants, locations and project decisions were not disclosed. Conditional inclusion is not final interconnection approval and sets no energization date. Some base-load submissions were reclassified to studied load, which can mean more studies, upgrade costs or curtailment terms. TSPs must notify customers of reclassification within two business days. Disputes go through Batch Zero dispute/reconciliation; excluded projects can seek ADR. ERCOT will seek a separate PUCT exception letting some energized-load-path applicants submit new evidence within 14 business days. ERCOT expects a final Batch Zero transmission plan in fall 2027. Missed by earlier runs; added now. _source: Blockspace (via Yahoo Finance), Sept. 4, 2026; ERCOT market notice M-A080326-04.
Executive Order 2026-005, 'Order Establishing the Nevada Standard for Responsible Data Center Development,' signed Sept. 18, 2026 and effective immediately. Conditions GOED Board consideration of partial tax abatements on (i) payment of the Local School Support Tax in full, (ii) execution of a binding Nevada Community Support Commitment, and (iii) a combined sales-and-use / school-support floor of not less than 4.6% that may not be abated. Minimum commitment terms: meet local water standards, cover the cost of service without ratepayer pass-through, and avoid straining the grid or community in emergencies. Bars applicants owned or controlled by a federally designated foreign adversary. Procedural guardrails on GOED: 30-day incompleteness notice, placement on the next lawful agenda, no exactions beyond the order, annual aggregate reporting. Requires a Responsible Speed to Power Plan from the Director of the Office of Energy by Dec. 31, 2026 covering load through 2036. Backdrop: the 2015 abatement statute had no energy or water protections and no denial authority; the 2025 Legislature gave the GOED Board power to deny, reduce or condition. Data Center Coalition responded that some provisions 'create additional hurdles.' Confirmed against the Governor's official executive-order index (primary source) — an executive order, not legislation. _source: Nevada Governor's Office EO index; FOX5 Vegas, Sept. 18, 2026.
Ordinance #1012, adopted 6-0 on third and final reading Sept. 14, 2026. Imposes a 12-month moratorium on the acceptance, review and approval of applications and permits associated with new data centers in unincorporated Laurens County; the municipalities of Laurens and Clinton retain jurisdiction inside their limits. County officials state the purpose is to develop a regulatory framework, citing water use, electricity demand and environmental impacts. _source: FOX Carolina, Sept. 14, 2026; Laurens County Advertiser.
Gov. Gavin Newsom signed a seven-bill data center package on Sept. 21, 2026 -- the same day as this refresh and after the morning run. Bills signed: SB 886 (Padilla) and AB 2383, directing the CPUC to establish special large-load power rates covering interconnection and service costs; SB 1168 (McNerney), directing the CPUC to ensure data centers bear their share of transmission and distribution costs rather than shifting them to residential ratepayers; AB 2469, prohibiting local approval of a data center until the developer discloses projected water usage; AB 1577 and AB 2619, mandating disclosure or estimation of water and other resource use; and SB 887 (Padilla), making data centers ineligible for blanket CEQA exemptions while offering fast-tracked approval for facilities meeting state water and energy conservation standards. Legal instrument: gubernatorial bill signatures, not an executive order. The package passed the legislature largely on party lines (SB 1168 was the unanimous exception) over Data Center Coalition opposition. Newsom vetoed a comparable water-reporting bill in 2025. Chapter numbers and operative dates not yet reported; implementation routes into CPUC R.26-04-009. _source: KQED (Sept. 21, 2026, 12:54 pm PT) and Reuters via GV Wire (Sept. 21, 2026), corroborated by CalMatters and KPBS same-day.
Third and final reading passed 5-1 on Sept. 21, 2026 after a five-week delay from the Aug. 17 reading. Four amendments were adopted before the vote: 65 MW threshold; exemption for data centers already holding county approval; siting restricted to established industrial parks or former industrial sites; no on-site generation except emergency backup; and a primary-use requirement limiting facilities to data storage, management and processing. Ordinance number not reported. Twelve-month term. Sole dissent: Councilwoman Jessica Coker. _source: FOX Carolina, Sept. 22, 2026.
St. Joseph County (South Bend), Ind. Council is scheduled to vote Tuesday, Sept. 22, 2026 on a resolution banning new hyperscale data centers beyond the Amazon and Microsoft facilities under construction. Sponsored by Republicans Amy Drake, Randy Figg, Andy Rutten and Joe Thomas; Democrat Jenn Shabazz's support gives the resolution a 5-of-9 majority. Council President Bryan Tanner opposes, citing the county's existing litigation costs and exposure to developer suits.
Michigan City, Ind. Common Council voted 8-1 on Sept. 15, 2026 to table the proposed data center moratorium ordinance rather than adopt it at second reading. The ordinance would have paused permits and tax abatements for data center projects pending zoning updates, exempting Google's in-progress build at the former Federal Mogul property. Council will instead draft a resolution directing the planning department; a separate proposal to create a data center zoning district is pending.
NERC's Project 2026-02 Computational Loads initial formal comment period and ballot closed Sept. 18, 2026. The SAR, accepted by the Standards Committee on March 18, 2026, proposes Glossary definitions for computational load and computational load entity plus a new Reliability Standard on near-term integration of large computational loads. FERC has directed NERC to file one or more new or modified mandatory standards governing computational load integration by Dec. 31, 2026.
The Pennsylvania PUC voted 5-0 on a motion by Vice Chair Kimberly Barrow directing staff to prepare a Tentative Order updating Pennsylvania's emergency electric load control regulations, including clearer curtailment order, criteria and applicability during pre-emergency and emergency conditions. The Tentative Order is set for the Oct. 1, 2026 public meeting, with a final order targeted for Jan. 28, 2027. The motion also directs a fall technical conference on cost responsibility for large computational loads including data centers. Announced Sept. 14, 2026; follows Gov. Shapiro's Aug. 18 Executive Order 2026-05.
The Evansville, Ind. Area Plan Commission recommended a 180-day data center moratorium in September 2026 to allow time for research and rulemaking. The City Council's first reading is scheduled for Sept. 28, 2026. No adoption vote has occurred.
Executive Order 22 (2026), 'Establishing New Nation-Leading Standards and Initiatives to Implement the Virginia Data Center Accountability Framework and Responding to Unprecedented Risk From Artificial Intelligence,' signed Sept. 18, 2026 and effective upon signing. Self-executing directives: (1) Sec. I.B.4 — effective upon issuance, VEDP shall NOT provide assistance through the Virginia Business Ready Sites Program, any expedited permitting program, or any similar discretionary state economic development, site-readiness or expedited-review program for a new data center project with anticipated peak electrical demand of 25 MW or greater; (2) Sec. I.B.2 — executive branch agencies, departments, boards, commissions and authorities are barred from entering, enforcing or requiring NDAs that prevent public disclosure of material information on proposed commercial data center development, its public incentives, resource demands or community impacts (existing NDAs honored; national-security carve-out); (3) Sec. I.C.3 — the Eastern Virginia Groundwater Management Area is designated a cooling water scarcity area, with DEQ to expedite criteria regulations (180-day workplan). Deadline-bearing directives: DEQ accelerated noise-rulemaking workplan and cumulative-impact review of diesel/other backup generation, including promotion of Tier II-to-Tier IV gen-set retrofits, findings due in 180 days; Office of the Chief Energy Officer to publish a Data Center Planning and Community Engagement Toolkit for localities within 120 days; Virginia Energy siting/regional-diversification recommendations within 240 days; VA-LEAD tiered responsible-development designation criteria due end of CY2027, to become the baseline for how executive agencies align incentives and administrative services. Grid and cost directives: Chief Energy Officer to engage utilities, the SCC and PJM to assign PJM Reliability Backstop Procurement costs to the data center large loads causing them and to push equitable cost allocation under PJM's Interim Resource Adequacy Service (IRAS); to work with the SCC and utilities on emergency curtailment procedures for data centers that have NOT brought their own capacity under IRAS, contingent on FERC approval, with curtailment priority favoring data centers bringing clean energy or peak shaving; Virginia Energy to evaluate state best practices on ride-through and voltage protections in coordination with PJM and NERC. Also creates a rapid-response AI Task Force (Chief Transformation Officer, Counsel to the Governor, Secretary of Administration) with an AI Policy Planning Unit. Rescinds Youngkin EO 30 (Jan. 18, 2024) and Executive Directive 5 (Sept. 20, 2023). LEGAL-INSTRUMENT NOTE: press coverage conflates the EO with the broader 'Data Center Accountability Framework' legislative package. Eliminating by-right local approval above 25 MW, banning local-government NDAs, and limiting behind-the-meter gas generation are 2027 General Assembly PROPOSALS, not EO directives. Spanberger declined to impose a statewide moratorium.
Ohio Capital Journal's Sept. 18 tally puts Ohio above 125 active local moratoriums on data center development — concentrated in the Columbus, Dayton and Cincinnati suburbs where AEP Ohio and Duke Energy Ohio have the largest large-load queues. The count materially outpaces the national trackers' Ohio figure (35 in the Interconnected Capital census), which suggests the national row-level trackers are undercounting township-level actions in home-rule states.
After more than nine hours of testimony, Colorado Springs City Council voted 7-2 to postpone its decision on five appeals of the Planning Department's June approval of Project Taurus — a data center on the former Intel microchip site near Garden of the Gods and Centennial Blvd. — until the April 13, 2027 council meeting. Councilmember Roland Rainey Jr. moved the delay to allow power and sound studies. The new date falls one week after the April 6, 2027 municipal election, effectively making the project a ballot issue. Four people were arrested after an altercation during public comment.
Mayor Eddie Melton signed an executive order pausing approval of new data center projects in Gary for one year while the city studies grid, water, infrastructure and quality-of-life effects. Notably, the order's scope is utility-based rather than purely geographic: it applies to any data center, wherever located, that would connect to or increase demand on infrastructure or utilities owned or operated by the city. Gary currently hosts no operating data centers. This is an executive order, not a council ordinance — a legally distinct instrument that a successor administration or a council ordinance could displace.
The Massena town board rejected a proposed six-month data center moratorium 3-2. Town Supervisor Raymond Lancto and board member Kristy Baker voted for the pause; the other three members voted against. The vote clears the way for developer NCCS's proposed ~400 MW facility on land near the former Alcoa East plant. Massena is a notable counterexample in New York, which enacted the first statewide moratorium in July 2026 — the local board's rejection keeps a large North Country interconnection live while the state framework is worked out. A residents' petition drive and a parallel town code review remain open.
The House passed H.R. 9340 (Rep. Gabe Evans, CO-08) by 417-3 on Sept. 16, 2026. The bill adds a PURPA Sec. 111(d) ratemaking standard directing state PUCs to consider large-load standards for data centers above 100 MW so they pay the full incremental cost of generation, transmission and distribution built to serve them. It is a consideration mandate, not a substantive federal cost-allocation rule; states may adopt, modify or reject after proceeding. The bill had cleared House Energy & Commerce 52-0 in July with no floor time then scheduled. It now goes to the Senate, where no companion vehicle has been scheduled. _source: House Energy & Commerce press release, Sept. 16, 2026.
Raleigh Mayor Janet Cowell announced Sept. 16, 2026 that she has asked the City Council to consider a draft six-month moratorium on new data centers larger than 10,000 square feet, with a public hearing and possible vote at the Oct. 6, 2026 council meeting. City staff report eight existing data centers in Raleigh, most under 10,000 sq ft; larger hyperscale projects already require special use permits in industrial zones. The proposal follows a developer's withdrawal of a southeast Raleigh data center plan after public opposition, and follows moratoriums already adopted in Charlotte, Durham County, Greensboro and Cary.
The Santa Cruz County Board of Supervisors voted on Sept. 15-16, 2026 against a proposal by Supervisor Justin Cummings that would have required voter approval for future AI data center projects in the county, opting instead to hold a study session before considering regulation. Supervisor Monica Martinez said the board lacked sufficient technical knowledge to legislate. County staff reported concerns about water and electricity consumption, noise, traffic and air quality. Cummings said he may pursue a citizen petition drive to place the requirement on the ballot regardless.
Leon County, Fla. commissioners voted unanimously on Sept. 15, 2026 to advance an 18-month moratorium on large-scale data centers, with a final adoption vote scheduled for Oct. 13, 2026 and staff findings due back in September 2027. Commissioners cited the absence of any data center provisions in the county's land development code or comprehensive plan and raised water consumption, electricity demand and ratepayer cost concerns. A hurricane-related exemption could permit applications on storm-damaged property.
The Marysville, Kan. City Council unanimously adopted a 12-month data center moratorium in mid-September 2026, halting new applications while the Planning Commission reviews citizen concerns and evaluates zoning code amendments. The ordinance covers hyperscale, cloud, AI and cryptocurrency facilities but excludes ordinary server rooms incidental to other uses.
The Riverside, Calif. City Council on Sept. 15, 2026 established a temporary three-member ad hoc committee (Councilmembers Steven Robillard, Philip Falcone and Steve Hemenway) to research artificial intelligence and draft citywide policy recommendations. The committee will meet monthly for 13 months covering ethical use in city government, workforce, resource demands, cybersecurity and AI literacy. Councilmember Falcone tied the work directly to the Land Use Committee's recent 90-day data center moratorium.
Richmond City Council voted Tuesday night, Sept. 15, 2026, to adopt a 45-day urgency moratorium on new data center development, becoming the third Bay Area city to do so after Oakley and Gilroy. Under a staff amendment, the city may continue to accept and process applications during the moratorium but may not approve them or issue related permits. Extendable by up to 22 months and 15 days.
On Sept. 15, 2026, Orange County, Fla. commissioners voiced support for a temporary moratorium on hyperscale AI data centers and directed staff to study zoning, electric load, water and noise impacts, but did not adopt an ordinance. The moratorium's length will be set by the study timeline; the commission could take the issue up again in early December. Sixteen Florida counties already have bans, three of them permanent.
The Woodburn, Ore. City Council held a public hearing and voted unanimously at its Sept. 14, 2026 meeting to declare a 120-day moratorium on new data center development, halting acceptance, review and approval of permits and development proposals for new data storage, processing and IT facilities under the Woodburn Development Ordinance. Other industrial projects are unaffected. No applications are currently pending. The city will use the window to update zoning, utility and location criteria.
Gov. Greg Abbott directed the Texas Water Development Board to enforce penalties against data centers and other major water users that failed to return the state-mandated water use survey (2025 responses were due in March). Abbott stated non-filers 'appear to have committed civil and criminal violations.' Penalties include a Class C misdemeanor, referral to county or district attorneys, and ineligibility for TCEQ permits, permit amendments and permit renewals. Response rates have been as low as 28% over three years. TWDB must report back on compliance and enforcement by Oct. 14, 2026.
Manatee County's draft ordinance establishing a 12-month moratorium on acceptance, processing and approval of development applications for data centers and other facilities with substantial electrical, water, wastewater or utility demand goes to the Planning Commission in September, then to the Board of County Commissioners for the two required hearings on Sept. 22 and Oct. 6. Commissioners voted unanimously on July 28 to direct the draft and have since expressed unanimous support for the 12-month pause. Manatee follows Hernando and Pasco counties.
The Elgin City Council gave unanimous preliminary approval to a one-year moratorium on data center development, raised by council members Tish Powell and John Steffen at a committee-of-the-whole meeting. Elgin has received no data center applications to date; the stated purpose is to develop siting standards and protections before any project is filed. A final council vote is scheduled for a future meeting. Follows South Elgin's denial of a data center application after resident opposition.
A legislative referral from Mayor Mark Salinas, Mayor Pro Tem George Syrop and Councilmember Angela Andrews directs staff to begin amending the Hayward zoning code to prohibit new data center development, and to establish monitoring and reporting on the impacts of previously approved and operating facilities. Hayward already amended its municipal code in April 2026 to require Major Conditional Use Permits for data centers. A majority endorsement sends the item to staff for drafting; a prohibition ordinance would require a later council vote.
Supervisors Walton, Chan, Fielder and Chen introduced an urgency ordinance establishing a 45-day interim zoning moratorium on new data center construction and on power-capacity expansions at existing facilities in San Francisco, while the Planning Commission studies environmental and public health impacts across the city's ~15 regional data center campuses. The control can be extended up to 22 months and 15 days. Walton has signaled intent to pursue a permanent prohibition. Status is introduced/pending — no board vote has been confirmed.
Memphis City Council postponed the third and final reading of the 12-month citywide data center permit moratorium from Sept. 15 to Oct. 6. Councilmember JB Smiley said he would amend his ordinance to incorporate other members' proposals and to target hyperscale data centers specifically. Multiple related data center ordinances were carried over to the same date. No moratorium is in force in Memphis in the interim.
The Memphis City Council holds the third and final reading of an ordinance imposing a 12-month moratorium on acceptance, processing and approval of zoning and land-use permits for large-scale data centers. The measure passed second reading unanimously on Sept. 1. Two companion ordinances are also in play: a 100% renewable-energy requirement phased in over 10 years, and a permissive standards ordinance that would allow data centers subject to construction conditions. Vote scheduled for 4:00 p.m. CT.
The Richmond City Council considers an urgency ordinance imposing a 45-day moratorium on new data center development, citing electricity, water and land demands plus noise and health concerns. Adoption requires a four-fifths vote of the council. If adopted, the moratorium may be extended for an additional 22 months and 15 days under California urgency-ordinance procedure. Richmond would be the second city in Contra Costa County and the wider Bay Area to adopt a data center moratorium, after Oakley.
The Statesville City Council unanimously approved the second reading of a 180-day moratorium on the acceptance, processing and approval of applications for new data centers within the city, effective Sept. 14, 2026. The original staff proposal called for 150 days; the council extended it to 180. The moratorium does not affect previously approved data centers. Statesville joins Charlotte and Kings Mountain among North Carolina localities with active pauses.
The Bemidji Planning Board voted 6-1 to advance a one-year moratorium on data centers to the full City Council. If adopted, the city would take no action to approve data centers exceeding 10,000 square feet for one year while a study of community impacts is completed. The Planning Board is composed of Bemidji City Council members, distinguishing it from the city's advisory Planning Commission. The proposal follows earlier inaccurate reports of a data center project in Bemidji.
Attorney General Kris Mayes called on Aug. 31, 2026 for a statewide pause on new data center construction. Gov. Katie Hobbs declined, saying on Sept. 3 and again as the debate escalated through Sept. 9 that 'data centers are an important part of the high tech economy that we are growing here in Arizona' and that 'I don't believe that a state moratorium is the right approach.' She acknowledged the underlying water, electricity and grid-capacity concerns are real. The split matters for two reasons. First, it is the mirror image of New England: where Ayotte and Lamont moved their states toward restriction from the governor's office, Arizona's governor is the brake and the restriction pressure is coming from the AG and from counties. Second, Hobbs has already signed a partial measure — the June 2026 budget bill included a three-year moratorium on new data center tax breaks, a fiscal rather than siting instrument. Read the Sept. 8 Pinal County 4-1 rejection against this: state policy stayed open while the largest proposed campus in the state was killed locally, which is the clearest example this year of local government, not the state, being the binding constraint.
The Foley City Council adopted an ordinance on final reading Sept. 8, 2026 restricting the acceptance, processing, approval and consideration of applications for data centers, Bitcoin and cryptocurrency mining facilities, server farms and similar technically-oriented uses for six months. No data center has been proposed in the Foley area. The city said the pause gives it time to study impacts on water resources, air pollution and noise pollution, and explicitly to study the experience of other Alabama cities, both good and bad. Foley is the first Baldwin County municipality on the tracker and joins Birmingham, Leeds, Cullman, Fort Payne, Homewood, Springville, Somerville, Westover, Anniston, Helena, Morgan County and Harpersville — a dozen-plus Alabama jurisdictions acting almost entirely preemptively, in a state the national posture map still classifies as 'Favorable / Incentives.' That gap between state posture and local practice is the pattern worth tracking in Alabama.
The Boone County, Iowa Board of Supervisors adopted a moratorium of up to one year on Sept. 9, 2026 covering the establishment, construction or permitting of new data centers, to allow time to study impacts and adopt ordinances. Naming hygiene note for the tracker: this is distinct from Boone County, Indiana, which adopted its own one-year moratorium effective June 16, 2026 (unanimous commissioners vote June 15, APC recommendation 6-0 May 6) and which expressly does not reach Meta's $10B Lebanon LEAP campus because that land was annexed. Both are now carried as separate records. Iowa's county-level tally continues to build — Adair, Johnson, Dubuque, Woodbury, Linn and now Boone — against a state posture still classified as 'Under Discussion,' with Salix and Marshalltown as the counterexamples.
The Beaufort County Board of Commissioners was scheduled to consider a one-year data center moratorium at its Sept. 14, 2026 meeting. Commissioners will hold an informal public hearing to accept comment but will not vote; the final public hearing, board discussion and official vote have been moved to Oct. 5, 2026 at 5:30 p.m. at the Beaufort County Administration Building, 121 W. Third St., Washington. The proposed moratorium would stop the county from accepting, processing or approving data center development applications. County officials emphasize no data center is currently planned — this is preemptive. North Carolina's count keeps rising and is now the deepest local-action state outside the Midwest, with Durham City and County, Charlotte, Asheville, Chatham, Orange, Harnett, Northampton, Rowan, Swain, Surry, Davie, Cumberland, Gates, Jackson, Waxhaw, Holly Springs, Apex, Clyde, Canton, Boone, Franklin, Spring Hope and Weaverville all on the board.
At the Sept. 8, 2026 Planning Committee meeting PJM introduced proposed changes to interconnection reliability requirements for Large Loads, defined to include data centers and crypto-mining facilities. The trigger was the July 22, 2026 event in which roughly 4,000 MW of northern Virginia data center load unexpectedly disconnected from the PJM grid and transferred to onsite backup generation, forcing PJM and Dominion operators to manage load/generation imbalance plus transmission voltage and system frequency excursions. David Souder, Executive Director of PJM System Operations, told the Planning Committee this was the third separate measurable event in two years and that 'this type of operation is unsustainable and needs to be addressed.' The proposal would set minimum voltage and frequency ride-through requirements obligating Large Load facilities to remain connected through normally cleared transmission system disturbances; PJM staff also intends to negotiate a transition plan with existing facilities to adjust operating parameters, per Byoungkon Choi, Principal Engineer for Generator Modeling & Dynamic Studies, who said PJM 'plans to establish these requirements as soon as possible.' The action responds directly to FERC's June 18, 2026 order in Docket EL26-67-000, which stated the Commission was 'concerned that the Tariff does not specify ramp rate or ride-through requirements with which the transmission customer taking transmission service on behalf of the large load must comply.' PJM plans to file proposed solutions at FERC in November 2026, with a PC Special Session on Large Load Ride Through Education set for Sept. 15. PJM notes the proposal follows standards already advanced by MISO, ERCOT, Dominion and AEP, and that NERC is developing continent-wide Large Load ride-through guidance and standards.
Speaking on Sept. 7, 2026, Gov. Ned Lamont said Connecticut will not host massive AI data centers, warning they would consume too much electricity and could raise rates for existing customers. He carved out room for smaller projects that supply their own generation and secure local approval. Lamont noted that the state's 2021 data center tax incentive program drew little interest and has since been scaled back. Crucially, no legal instrument was invoked — no executive order, no bill, no agency directive — so this is a stated executive posture rather than binding policy. Its significance is regional: it lands five days after New Hampshire Gov. Kelly Ayotte's Sept. 2 statement that she opposes 'putting any data center in the state of New Hampshire' and will seek a multi-year statewide moratorium through her next budget. Two ISO-NE-footprint governors declaring against hyperscale siting inside a single week, in the region with the highest marginal power costs in the country, establishes New England as the first multi-state cluster where the restriction posture is set at the governor's office rather than by city councils.
On Sept. 8, 2026 the Pinal County Board of Supervisors voted 4-1 against Vermaland's proposed 3,300-acre data center campus south of Eloy, which would have been Arizona's largest. The rejection came after substantial developer concessions: the project had been scaled down from 59 buildings and two onsite gas plants to 11 buildings and one gas plant. The vote is analytically important because it separates two failure modes that are often conflated. Most denials this year have been procedural (wrong zoning, missing study, moratorium in force) or have followed a refusal to negotiate. Here the developer negotiated substantially and still lost on the merits by a 4-1 margin, which suggests that in jurisdictions where opposition has consolidated, right-sizing is no longer a viable path to approval. Arizona is also a state where officials remain publicly divided on whether to pause development statewide, so a county-level rejection of this scale sets a reference point for the rest of the state.
Escambia County commissioners are preparing public hearings for a new 12-month moratorium targeting mid-sized data centers between 10 and 50 megawatts, with hearings tentatively set for Oct. 1 and Oct. 15, 2026. The measure layers onto two earlier actions: a July 2026 resolution barring data centers as principal uses, and an August 2026 ban on large-scale facilities. The result is a deliberately tiered regulatory structure. Its significance is that the 10–50 MW band is precisely the range that falls below most large-load tariff thresholds (45% of tracked DELTa tariffs set thresholds at 50 MW or above, matching FERC's June 2026 show-cause recommendation) and above the small-facility exemptions most zoning ordinances carve out. Escambia is the clearest example so far of a local government explicitly sizing its ordinance to the regulatory gap rather than to the headline project.
The Kearney City Council unanimously approved Project Horizon on Sept. 9, 2026, expanding an existing cryptocurrency data center into a 368 MW facility using up to 5 million gallons of water annually. The approval followed adoption of roughly ten pages of new regulations covering water efficiency, noise limits and conditional-use review, and developers agreed to add sound-deafening walls to address existing humming complaints. This is the operative counterexample to the moratorium wave and the cleanest instance of the 'regulate-then-approve' path: the same week Lubbock, Tex. passed a non-binding resolution to wait for standards before approving anything, and Lancaster County, Neb. declined a moratorium in favor of study task forces, Kearney demonstrated the sequence actually completing. For queue-distress purposes it matters that the approved facility is an expansion of existing crypto load being converted upward, not a greenfield interconnection — a pattern worth watching as stranded crypto sites get repurposed.
The Zeeland Township board approved a new year-long moratorium on data centers and energy facilities on Sept. 7, 2026, repealing and replacing a prior moratorium in the same session, in order to protect local planning authority while the township updates its master plan. The repeal-and-replace mechanic is worth flagging as a technique: extending an existing moratorium typically invites a challenge that the cumulative pause has become an unlawful de facto prohibition, whereas adopting a fresh ordinance with a new stated purpose (master plan update) restarts the record. The scope expansion to 'energy facilities' is equally notable — it captures the behind-the-meter generation that co-located data centers depend on, meaning a developer cannot route around the data center pause by permitting the generation first.
Springhill Township (Fayette County) supervisors approved a temporary ban on new data center and power-plant applications on Sept. 8, 2026, while tabling votes on two more detailed ordinances until Sept. 17 to satisfy Pennsylvania notice requirements. The delayed rules would impose 200-foot property-line setbacks and separate daytime and nighttime noise limits. The trigger is Nadara's interest in roughly 800 acres near Gans. The sequencing — interim ban first, substantive ordinance second — is the standard defensive pattern for small Pennsylvania townships facing a specific named developer, and the pairing of data centers with power plants in a single ordinance again reflects the co-location reality that the two are one project.
Weld County commissioners approved a construction permit for Global AI on or about Sept. 11, 2026, positioning the project to become Colorado's largest data center. Reported via The Denver Post. Weld County's approval is a useful counterweight to the moratorium tally: Colorado is classified as a jurisdiction with active legislative discussion rather than an active ban, and the county-level permitting path remained open. Detail on megawatt sizing, interconnection posture and utility service arrangement was not available in the initial report and should be verified against county records before the figure is used in any sizing analysis.
Councilwoman Rohli Booker introduced legislation on Sept. 9, 2026 to pause Fort Wayne council actions on data centers for one year and create a nine-member commission to study large developments. The measure received unanimous support for introduction — a procedural rather than substantive vote, but notable because it signals no organized council bloc opposing even the framing. The driver is resident opposition to Google's $2 billion Fort Wayne campus, which is now operational. This is the post-approval variant of the moratorium wave: the pause is not aimed at stopping the project that generated the backlash, which is already built, but at preventing the next one from following the same approval path. That dynamic — regulation arriving one project too late — is showing up repeatedly and is a leading indicator for where the next wave of restrictions lands.
Grant County, N.M. residents were caught off guard when a legal notice revealed Site Layer 1 LLC's plan for a natural gas-powered data center near Hachita and Playas that could consume up to 2.3 million cubic feet of gas per hour. The project's only listed address is an empty Manhattan office floor. A county commissioner is proposing a one-year moratorium modeled on Socorro County's ordinance, to be considered Sept. 24, 2026. Two things make this relevant beyond the local dispute. First, the gas consumption figure implies a behind-the-meter generation build of roughly 250-400 MW depending on heat rate — meaning this is a fully off-grid or islanded design that would never appear in an interconnection queue at all, and is therefore invisible to queue-based siting analysis. Second, the shell-entity opacity is now itself generating regulatory response: Rock County, Wis. is separately weighing an NDA-restriction policy, and the transparency backlash is becoming a distinct ordinance category alongside water, noise and setbacks.
Jasper County Council approved on first reading a temporary moratorium on new data centers, cryptocurrency mining and data-processing facilities in unincorporated areas; additional readings are required before it becomes law, so the measure is not yet in force. Separately, Mount Pleasant officials are set to debate a 120-day moratorium specifically to close potential loopholes allowing hyperscale facilities in light industrial zones, with the mayor stating such centers 'will not be permitted.' South Carolina had been comparatively quiet relative to Georgia and Virginia; two simultaneous actions in a Savannah-adjacent county and a Charleston suburb suggest the wave is now propagating along the coastal Southeast corridor. The Mount Pleasant framing — loophole closure rather than blanket pause — matches the Christiansburg, Va. by-right-removal technique and is the lower-friction path councils are increasingly choosing.
As of the morning of Sept. 14, 2026, no MPSC order, Commission news release or contemporaneous press report confirming an outcome in Case U-22058 has appeared in public sources. DTE had requested a decision by Thursday, Sept. 10, and the special contracts — a primary supply agreement and a clean capacity accelerator agreement for Google's 1.0 GW Van Buren Township data center — were conditioned on that date. This is the state's first contested rate case for a hyperscale data center, distinguishing it from the December 2025 Saline Township approvals, which AG Dana Nessel is separately appealing (briefed Aug. 7, 2026). Nessel's core objection is stranded-cost risk: that existing ratepayers could be charged if the data center draws less power than forecast or exits before the 20-year contract term expires. Continue to treat U-22058 as pending, not approved. A four-business-day slip past a contract-conditioned date is itself informative — it is consistent with either a contested drafting process or a request for modified conditions, and either outcome is consequential.
NCCETC and SEPA published the Q2 2026 DELTa update commentary on Sept. 1, 2026. Headline figures: 104 approved and pending tariffs and service rules across more than 70 utilities (up from 41 in July 2025); 69 approved and 35 awaiting regulatory decision; 37 states with at least one tracked tariff; 25 new large-load tariffs and service rules proposed in 2026 year-to-date; and 45% of tracked tariffs specifying a large-load threshold of at least 50 MW peak demand, aligning with the threshold FERC recommended in its June 2026 transmission-level interconnection show-cause orders. One quarter of tracked tariffs now include a concrete dispatchable large-load flexibility option or codified curtailment pathway, typically via an optional interruptible service rider. The post situates tariffs against four other flexibility mechanisms — wholesale market rules (SPP CHILL, FERC's six show-cause orders), state legislation (Texas SB 6, Virginia HB 284/SB 371), cross-agency working groups (North Carolina Energy Policy Task Force, Washington Data Center Workgroup) and bespoke contracts (Georgia Power's load flexibility compliance report; Google's OPPD, TVA and Indiana Michigan Power partnerships). Note for tracker hygiene: this is the Q2 data release commentary, not Q3. The Q3 2026 DELTa release remains outstanding and is expected by end of September.
The Woodford County Fiscal Court approved a permanent countywide prohibition on data center construction at its Sept. 8, 2026 meeting, the first permanent county-level ban in Kentucky. Judge-Executive James Kay described the coordination as unusual: the Fiscal Court worked with the Versailles and Midway city councils so that all three jurisdictions adopted identical banning language, closing the municipal-annexation route that has undercut county-level restrictions elsewhere (compare Festus, Mo.). The ban is framed as farmland and rural-character preservation in a county that is the 14th smallest in Kentucky by area but holds some of its most valuable Thoroughbred operations. Because it is permanent rather than time-limited, it carries no expiry date to track.
Levy County commissioners unanimously approved Ordinance 2026-05 halting applications, permits and rezonings for new data centers and other large-scale, power-intensive facilities in unincorporated areas until Sept. 30, 2027. The county has no existing zoning category addressing data centers. The ordinance directs staff to study water supply, drought conditions and conservation given reliance on the Floridan Aquifer, plus electricity, infrastructure and environmental impacts, with recommendations due by August 2027 or a status report if regulations are not ready. Exemptions cover telecom infrastructure, public safety facilities and previously approved projects. Note the tension with state policy: Florida utilities face an Oct. 1, 2026 statutory deadline to file compliant large-load tariffs under Fla. Stat. 366.043(8) even as counties close the land-use door.
Christiansburg's Town Council voted 6-0 on Sept. 10, 2026 to require conditional use permits for all data center proposals, removing their prior by-right entitlement in industrial zoning districts. Planning Director Retta Jackson and Town Attorney Reid Broughton said the amendment also clarifies previously vague definitions. Mayor Mike Barber acknowledged the change could slow or halt applications, citing water demand, energy use and limited long-term job creation; Councilwoman Johana Hicks pressed for speed to prevent projects filing under the old definitions. Council plans to revisit definitions later but the CUP requirement stands now. This is the discretionary-review template — no sunset, no moratorium optics — and it is spreading faster than outright bans in Virginia.
Imperial County Superior Court Judge L. Brooks Anderholt ruled that county officials 'prejudicially abused' their discretion by approving a lot merger for a nearly 1-million-square-foot data center complex without conducting CEQA environmental review, halting development and ordering the review. The suits were brought by the city of Imperial and the Sierra Club, which argued the project — including natural gas generators, a battery system and a new substation adjacent to the Victoria Ranch neighborhood — would strain water, power and air quality. Developer Sebastian Rucci vowed to appeal, citing ~$12M in annual tax revenue. For queue and siting purposes the relevant signal is that ministerial/streamlined approvals of large campuses in California now carry meaningful reversal risk, independent of the AB 2383 / SB 886 / SB 1168 bills sitting on Gov. Newsom's desk.
Eugene city officials rejected a buyer's proposal to build a data center at the former Hynix plant, ruling the project prohibited under the site's E-1 Campus Employment zoning. The city reasoned data centers are 'almost self-operating' and do not meet the employment-focused intent of the zone, rejecting the applicant's argument that they qualify as IT services. The determination is appealable to the Oregon Land Use Board of Appeals, which can uphold, remand or overturn. Context: Gov. Kotek has paused data center projects on state-owned land until 2027 and advocates are pushing a three-year statewide moratorium; local groups plan to request a Eugene moratorium at the Sept. 14 council meeting, and city leaders will take up the issue more broadly in December. The Oregon Data Center Advisory Committee holds its final public meeting Sept. 23.
Clinton Township (Wayne County) supervisors voted unanimously to deny Lindy Corporation's proposed 20-building data center campus after nearly six months of review, following a township engineer's conclusion that the plan was not environmentally sound. Supervisor Ken Coles said the application was incomplete and the township was not obligated to grant further extensions. Attorneys will meet with the applicant within 15 days to review deficiencies, leaving a revised submission possible. The Save Browndale Mountain Group organized the opposition. This is a completeness/engineering denial rather than a zoning or moratorium action — a reminder that in Pennsylvania, where Gov. Shapiro's Executive Order 2026-05 explicitly targets speculative proposals, application quality is itself becoming a gating factor.
Lancaster County officials opted against adopting a data center moratorium, instead creating task forces to study the facilities' impacts. Read alongside Kokomo, Ind. (Sept. 9, where the council president called a moratorium 'kicking the can') and Lubbock, Tex. (Sept. 10, non-binding standards resolution), this is now a discernible counter-current: jurisdictions that engage the issue but decline the pause. For queue purposes these are the markets where development timelines are not interrupted, and they are worth tracking with the same discipline as the ban list — the moratorium census systematically undercounts them because 'no action taken' produces no ordinance to record.
Lubbock City Council members unanimously passed a non-binding resolution directing staff to develop proposed standards for large-scale data centers before development proceeds within city limits. No moratorium, no permit change and no effective date attach to the resolution itself; the operative question is what staff bring back and when. Note the ERCOT overlay: Texas large loads are separately governed by SB 6 (2025) disclosure and curtailment obligations and by ERCOT's PGRR145 Batch Zero process, which remains paused behind the Abbott-directed audit with a Dec. 10, 2026 report target — so Lubbock-area projects face a state-level queue constraint regardless of what the city writes.
In Licking County — the heart of Ohio's data center build-out — residents in Heath and Johnstown are pressing for special elections after failing to qualify charter amendments for the November 2026 ballot. Heath's petitions fell short on valid signatures and organizers must restart the drive; Johnstown's council said it lacked time to certify petitions before the cutoff and was expected to approve a special-election ordinance at a Thursday meeting. The amendments would mirror measures already adopted in ten other Ohio communities banning facilities consuming more than 25 MW. The Licking County Board of Elections says special elections must be scheduled within 60 to 120 days of approval, putting any vote in the November 2026–January 2027 window. Compare Trenton, Ohio, which placed its charter amendment on the ballot directly.
The MPSC's regular meeting was set for 1 p.m. Thursday, Sept. 10, 2026, the date DTE requested and the date to which the special contracts themselves are conditioned. As of the morning of Sept. 11 no Commission order, news release or contemporaneous press report confirming an outcome in U-22058 has appeared in public sources; the most recent Planet Detroit update (modified Sept. 10, 16:24 UTC) still frames the decision prospectively. We are therefore holding the Sept. 10 key date open rather than recording an approval or denial. The stakes are unchanged: this is Michigan's first contested hyperscale rate case (contrast the ex parte Saline/Green Chile Ventures approval of Dec. 18, 2025), AG Nessel has sought stronger ratepayer protections against underutilization and early-termination cost shifts, and her appeal of the Saline approvals was briefed Aug. 7, 2026. Verify against MPSC E-Dockets before relying on any reported outcome.
DTE requested an MPSC decision by Thursday, Sept. 10, 2026 on the special contracts supporting Google's ~1.0 GW Van Buren Township campus; the Commission's regular meeting is set for 1 p.m. that day and the contracts are conditioned on approval by that date. This is the second DTE hyperscale contract before the Commission: the Saline contracts were approved with ratepayer-protection conditions in December 2025, AG Nessel petitioned for rehearing in January 2026 and briefed her appeal of that approval on Aug. 7, 2026. Earthjustice filed initial and rebuttal briefs on July 20 and Aug. 3, 2026 seeking additional safeguards on cross-subsidization and DTE's Renewable Energy Standard compliance. As of this morning's run no order had issued.
Kokomo Common Council advanced amended zoning permitting data centers on industrial sites 6-2 on first reading over opposition from 11 public commenters, who faulted the ordinance for not addressing utility consumption or quality-of-life impacts. Council President Greg Davis expressly rejected a moratorium. Final adoption is scheduled for the council's Sept. 14, 2026 meeting — the same date as Charlotte's moratorium-extension vote, making the two a useful paired read on divergent municipal posture. Kokomo sits in Indiana Michigan Power territory, where the IURC-approved large-load settlement tariff applies at 70 MW single-site / 150 MW aggregate.
Contrary to the agenda framing carried into Tuesday, the Sept. 8 Gallatin City Council action was an advance, not an adoption: councilors voted unanimously to move the planning-commission-recommended 12-month moratorium forward and set the formal vote for the following week's meeting. The unanimity matters more than the delay — the planning commission had recommended only 5-2 on Aug. 25, and the June 23 posture was a deferral, so the council has consolidated behind the pause even as it slips the effective date. Gallatin is an operating host community, not a speculative one, which is what makes it a bellwether for Middle Tennessee.
Charlotte City Council received staff findings from its data center study on Sept. 8 along with a recommendation to extend the 150-day moratorium adopted unanimously in early June, which sunsets Nov. 5. Staff cited unfinished work on air-pollution monitoring and permissible noise levels. Reporting on the exact extension length is not fully consistent — WFAE frames it as nine months, other outlets do not state a term — so treat the duration as unconfirmed pending the Sept. 14 vote. Materially, this is the largest metro in the Carolinas moving from a study pause to something closer to a policy-development pause, in Duke Energy Carolinas territory where the dedicated large-load tariff proceeding is running in parallel.
The Burgin city council approved, on first reading, an ordinance to rejoin the joint Mercer County / Harrodsburg / Burgin Planning and Zoning Commission, with Mayor Joseph Monroe casting the tie-breaking vote. This is the structural counter-move to the Panattoni 'Project Bluegrass' campus: Mercer County's one-year moratorium (adopted July 28) has a city-sized hole in it precisely because Burgin sits outside the joint commission, and Burgin's earlier 1,000-acre annexation for the developer was declared void last month before the city moved to restart it with adjusted boundaries. A tie vote on first reading means adoption is not assured. Watch the second reading.
Speaking to the Executive Council on Sept. 2, Gov. Kelly Ayotte said she is against 'putting any data center in the state of New Hampshire' and intends to propose a moratorium lasting 'a period of years,' citing energy price impacts, water use and noise. The trigger was confirmation of hyperscale talks in Bow. The legal instrument matters here and is easy to misreport: Ayotte tied the moratorium to her forthcoming budget, which would not take effect before roughly July 2027, and reporting notes an executive order could impose a ban sooner but none has been issued. So as of today New Hampshire has a stated gubernatorial position and no enforceable restriction. It is nonetheless the first governor-level statewide 'no' in ISO-NE territory, which is the part that travels.
The Lake County Board voted Sept. 8, 2026 to adopt the eight-month moratorium on data centers in unincorporated Lake County, converting the Aug. 18 unanimous Zoning Board of Appeals recommendation and the Sept. 2 committee advancement into law. The instrument is a county board ordinance enacting a text amendment to the Lake County Code of Ordinances (reported as amending Chapter 151); it is effective immediately on passage and reported to sunset in May 2027 (Lake & McHenry County Scanner reports May 11, 2027), with the county noting it may lift earlier if permanent data center regulations are adopted first. Two features matter more than the pause itself. First, the ordinance creates a legal definition of 'data center' in the county code where none previously existed — durable regulatory infrastructure that survives the moratorium's expiry and is the precondition for the development restrictions the county says it intends to enact. Second, jurisdictional reach is limited to unincorporated territory: incorporated municipalities are untouched, including the T5 Data Center Campus in Grayslake, so the practical effect is to push siting pressure into Lake County's municipalities rather than out of the county. Lake County sits in ComEd territory inside PJM with meaningful transmission headroom, and the county states it has received no unincorporated data center applications to date — this is pre-emptive, not reactive. Combined with Mattoon's one-year auto-renewing ordinance on Sept. 2, Illinois has now produced two local enactments in a week.
Trenton City Council adopted an emergency ordinance on Sept. 3, 2026 placing a citizen-initiated charter amendment on the Nov. 3, 2026 ballot that would prohibit new data centers above 25 MW within city limits. The council had originally declined to certify the initiative; the Ohio Supreme Court ruled it must, after the Butler County Board of Elections certified 336 valid signatures against a 128-signature threshold. The county prosecutor's office hand-delivered legal notice to council and city counsel at the meeting confirming that the initiative could still be placed on the November ballot if council acted that night or at a special meeting the following day. Two structural points matter for siting risk: a charter amendment is materially harder to unwind than an ordinance-level moratorium, and the 25 MW threshold is low enough to capture most modern hyperscale and colocation configurations. A separate annexation dispute affecting the same land remains unresolved. This is the second Ohio referendum route validated by the state supreme court in under a month (following Ashville), which establishes ballot-box siting risk as a live pathway in Ohio rather than an outlier.
Gallatin (Sumner County, Tenn.) City Council is scheduled to vote Sept. 8, 2026 on a 12-month moratorium on new data center applications, per the published council agenda. The proposal originated with council member Pascal Jouvence and follows a deferred vote on June 24, a 60-day application pause adopted July 28, and an Aug. 25 Gallatin Planning Commission recommendation in favor of the 12-month version. Staff cited resident complaints about noise and utility impacts from the existing Meta-anchored campus. The immediate catalyst is the city's recent annexation of land adjacent to that campus. Gallatin currently has no data-center-specific ordinance beyond baseline zoning, so the moratorium is being used to buy drafting time. Read across the region, this extends the Middle Tennessee cluster of local pauses and puts a TVA-territory host community — one with a live operating hyperscale campus, not just a proposal — into the moratorium column.
Festus (Jefferson County, Mo.) City Council voted 5-2 on Sept. 3, 2026 to annex three additional parcels along Highway 67 tied to CRG's conceptual $6 billion hyperscale campus, expanding the assembled site beyond 360 acres. A motion to defer for further study failed. CRG confirmed the parcels are part of its conceptual plan, under which CRG would develop and an operator would subsequently take over. The annexation was completed immediately before a new Missouri statute limiting Jefferson County annexations took effect; Crystal City has filed suit challenging those restrictions. Litigation from a local opposition group against the city and developer, filed in April, remains pending, and no site plans have yet been submitted. The council's Sept. 14 meeting was cancelled for lack of quorum, which pushes next procedural steps out. Context worth flagging: Festus voters ousted every incumbent council member in April 2026 over this project, and the replacement council is nonetheless advancing it — a useful data point against assuming electoral backlash reliably converts into siting blockage.
SB 1168, authored by Sen. Jerry McNerney, cleared the California legislature unanimously and now sits with Gov. Newsom alongside AB 2383 and SB 886, all subject to the same end-of-September action deadline. SB 1168 directs the CPUC to ensure data centers bear their fair share of transmission and distribution costs rather than shifting them to residential ratepayers; AB 2383 and SB 886 direct the CPUC toward special large-load tariffs and passed on party lines. The unanimous vote on SB 1168 is the notable feature — it removes the partisan-vote framing available for the other two and raises the political cost of a veto. Each bill leaves the CPUC substantial discretion on how strictly to ring-fence data center costs, so signature alone does not resolve the ~$1.8B contested cost-shift; it relocates the fight into a CPUC implementation proceeding. Track all three as a single September decision point with three separately vetoable parts.
PJM expects to present its governance reform package to the full membership at the Sept. 24, 2026 Members Committee meeting for review and approval. The reforms respond to a FERC directive focused on enhancing the independence of the PJM Board of Managers, expanding state participation, and improving transparency. Relevance to the queue: PJM's board is the body that directed the Reliability Backstop Procurement and Interim Resource Adequacy Service filings (ER26-3380) and that will sit above the Cycle 01 process and any future large-load tariff design. A shift in board composition or in the weight given to state input changes the decision environment for exactly the co-location, large-load and capacity questions in this tracker. Adding Sept. 24 to the calendar as an item to watch rather than a filing deadline.
PJM filed its Rule 213 Answer in Docket EL26-101-000 on Sept. 4, 2026, the date Oklo had requested, resolving the open question flagged in the prior refresh. PJM asks the Commission to deny the complaint in full on the ground that Oklo never furnished a working model demonstrating the entire 750 MW facility is stable at its proposed Maximum Facility Output, and that Tariff Part VIII, Subpart B, section 403(B) affords a Project Developer only one opportunity to cure deficiencies identified by PJM. PJM frames Oklo's request as a demand for a second deficiency review, which it argues is contrary to the Tariff, inconsistent with the treatment of other applicants, and detrimental to the 715 projects that did meet Cycle 01 requirements. On the merits of the technical dispute, PJM disputes Oklo's characterization: it says it did not reject the models for failure to demonstrate facility-wide low-voltage ride-through, and points to the three-phase fault test in DMDG section 7.4 as extending beyond the IBR voltage ride-through test. Timing is the operative pressure — PJM states Phase I of Cycle 01 begins Sept. 28, 2026, thirty days after base case data posting, and argues the relief Oklo seeks would delay it. For queue purposes the read-through is that PJM is defending a hard, one-shot deficiency-cure standard at the front of the reformed cycle process, which raises withdrawal risk for complex mixed-technology and co-located configurations whose dynamic models are hardest to validate.
The Mattoon City Council voted 5-0 to enact a one-year moratorium on large-scale data center development, reported by WAND on Sept. 2 and announced by the city on Sept. 3, 2026. The threshold is 21,780 square feet (half an acre), and the moratorium reaches the extraterritorial zoning area up to 1.5 miles beyond city limits. The city will not accept new applications above the threshold while it is in force. Two design features make this materially stricter than the typical municipal pause: it auto-renews annually and requires an affirmative council vote to modify or terminate, so the default is continuation rather than lapse; and the square-footage trigger is low enough to capture edge and mid-size facilities, not just hyperscale campuses. Existing businesses meeting the city's data center definition may continue operating. Mattoon sits in Coles County in central Illinois, inside MISO Zone 4, and the action follows a lengthy public comment period. It is the second Illinois local action in the same week alongside Lake County's pending vote.
Miamisburg City Council voted unanimously 6-0 on Sept. 1, 2026 to impose a nine-month moratorium on data center development. The immediate driver is community concern over a potential large-scale data center at the former DP&L Hutchings Power Station, a retired coal site on the Great Miami River. City Manager Chris Fine framed the action as pre-emptive — to avoid being 'caught off guard by an application' — and the pause is intended to let the city write zoning rules and development standards. Retired thermal plant sites are among the most contested large-load locations in PJM's ATSI/AEP-Ohio footprint precisely because the existing interconnection and switchyard shorten time-to-power, so a nine-month zoning pause at a brownfield generation site is a more consequential constraint than the acreage suggests. Miamisburg joins a growing set of southwest Ohio jurisdictions pausing data center growth.
The Mendocino County Board of Supervisors voted 5-0 on Sept. 1, 2026 to adopt an urgency ordinance barring any new data center in the unincorporated county. It took effect immediately and runs 45 days, to approximately Oct. 16, unless the board extends it. This is the fifth California urgency-ordinance action in roughly six weeks (Coachella, Indio, Palm Springs, Eureka, now Mendocino County) and the first at the county rather than municipal level, which broadens the covered land area substantially — unincorporated Mendocino County is far larger than any of the four cities. Under California Government Code section 65858 a 45-day urgency ordinance is extendable to a cumulative two years, and on the observed 2026 California pattern the Oct. 16 lapse should be treated as conditional rather than self-executing. Mendocino sits in CAISO's far-north footprint alongside Eureka, so the direct MW at stake is small; the significance is the county-level template now circulating among California boards.
The Lake County Board is scheduled to vote Tuesday, Sept. 8, 2026 on an eight-month moratorium on data centers in unincorporated Lake County, following committee advancement in the first week of September. Daily Herald reporting indicates enactment is likely. Lake County is one of the larger collar counties in the Chicago metro and sits in ComEd/PJM territory, an area with meaningful transmission capacity and active data center prospecting, so an eight-month unincorporated-area pause is a more material siting constraint than the small downstate Illinois actions. Combined with Mattoon's Sept. 2 one-year moratorium, Illinois now has parallel local activity at both ends of the state and in both ComEd/PJM and Ameren/MISO footprints.
Reporting on Sept. 2 describes data centers and the associated ~$33B ERCOT transmission build-out as late-emerging issues eroding Gov. Greg Abbott's support in rural and suburban Texas as he seeks a fourth term. Democratic gubernatorial nominee Gina Hinojosa has called for a moratorium on new data center construction until the legislature votes on new ratepayer, water and siting protections. Abbott's counter-position is the August comprehensive PUCT/ERCOT audit, which already functions as a de facto pause on energization of new large computational loads. ERCOT is now reported to be screening on the order of 474 GW of large-load interconnection requests -- above the 438 GW figure cited at Batch Zero approval in June, and more than five times ERCOT's record peak demand. This is a political, not a regulatory, development: no new order, docket or bill number attaches to it. It is tracked because Texas holds the largest concentration of distressed large-load capacity in the national queue and the Nov. 3 election is now a genuine two-sided policy catalyst.
The Eureka City Council adopted urgency ordinance Bill No. 1061-C.S. on Sept. 1, 2026, imposing an immediate 45-day moratorium on the siting of data centers in both the city's inland and coastal zones while staff reviews potential zoning standards. Staff cited electricity demand and grid/rate effects, cooling water use, noise from cooling equipment and backup generators, carbon footprint, and cooling-effluent water quality as the impacts requiring study. The ordinance took effect on adoption and is extendable by council under California Government Code section 65858 (which permits extension to a cumulative two years). Queue relevance is modest in absolute MW -- Eureka is a small Humboldt County city in CAISO's far-north footprint -- but it extends the California urgency-ordinance pattern (Coachella, Indio, Palm Springs, and now Eureka) into a coastal-zone jurisdiction, meaning a Coastal Commission overlay sits on top of the local pause.
An Interior Board of Land Appeals administrative judge granted a stay blocking Townsite Solar 2, LLC from proceeding on an 80-acre BLM parcel near I-11 and US-95 outside Boulder City, Nev., pending review of the appeal. BLM had amended a 2023 right-of-way granted for a solar project to permit data center use and carried the original NEPA analysis forward unchanged. The judge found persuasive evidence BLM 'acted arbitrarily or capriciously' in determining the data center was 'substantially the same' as the solar plant for NEPA purposes. Appellants are the City of Boulder City, the Center for Biological Diversity and the Sierra Club, which argued BLM failed to consult the city or permit adequate public input. Significance for the queue: this is a federal-lands permitting vector distinct from state PUC and municipal zoning risk, and it directly attacks the practice of converting approved renewable ROWs to data center use.
Both chambers passed AB 2383 and SB 886, aimed at preventing large data center loads from shifting transmission and generation costs onto residential and small-business ratepayers, against the backdrop of a roughly $1.8B contested cost-allocation fight. Gov. Newsom has not signaled his intent and holds signature authority through the end of September 2026. Note the interaction risk: CAISO is simultaneously under FERC's June 18 show-cause order (RM26-4 companion dockets) to justify or reform its large-load interconnection rules, so a state cost-allocation statute could land on top of a federally directed tariff rewrite. Treat the Sept. 30 deadline as conditional -- California governors routinely act on the final days of the window.
The Michigan City Common Council discussed and advanced a proposed data center moratorium ordinance at its Tuesday, Sept. 1 meeting; the ordinance is scheduled for second reading at the Sept. 15 meeting and is not final until then. Google's roughly $832M 'Project Maize' data center remains under construction in the city and is expected to be grandfathered. Indiana now carries several of the largest active municipal pauses in the country -- Indianapolis/Marion County (23-1, binding Aug. 10, running through end of 2027) and Elkhart (9-0, data center and battery storage, through December) -- making it one of the more hostile local-permitting states in the Midwest despite MISO-region load growth.
Environmental and community groups publicly called on Detroit to adopt an interim moratorium on data center approvals while the city develops a governing ordinance. This is advocacy pressure, not enacted policy -- no Detroit moratorium exists as of this refresh, and the tracker carries it as a watch item rather than a construction ban. Worth monitoring because Detroit is the largest Michigan jurisdiction to see organized moratorium pressure and DTE's service territory sits inside MISO, where the 50 MW large-load framework and the Aug. 28 reliability-requirements filing are simultaneously in motion.
CORRECTION to the Sept. 1 refresh, which classified MISO's Large Load Interconnection Reliability Requirements filing as 'delayed / remains unfiled at FERC.' MISO in fact filed on Friday, Aug. 28, 2026 (FERC eLibrary accession 20260828-5278), and asked FERC to let the framework take effect Dec. 4. The framework defines 'large loads' at the 50 MW threshold and creates a separate 'computational load' class -- large loads with at least 25 MW of IT-equipment demand -- so data-center-specific requirements can be targeted without capturing industrial load. (The Utility Dive brief renders the threshold as '50 GW'; that is a typo for 50 MW, consistent with MISO's existing 50 MW framework.) Four requirement areas: visibility (modeling data plus real-time and day-ahead facility forecasts), phasor measurement unit monitoring for computational loads, ramp-rate limits on stable-state transitions, and voltage/frequency ride-through minimums. Grandfathering provisions protect existing and near-complete commercial arrangements. This is a partial show-cause response: MISO said it will file the remainder -- transmission products and study processes, cost-shift protections, and treatment of generation serving 'electrically proximate' large loads -- by the Nov. 16 deadline. The enforceable dates are now FERC action on a Dec. 4 requested effective date and the Nov. 16 balance-of-response deadline.
Oklo filed an emergency complaint at FERC on Aug. 28, 2026 (Docket EL26-101-000) asking the Commission to order PJM to reinstate a 750 MW generating project -- a mix of advanced nuclear, natural gas and fuel cells, backed by Meta offtake in Ohio -- into the current interconnection study cycle at its original queue position. PJM withdrew the project citing several deficiencies, including an alleged failure to demonstrate low-voltage ride-through capability. Oklo argues the withdrawal delays a project of 'critical national importance' by at least 14 months, and asked FERC to grant any waivers needed to avoid disrupting the study cycle and to direct PJM to answer by Sept. 4. Oklo shares fell about 5% on the news. Why it matters to the distressed queue: this is the first high-profile test of whether PJM's deficiency-and-withdrawal discipline survives FERC review when the withdrawn project is the generation half of a large-load pairing -- the same ride-through criteria PJM is applying to co-located and large-load-serving generation.
The Cary, N.C. Town Council voted unanimously on Aug. 27, 2026 to adopt an 18-month moratorium on all data center development, suspending development approvals, rezonings, development plans and building permits. Planning director Heather Whelehan said the period will be used to study power demand and grid capacity, water consumption, noise and vibration, site design and buffering, with periodic progress updates and an ordinance decision expected February 2028. The ordinance exempts enterprise, small-scale co-located data processing equipment drawing under 1 MW. No applications were pending at adoption.
Gov. Mikie Sherrill signed S3379/A4096 requiring every NJ data center to report total energy consumption, cooling vs. IT load, peak daily water use, water sources and backup power supply to the BPU every six months for three years. A separate bill signed the same day (the 'End Data Center Tax Credits Act') cuts the remaining ~$250M allocation for data center/AI incentives under the Next New Jersey Program, effectively terminating the $500M program; the single $250M award already made by the NJEDA is unaffected. An OPRA carve-out in the reporting law limits public disclosure of the submitted data. Legal instrument confirmed: bills signed into law, not executive order. NJ has explicitly declined a statewide moratorium.
Rep. Andrea Salinas (D-OR) introduced H.R. 10102 on Aug. 13, 2026, amending the Internal Revenue Code to impose a $0.01/kWh excise tax on electricity consumed by data centers with more than 1 MW of power capacity, applying to both grid-supplied and on-site generated power. Estimated to raise ~$1.76B/yr, split five ways including the Land and Water Conservation Fund and the Housing Trust Fund (~$352M each). Referred to House Ways and Means, with additional referrals to Energy and Commerce and Science, Space and Technology. No markup scheduled. Materially, the on-site generation reach is the provision with implications for behind-the-meter and co-location structuring.
Rep. Henry Cuellar (D-TX-28) introduced H.R. 10139, the Ratepayer Bill of Rights Act of 2026, on Aug. 24, 2026, after previewing it at an Aug. 17 media briefing in South Texas. The bill applies to covered projects with peak electricity demand of at least 50 MW or daily water use of at least 100,000 gallons, and would require disclosure of projected and actual resource consumption, associated infrastructure development, costs, and any public assistance received. Its operative provision bars charging ratepayers for electricity, water, wastewater, infrastructure, mitigation or related costs caused by a covered project. This is the third live federal ratepayer-protection vehicle tracked here, alongside H.R. 10102 (Data Center Community Reinvestment Act, 1 cent/kWh excise) and H.R. 9340 (Ratepayer Protection Act, cleared House Energy & Commerce 52-0 in July). None has floor time scheduled; the signal value is that the 50 MW disclosure threshold is converging with the state large-load tariff threshold, which would make federal disclosure and state tariff triggers coincide.
H.R. 9340 (Reps. Gabe Evans R-CO / Kathy Castor D-FL) would require states to consider adopting a federal standard directing data centers to pay the full cost of new generation and transmission upgrades needed to serve them. Advanced from House Energy & Commerce 52-0 on July 21, 2026 as part of a seven-bill energy markup; leadership narrowed the bill to data centers specifically ahead of the markup. No floor vote scheduled as of Sept. 1, 2026. Added in this refresh as backfill — the federal legislative track was not previously represented in this tracker.
H.R. 8241 (Reps. Paul Tonko D-NY and Kweisi Mfume D-MD), with Senate companion S.3682 (Sen. Chris Van Hollen D-MD). Directs FERC to ensure data centers pay for local transmission upgrades and requires electric grid operators to create a data center load queue; prioritizes loads bringing their own generation and storage, mitigating pollution, and creating jobs. Introduced April 2026, no committee action to date. Added as backfill in this refresh alongside H.R. 9340 and H.R. 10102 to establish federal legislative coverage.
Monday full scrape added 48 local records, bringing the census to 274 (220 active or permanent; 18 states classified at the posture level as active-ban). Level mix now skews County (97) and City (94). Notable additions: Harford County, MD — first Maryland county to prohibit data centers outright by zoning code, citing insufficient electrical capacity for hyperscale load; Mansfield and Holyoke, MA — permanent zoning bans (Holyoke bans them in every district); Independence County, AR — five-year pause, longest in Arkansas; Cherry Hill, NJ — permanent ban on large-scale AI/cloud facilities in a Philadelphia-metro township (small server rooms exempt); Town of Tonawanda, NY — Local Law 2-2026 sets a 20 MW threshold expressly tighter than the 50 MW state EO 62 line; Hillsboro, OR — emergency 120-day pause called with one day's notice to pre-empt an application rush, covering battery storage as well; Denton, TX — council opened a moratorium process with hearings Sept. 22 and Oct. 27 and an adoption vote Dec. 2; Palm Beach County, FL and Manatee County, FL — one-year pauses recommended/drafting. The recurring pattern worth tracking for co-located storage siting: a growing share of these ordinances sweep in battery energy storage alongside data centers (Hillsboro, Charlestown RI, Harwinton CT, Elkhart IN, Dearborn County IN, Dunn County ND).
The Aug. 31, 2026 refresh of the 50-state policy-posture classification (datacenterbans.com, last updated Aug. 28) re-rated 13 states versus the prior week. Upgrades to 'Active Ban / Moratorium': Texas, Arkansas and Nevada (each from 'Favorable / Incentives'); New York and Pennsylvania (from 'Legislation Advancing'); North Carolina, Kentucky and Oregon (from 'Under Discussion'). Other movement: Mississippi 'Favorable' → 'Under Discussion'; Montana, Nebraska and Wyoming 'No Action' → 'Under Discussion'; New Mexico 'No Action' → 'Legislation Advancing'. Resulting distribution: Active Ban / Moratorium 18, Under Discussion 17, Legislation Advancing 7, Favorable / Incentives 4, No Action 4 — verified against the source's own on-page legend counts. The 'Favorable' cohort is now only South Dakota, Utah, West Virginia and Alabama. Caveat on interpretation: the upgrade for Texas reflects the ERCOT/PUCT interconnection audit pause rather than a construction moratorium in the zoning sense, so the label conflates two different kinds of constraint — but both bind new large load.
At a special hearing on Aug. 27 the Elkhart City Council voted 9-0 to adopt a moratorium suspending new data center and battery energy storage applications within city limits through Dec. 31, 2027. The stated purpose, per the sponsoring council member's memo, is to protect public health, safety and welfare while the city completes targeted impact studies on electrical capacity, water use, public safety, traffic, noise and environmental effects, and writes development standards. Mayor Rod Roberson characterized it as a pause rather than a rejection. The measure had advanced on Aug. 18 and was finalized Aug. 27. Jurisdiction is city-only; Elkhart County retains its own authority. Notable for the Edged thesis in two ways: (1) it is the third Indiana municipal action in three weeks, after Indianapolis/Marion County's Aug. 10 construction bar through end-2027, suggesting an in-state cascade rather than isolated votes; and (2) it bundles BESS into the same pause, a pattern that increasingly constrains co-located storage as a curtailment-mitigation strategy, not just the compute load itself.
Austin City Council on Aug. 27, 2026 approved a resolution initiating Land Development Code amendments to define and regulate data centers, including potential prohibition of hyperscale facilities. Austin's current code accommodates data centers up to ~20 MW and has no standards for facilities above 75 MW; 10 smaller data centers exist in the city and staff report no confirmed hyperscale applications. Staff will return phased draft regulations, with the first round targeted by end of 2026 and the full LDC amendment process potentially running into spring 2027. Interim posture: any large-scale data center proposed within city limits requires City Council approval before proceeding. Mayor Kirk Watson emphasized building 'legal, durable and enforceable' rules; CM Vanessa Fuentes and at least four other members publicly support a complete hyperscale ban.
Protest round closed on PJM's July 31, 2026 Reliability Backstop Procurement filing (FERC Docket ER26-3380-000). State consumer advocates ask FERC to reject; NRG Business Marketing filed a limited protest earlier. RBP is a one-time procurement covering 2027/28 and 2028/29 BRA shortfalls (6,831 MW in 2028/29), terms up to 15 years, max willingness-to-pay $555/MW-day. Bid/offer window targeted Sept. 30-Oct. 21, results early December. Awaiting Commission action -- no order.
Palm Springs, CA council approved a 45-day temporary moratorium on new data center projects Aug. 26, 2026. Coachella, CA converted its June 4 moratorium (45 days + ~10.5-month extension) into a permanent ban; Planning Commission approved the permanent-ban draft July 15, council votes carried in August. Desert Hot Springs and Indio have temporary moratoriums in force. Coachella Valley Technology Campus (400+ acres, 6 data centers) previously shelved.
Aug. 26, 2026 reporting: WA legislators expect to impose new data center rules in the 2027 session after HB 2515 (20 MW threshold, mandatory utility large-load tariff/policy filings) failed in 2026. Data Center Workgroup final report due later in 2026; Governor's task force report expected to shape the 2027 session. Separately, SB 5982 requires WA utilities to file large-load tariffs by Oct. 1, 2026.
San Antonio council special session Aug. 25, 2026: declined a proposed 90-180 day citywide data center moratorium; will pursue Universal Development Code amendments instead. Draft UDC terms: 500-ft setback from residential, hospitals, schools, nursing homes, day cares; industrial/commercial districts only; no downtown; landscape noise buffers. Mayor also proposed 50 dBA day / 45 dBA night limits, enclosed diesel generator housing, and Special Use Authorization (case-by-case council approval). Existing sites grandfathered. 23+ operating, 11-12 in development. Zoning Commission Sept. 15; council vote Oct. 15. Comparison point: Tucson, AZ ordinance approved Aug. 5 (1,000 ft commercial / 0.5 mi residential).
Colorado PUC Proceeding 26AL-0137E (filed April 2, 2026). Remote public comment hearing held Aug. 25, 2026 with a non-unanimous settlement pending. Principal contested issues: the Speed-to-Market pathway that would bypass the large-load tariff under review, the 50 MW threshold, and cost-allocation methodology. Base structure requires >=50 MW customers to fund transmission, substation, interconnection and new generation capacity costs. No Commission decision yet.
On Aug. 24, 2026, sixty members of the New York Assembly and Senate signed a joint letter urging Gov. Hochul to sign the Responsible Data Center Development Act (S10642/A11560), which passed both chambers in June 2026 and has not been signed or vetoed. The bill applies a moratorium threshold of 20 MW, materially below the 50 MW DEC-permit threshold in Executive Order 62 (signed July 14, 2026), and would establish a statutory rather than executive pause. The sign/veto posture remains open; EO 62 continues to operate in the interim as the binding constraint on new NY DEC permits for facilities at or above 50 MW. For siting purposes, the 20 MW threshold would sweep in a substantially larger population of projects, including many edge and colocation-scale facilities that EO 62 does not touch.
TVA Board action Aug. 20, 2026. New data center wholesale rate class; Capacity Commitment Charge on new/expanding data center load >5 MW effective Oct. 1, 2026. Adopted with TVA's 2026 IRP and FY27 budget (>$13B generation/transmission through FY29). ~10% overall billing impact phased over three fiscal years. Federally self-regulated — no state PUC docket, no intervenor path.
Delaware PSC Docket 25-0826 (opened Oct. 15, 2025 on joint PSC Staff / Division of the Public Advocate petition): large-load tariff development for Delmarva Power customers ≥25 MW, plus a concurrent pause on new large-load interconnections in Delmarva territory until a tariff is established. Hearing Examiner appointed. Pause still in effect as of latest public reporting; no end date set.
Day 1 of the Aug. 25-26 evidentiary hearing in Docket 20260064-EI. ~5 hours of testimony. Florida Rising (Earthjustice) admitted as a party over Duke's objection; also of record: OPC, FIPUG, PCS Phosphate White Springs. Briefs due Sept. 15. First contested application of SB 484's full-cost-of-service standard; sets the template ahead of the Oct. 1 statutory filing deadline for all Florida IOUs.
Four-month moratorium finalized Aug. 24 (second reading passed, third reading waived). Runs through Nov. 23, 2026 with a one-time 60-day council extension available. Council had rejected a moratorium in June before reversing in July. Swarm Systems project presented same night; no action taken, land-sale motions failed.
Salix, IA council voted 3-2 on Aug. 20 against a one-year data center moratorium. Recorded as a negative data point in the national local-moratorium census; no construction restriction in force.
Two competing clocks: MISO LLWG materials (Aug. 12) signal a Large Load Interconnection Reliability Requirements tariff filing before end of August 2026; the EL26-70 abeyance track allows until ~Nov. 15-16, 2026 for the substantive show-cause response. No FERC filing as of Aug. 26. Aug. 27 LLWG call is the next checkpoint. Attachment GGG (MHVDC, PAC-2024-6) remains a separate, still-unfiled workstream.
At its Aug. 20, 2026 open meeting (PUCT Project No. 59142), the Commission approved all three good-cause exceptions ERCOT filed Aug. 10 under 16 TAC 25.3(b): (1) relief from the Planning Guide 9.3.1(2)(a) Aug. 7 classification deadline, permitting conditional classification; (2) deviation from Planning Guide 5.3.5(5)(a)(ii) so conditionally-eligible Base Loads may participate in the August and November Quarterly Stability Assessments (6 projects flagged for the August QSA on Q1-2027 energization dates, 17 for the November QSA on Q2-2027 dates); and (3) authority to notice dynamic-data deficiencies after Aug. 7 while preserving a 24-day cure period measured from actual notification. ERCOT SVP/GC Chad Seely stated ERCOT will not complete the Batch Zero study by April 9, 2027 and has not yet proposed a new date; ERCOT is targeting a Dec. 10, 2026 comprehensive verification/audit report filing. Approximately 300 large loads of 75 MW or greater are in Batch Zero; a separate Community Impact Audit covers computational loads of 25 MW and above (an April snapshot of ~157 medium facilities totaling ~8,800 MW is being refreshed). Seventeen large loads totaling ~6.6 GW peak have cleared stability assessment and await energization approval, which remains withheld pending verification.
Executive Order 2026-05 ('Protecting Pennsylvania Consumers from Data Center Impacts'), signed Aug. 18, 2026, directs PA DEP to build a new permitting review framework for projects with peak demand above 25 MW. Applicants executing a consent order and agreement binding them to the Commonwealth's February 2026 infrastructure development standards receive rolling DEP review; non-signatories are not reviewed until all local permits and water withdrawal/wastewater discharge authorizations are secured. Standards require full cost causation (energy, ancillary services, transmission, distribution, network upgrades) and supply from new generating resources in the same PJM zone, with firm clean energy (solar, advanced nuclear, storage) ramping from 10% on Jan. 1 to 14.5% three years later and 32% by Jan. 1, 2035. The order also directs DEP to expedite clean energy and storage permitting on brownfields and to facilitate advanced reconductoring on existing rights-of-way, removes existing data center projects from the 2024 PA Permit Fast Track Program and rescinds their eligibility, and bars state agencies from entering confidential agreements with data center developers. This is an executive order, not legislation; it does not amend the July 2026 budget-bill oversight provisions or the PA PUC's May 13, 2026 model large-load tariff framework, both already tracked.
Final vote (24-1) on the moratorium advanced by the Planning & Zoning Committee (7-1) on Aug. 4-5; pauses new data center construction approvals in Louisville Metro for 180 days or until comprehensive zoning rules are adopted, whichever is first.
Fort Worth City Council voted unanimously (Aug. 11) to initiate -- not finally adopt -- a 90-day moratorium on new data center construction following a late-night public hearing. Per Fort Worth Report/KERA/The Texan, the moratorium's earliest possible effective date is Feb. 16, 2027, and zoning applications filed before that date fall outside it. The council concurrently created the Fort Worth Data Center & Infrastructure Commission and adopted an ordinance requiring new data center permit applications to include evidence of grid interconnection approval from PUCT and ERCOT. This is a distinct, Fort-Worth-specific action alongside Denton's Aug. 5 moratorium vote and the broader Abbott/PUCT/ERCOT statewide audit already tracked.
In an order filed July 31, 2026 (reported by Utility Dive, Virginia Mercury, Virginia Business, WTOP, DCD, henricocitizen.com the week of Aug. 4-7), the Virginia SCC directed Dominion Energy to develop and file, within 90 days, a new cost-allocation policy that directly assigns the cost of 'direct-connect' transmission facilities (substations/lines built solely to serve a specific large-load customer) to that customer rather than to the broader Rider T-1 ratepayer base. The order followed a July 14, 2026 SCC hearing on Dominion's proposed Rider T-1 increase (~$1.5B in transmission cost recovery) and a filing by Gov. Spanberger's administration on behalf of ratepayers. This is distinct from the previously-tracked GS-5 large-digital-customer rate class (approved July 1, 2026) and the data center consumption tax (signed June 30, 2026) -- this action addresses transmission cost allocation specifically, via Dominion's Rider T-1 docket.
Governor's office press release (Aug. 12) announcing Google, Rowan, and CleanSpark as the latest companies to commit to Abbott's PUCT/ERCOT data center standards (grid infrastructure cost responsibility, water reuse, community-impact mitigation, ownership/incentive disclosure). Continues the same compliance-pledge pattern intel.json already tracks for QTS (Aug. 6) and Skybox/Digital Realty/Mara (Aug. 7). Per Dallas Express (Aug. 11), the intervening wave -- Meta and OpenAI (Aug. 10), then Oracle, EdgeConneX, and Stream Data Centers (Aug. 11) -- is not yet reflected in intel.json; flagged here for the next morning refresh to backfill for completeness.
Consolidated explainer of the legal mechanics behind the Aug. 3 Abbott directive to PUCT/ERCOT, cross-referenced against the governor's letter, ERCOT Market Notice M-A080326-01, and law-firm alerts (Butler Snow Aug. 4, Foley & Lardner, Holland & Knight Aug. 11). Confirms: (a) legal instrument = administrative directive/letter, not a signed bill or numbered executive order; (b) scope = audit precondition on APPROVING new ERCOT interconnections (~2,000 pending projects, ~474 GW queue), not a curtailment or disconnection order for projects already energized and operating; (c) enforcement = noncompliant projects 'must be denied' grid connection per the governor's letter; (d) immediate effect = ERCOT suspended the Aug. 7 Batch Zero classification notifications and will seek a PUCT good-cause exception (filing not yet confirmed as of Aug. 12; PUCT addresses it at the Aug. 20 open meeting). No statutory or regulatory end date has been set.
Holland & Knight's Aug. 11 client alert confirms the Aug. 3 Abbott audit directive and ERCOT's Batch Zero pause have created 'immediate regulatory uncertainty' with no predictable resolution timeline. The firm's Texas Government Advocacy Team announced formation of the Texas Data Center Association to represent the industry before state policymakers, and is advising clients that political engagement is now as important as land/power access for Texas projects. Also flags the Governor's directives to the Texas Legislature (reported by H&K in June) as directly linked to the audit's scope.
Gov. Abbott announced Aug. 7 that Skybox Datacenters, Digital Realty, and bitcoin miner/hyperscale developer Mara have committed to comply with his Aug. 3 audit standards, citing existing/pledged practices on grid infrastructure cost responsibility, water use and reporting, cooling technology, load flexibility, and community impact. This follows QTS Data Centers' (Blackstone portfolio company) Aug. 6 statement welcoming the audit and framing it as a chance to distinguish 'responsible' operators from speculative ones. Any project that fails the PUCT/ERCOT verification process is subject to denial per the governor's directive.
BloombergNEF's Aug. 5 report (Flakoll/Limandibhratha/Daly) models a 3-month delay across ERCOT's Q3 2026-Q1 2027 data center capacity additions slipping to Q2 2027, exposing 49.8 GW (~20% of the U.S.'s 253-GW pipeline) and costing projects roughly $8B cumulatively (60% AI-compute mix) up to ~$15B (100% AI mix) by Q1 2027. BNEF frames the audit as politically timed ahead of Abbott's November re-election and warns 'the pause could last months,' with risk of extending into the Texas Legislature's 2027 session (convenes January, could run as late as April) - which would create an opening for lawmakers to further restrict SB6's large-load framework. ERCOT's own Batch Zero study delivery target has since slipped from Jan. 29, 2027 to April 9, 2027, consistent with BNEF's scenario.
New — not previously tracked. Distinct from the July 6 Independence, MO moratorium; this is a state-legislative signal (2027 bill re-file plus a local-government guidance document) rather than a local enactment.
Confirms and closes out the previously-tracked 'upcoming' Aug. 10 council vote; moratorium passed 23-1 and now awaits Metropolitan Development Commission final approval (as early as Aug. 19).
New reporting (Canary Media, republished by Ohio Capital Journal, Aug. 10) confirms PJM's IRAS/'BYONC' large-load framework and a new 50 MW+ large-load registry are now pending at FERC, following the July 27 board decisional letters; enforcement responsibility falls largely on states/utilities, not PJM directly.
Follow-up reporting (TPR, Aug. 9) adds detail to San Antonio's pending moratorium request: Councilmember Galvan wants CPS Energy and SAWS to require clean energy and recycled water for new data center facilities; the special council meeting request (by Aug. 31) has not yet been granted or voted on.
New — not previously tracked. A gubernatorial statement of support (not a bill signature or executive order establishing a moratorium — Oregon's governor has no unilateral authority to impose one) plus a confirmed state-land contract termination.
Three of San Antonio's 10 council districts are pushing for a formal council vote on a data center construction moratorium, requesting a special meeting by Aug. 31; a supporting press conference was held Aug. 7 at City Hall.
Denton City Council voted 4-3 to direct staff to proceed with a possible moratorium on data centers and related amendments to the city's development code. No moratorium is yet in effect; the council will set the first public hearing date at its Aug. 18 meeting.
Virginia SCC ruled in Case PUR-2026-00056 (Dominion's Rider T-1 transmission cost rider case) that new transmission infrastructure built exclusively to serve data centers/large loads should not be spread across all ratepayers. The order directs Dominion to develop a policy/tariff for direct cost assignment to large-load customers 'with the goal of finding an acceptable and symmetrical approach.' Gov. Spanberger's administration had intervened urging this outcome; order is projected to save residential ratepayers hundreds of millions vs. status quo cost-spreading. Primary source: SCC order at scc.virginia.gov/docketsearch/DOCS/8dmn01!.PDF. Also corroborated by WJLA, WTOP, Virginia Mercury, News From The States (2026-08-05 coverage).
Councilwoman Chappell's reintroduced temporary moratorium on new data center construction cleared the Planning & Zoning Committee 7-1 on Aug. 4-5 and now heads to the full Metro Council, with a final vote expected at the Aug. 13, 2026 meeting. Jeffersonville, IN, just across the river, separately approved its own 1-year data center moratorium the same week.
New — not previously tracked. Precedes and is distinct from the Aug. 7 Kotek statement; both are state-level (not local) Oregon developments.
Gov. Greg Abbott directed PUCT and ERCOT on Aug 3 to audit all data center applicants seeking grid connection before further approvals proceed, covering power demand/generation, water use/cooling, tax breaks received, community-impact mitigation, and ownership. Scope: ~2,000 proposed projects across ERCOT's ~474 GW large-load interconnection queue. Confirmed via Texas Tribune, Houston Public Media, KERA, Axios San Antonio, and Foley & Lardner client alert (2026-08-03/04). No formal EO number identified in any source as of this refresh — treat as an administrative agency directive, not signed legislation or an executive order, pending confirmation of the specific legal instrument.
Salem City Council unanimously adopted a resolution to begin updating zoning/land-use code toward a temporary data center moratorium. Staff must send the required 45-day notice to Oregon's Department of Land Conservation and Development by Aug. 10, 2026; earliest hearing estimated for the second September council meeting (Sept. 21).
Greensboro City Council voted 9-0 on Aug. 3 to reverse its July 21 5-4 rejection and begin the formal process toward a 120-day moratorium on new data centers requiring more than 10 MW. Public hearing scheduled for Aug. 17, 2026, 4pm, Katie Dorsett Council Chamber, Melvin Municipal Office Building.
Per FERC's June 18, 2026 Section 206 show-cause orders (RM26-4) to PJM, MISO, SPP, CAISO, ISO-NE, and NYISO, requests for full or partial abeyance (up to 90 days) of the Aug 17 tariff-justification/revision deadline were due 45 days after the order, i.e. Aug 3, 2026. FERC stated it will heavily scrutinize abeyance requests and disfavor extending the abeyance period once granted.
SPP's High Impact Large Load (HILL) integration framework includes both CHILLS (conditional, curtailable near-term service, FERC-approved and effective July 1, 2026) and a longer-lead cluster study path under the Consolidated Planning Process (CPP). The first CPP large-load cluster study begins August 2026, with interconnection agreements expected in spring 2027.
SCC Case No. PUR-2026-00056 concerns Dominion's Rider T-1 (transmission cost recovery). Governor's office argued for a strict 'but for' cost-causation standard assigning any upgrade that wouldn't have been built but for a large-load customer directly to that customer. Hyperscalers (Meta, Google, Amazon, Microsoft), Loudoun County, and consumer advocates all filed positions. Dominion's residential impact estimate moved from $2.90/month to $0.94/month for a typical customer during the proceeding.
Montgomery County Council approved an 18-month moratorium on new data center permits (unanimous vote, July 28, 2026), alongside new limitations and safeguards on data center development going forward. No new data center permits can be issued in the county for the moratorium period.
Board decisional letter dated July 27, 2026, directs PJM to file the Reliability Backstop Procurement (targeting the ~60 GW capacity shortfall identified in the BRA, auction beginning September 2026) and IRAS/Connect & Manage successor with FERC, including a large-load compensation framework for curtailment administered by EDCs in coordination with states.
At a special July 27, 2026 meeting, Hillsboro City Council adopted Resolution No. 2932, enacting a temporary land use moratorium barring the city from accepting new applications proposing data centers or battery energy storage system (BESS) facilities as a primary use, for a four-month period.
In a July 27, 2026 decisional letter closing out the Critical Issue Fast Path (CIFP) stakeholder process, PJM's Board of Managers directed staff to file two proposals with FERC. (1) Reliability Backstop Procurement: a one-time procurement to backfill the 6,831 MW shortfall from the 2028/29 Base Residual Auction, run in parallel with a facilitated bilateral-contracting process (RFP launched June 9; initial buyer/seller matches expected August 2026). The central procurement window runs Sept. 30–Oct. 21, 2026, with results released in early December and commitments of up to 15 years; PJM proposed capping accepted supply offers at $555/MW-day, with resources required online no later than June 1, 2032. Costs will be allocated to Load Serving Entities by zone, with states deciding how they flow to rate classes. (2) Interim Resource Adequacy Service (IRAS) — the framework previously called 'Connect and Manage' — pairs with a new PJM Large Load Registry (tracking loads ≥50 MW at a single site within a 1-mile radius). New Large Loads that don't bring their own generation by June 1, 2027 and haven't otherwise secured supply will be subject to curtailment ahead of Pre-Emergency Load Management during capacity shortages, with compensation subject to a FERC-approved rate and state jurisdiction. This materially firms up (and in some respects revises the timeline of) the backstop auction process previously expected around a July 10 FERC filing and a Sept 10 bid window — the actual Board-approved dates are later (Sept 30 bid window; early-Dec results).
Backfill — identified in an Aug. 31 gap sweep, not weekend news. On July 21, 2026 Nebraska Gov. Jim Pillen signed Executive Order 26-17, prohibiting approval of data center applications under the ImagiNE Nebraska Act (the state's principal sales/property tax incentive program) and directing the Departments of Economic Development, Revenue, and Water, Energy and Environment to jointly review project proposals for state interest. The order also establishes a data center task force through DWEE oriented to natural-resource protection. Pillen stated explicitly at the signing that 'this is not a moratorium on data centers' — local entities retain siting authority, subject to the order's guidelines. Context: data centers received roughly $317M in ImagiNE credits/refunds/exemptions from Jan. 2021 through June 2026 plus an estimated $519M in property tax exemptions on ~$15B of exempted personal property. Separately, LB1261 (enacted 2026) authorizes behind-the-meter generation by large industrial users, which is the more materially relevant Nebraska development for large-load siting economics. Sen. Mike Jacobson has signaled codifying legislation for the 2027 session.
At the July 21, 2026 council meeting, an off-agenda motion by Councilwomen Crystal Black and Cecile Crawford to impose a data center moratorium was seconded but failed 5-4. No moratorium is in effect; the council held a subsequent work session to review data center opportunities and impacts.
Cherokee County Board of Commissioners unanimously approved a 30-day moratorium on data center applications at its July 21, 2026 meeting, giving staff time to draft development regulations. Officials have scheduled an August 18 public hearing at which they expect to request a 180-day extension (through mid-February 2027).
Chamblee City Council voted unanimously at its July 21, 2026 meeting to adopt a 180-day moratorium on data center development and acceptance of related applications, in effect through January 16, 2027.
Greenwood County Council approved the third and final reading of an ordinance imposing a one-year moratorium on new data center approvals, by a 4-3 vote on July 21, 2026, after separately denying a proposed data center zoning text amendment.
Milton City Council unanimously voted July 20, 2026 to extend its data center-related application moratorium (originally enacted June 15, 2026 for 30 days, then briefly extended July 6 pending a public hearing) out to a full 180 days, to allow time to evaluate existing regulations, develop amendments, and take stakeholder input before recommending a permanent framework to Council.
FERC left docket RM26-4 open rather than issuing one uniform final rule; instead used individualized show-cause orders per RTO. Intervention deadline for the show-cause dockets was July 9 (passed).
During the pause, Cleveland will not review or issue permits/approvals for new standalone, principal-use data centers or expansions of existing standalone data centers. Adds Cleveland to the growing list of Ohio municipalities (18+) considering or enacting moratoria.
PUCT approved the Batch Zero revision requests with an effective date of July 11, 2026. Developers who miss today's window risk falling out of the one-time transitional batch and into a slower, as-yet-undefined repeatable process.
This is the first hard gate in ERCOT's new batch process replacing the individual Large Load Interconnection Study (LLIS) approach. Expect a wave of classification news around Aug 7.
138,318 MW procured, $325/MW-day (cap), $16.4B total capacity cost (~$6.3B linked to data centers), reliability requirement missed by 6,831 MW — first shortfall in PJM history.
Lansing City Council 7-1 vote for a 182-day moratorium (July 27, 2026 – Jan. 25, 2027) to draft data center regulations. Fairfax, Iowa council passed a moratorium 3-1 the same night. MI legislature reintroduced statewide moratorium bills in June; Whitmer opposes.
Track separately from EO 62 — two different legal instruments with different scope and duration mechanics.
Key distinction for our tracker: EO 62 threshold is 50 MW (narrower than the bill's 20 MW); it only pauses DEC permits, not utility interconnection/tariff processes; and it does not create the new large-load rate class contemplated by S10642/A11560.
During the 183-day window the city will not accept, process, or approve special use permits, conditional use permits, zoning map amendments, or building permits for data center projects.
First state-level data center moratorium via executive action in the US. Threshold (50MW EO vs 20MW legislative bill) differs from the pending bill, so both tracks now need monitoring. Industry groups warned of economic harm; environmental advocates praised the move.
Continues the trend of rapid large-load tariff proliferation (65 in Nov 2025 -> 77 in Mar 2026 -> 104 in Jul 2026). Confirms the quarterly cadence (Mar/Jun/Sep/Dec) flagged as due this period.
The Indianapolis Metropolitan and City-County Council's committee voted 10-3 along party lines on July 13, 2026 to advance a moratorium on approval of new data centers through the end of 2027. Council President Maggie Lewis introduced the measure amid growing resident concern over water and power use; Democratic Mayor Joe Hogsett publicly backed it. If ratified by the full City-County Council at its Aug. 10, 2026 meeting, the moratorium would not apply retroactively to projects that already secured zoning clearances. This follows a broader wave in which roughly a third of Indiana counties have adopted data center ordinances or moratoria.
Sector mix behind the 232.5 GW: data centers ~158 GW (70%), industrial ~54 GW (24%), crypto ~14 GW (6%). ercotqueue.com flags its large-load dataset as running on an April 2026 public-source refresh (i.e., roughly one quarter stale relative to its own July-refreshed generation-queue data) and explicitly notes these are public-source signals, not a complete customer queue.
Signed July 7, 2026. Creates a dedicated large-load/data-center ratepayer class; BPU to set tariff terms for 50 MW+ facilities. Predecessor bill was pocket-vetoed by Gov. Murphy in early 2026; Sherrill signed the reintroduced version.
Independence City Council voted 7-0 on July 6, 2026 to impose a 180-day moratorium on acceptance, processing, and issuance of permits/licenses for new data center and battery energy storage system (BESS) facilities. Applies only to new, not-yet-submitted projects; does not affect previously authorized projects including the Nebius data center campus.
The Westfield, MA City Council voted unanimously in a second and final vote on July 6, 2026 to impose a 12-month moratorium on new data center permitting and construction, driven by resident concerns over water use, pollution, noise, and electricity demand tied to the proposed $4 billion, 274 MW Servistar Realties data center campus. The matter next moves to the Council's Natural Resources Committee to study ecological and public health impacts. This adds Massachusetts to the growing list of states seeing local-level moratoria alongside statewide legislative activity.
Per Indiana University's Environmental Resilience Institute tracker. Reflects the broader county/municipal-level pattern (Seattle, Denver, Baltimore, Atlanta, Minneapolis) where local moratoria are advancing faster than state-level bills, which have mostly stalled or died in committee.
June 30 Stage 4/Special MC meeting completed the PJM stakeholder process. FERC filing for Connect & Manage (C&M) + Reliability Backstop Procurement (RBP) expected July 10, 2026. Key C&M update: existing-load threshold moved from summer 2026 → summer 2027 (loads not online by June 1, 2027 subject to C&M unless they bring new generation). C&M triggers only on capacity shortfall and only for the shortage quantity. Backstop bid window: Sept 10–Oct 9; results by Nov 20. July 14: PJM 2028/29 BRA results determine shortfall to be procured. July 23: FERC Technical Conference on long-term PJM reform. LCEP ('Load-Contingent New Capacity at Existing Plants') proposed in FERC RM26-4 as a speed-to-power co-location pathway at existing plant POIs — advantage to incumbent IPPs. Vistra (VST): FERC cleared Zimmer 800-MW gas plant conversion (no tariff waiver needed); likely backstop candidate alongside 300 MW of CCGT uprates. Source: Jefferies Power Debrief — 'Connect & Manage or Check & Mate?' (Dumoulin-Smith et al., June 11, 2026).
ERCOT Batch Zero deadline clarified: July 10 = ILLE hard deadline; July 24 = TSP/DSP package submission; August 7 = ERCOT eligibility notifications; August 31 = final deficiency resolution. Projects missing July 10 risk being dropped from the batch entirely.
Arizona: 3-year sales-tax-exemption pause via budget (no legislative stand-alone bill), effective July 1, 2026–June 30, 2029. Illinois: executive pause on new DCIP applications from July 1, 2026; Pritzker cited need to assess whether incentives cause residential ratepayer harm. Combined market-signal: more states likely to revisit blanket tax exemptions as data center load growth strains utility infrastructure.
PJM 2027/28 BRA: $333.44/MW-day (UCAP), 134,479 MW procured. Market monitor flags continued data center load as primary driver of elevated capacity prices. Two consecutive auctions at or near FERC price cap signals structural capacity tightness in the mid-Atlantic.
RM26-4 timeline: July 9 = interventions (passed); July 20 = gen-adequacy reports; August 3 = abeyance requests; August 17 = full show cause / tariff revisions. All six RTOs must respond. If RTOs miss deadlines or provide insufficient justification, FERC can direct changes over RTO objection.
Reinforces the ratepayer cost-shifting narrative underlying the FERC show-cause orders and state large-load tariff pushes across the PJM footprint.
Signed into law June 30, 2026 (one day ahead of its July 1 effective date) as part of Virginia's $205B two-year budget. Sales/use tax exemption for qualifying DC equipment stays intact — this is a new, separate consumption tax. Sunsets June 30, 2028 absent legislative extension.
FERC's June 18 Section 206 show cause orders (RM26-4) to PJM, MISO, SPP, CAISO, ISO-NE, and NYISO set binding response deadlines. July 18 = generation adequacy informational reports. August 17 = full tariff justification or proposed tariff revisions. FERC may direct changes if RTOs fail to justify existing rules.
July 1, 2026 is a multi-state activation date: SPP CHILLS (FERC-approved June 5) allows curtailable non-firm service; Florida SB 484 (Gov. DeSantis signed May 7) takes effect; Oklahoma HB 2992 (signed May 11) mandates cost-responsibility agreements. Three distinct large-load cost frameworks go live simultaneously.
FERC's April 16 Order Regarding Intent to Act committed the Commission to issuing its RM26-4 rulemaking by end of June 2026. As of June 22 no order has been published. The forthcoming order will establish national standards for processing large-load (≥20 MW) interconnection requests, including potential 60-day study fast tracks and full cost-of-upgrade assignments. FERC's June 2026 open meeting included RM26-4 and PJM co-location (EL25-49-002) items on the agenda.
Edison Electric Institute's June 2026 Large Customer Projects and Tariffs list shows at least 36 utilities across 23 states have adopted large-load tariffs. Seven additional states have pending tariffs. Dominion Energy Virginia leads with 47.1 GW of contracted data center capacity (9.8 GW in take-or-pay ESAs, 9 GW in construction letters). Georgia Power has 28 large-load projects representing 11 GW under contract. Xcel Energy has 2+ GW contracted with another GW expected in 2026.
At its June 18 open meeting, FERC issued orders finding that existing RTO/ISO tariffs are inadequate for large load interconnection. FERC directed all RTOs/ISOs to file tariff revisions addressing: (1) efficient study/application processes including alternative transmission technologies; (2) prevention of cost shifts and transparency into transmission costs; (3) study processes for generating facilities serving electrically-proximate large loads; (4) co-located load service clarity; (5) interim non-firm service options. This is distinct from the RM26-4 final comprehensive national rule, which remains pending before the June 30 hard deadline.
NERC submitted an Accelerated Large Load Action Plan to FERC in Docket No. RM26-4 outlining reliability standards and study requirements for large load interconnection. The plan addresses modeling, system impact studies, and reliability coordinator notification requirements. Filed to inform the Commission's broader national rulemaking.
FERC's June 2026 open meeting included Item E-2 covering PJM Interconnection dockets EL25-49-002, EL25-49-000, AD24-11-001, EL25-20-001, and ER26-1479-000 — the next step in FERC's December 2025 order directing PJM to establish transparent co-location rules for data centers and generators. The June meeting also featured RM26-4 on the agenda as FERC works toward its end-of-June national rulemaking deadline. White & Case summarized the full June 2026 agenda.
PJM's Independent Market Monitor published the Q1 2026 State of Market report. Data center load accounted for $6.5 billion (40%) of the $16.4 billion in PJM's December 2025 capacity auction costs. PJM capacity prices hit the $333.44/MW-day price cap in the 2026/27 delivery year, up from $28.92/MW-day in 2024/25 — an approximately 11x increase in two years. Data center forecasts make up 45% of the $47.2 billion in capacity costs across PJM's last three auctions combined.
Following the March 31, 2026 update, SEPA and NCCETC DELTa now tracks 77 approved and proposed tariffs and service rules targeting large-load customers of 60 different utilities, with 51 approved and 26 proposed. The Q2 2026 release (today, June 15) confirms the database continues quarterly cadence.
The Virginia State Corporation Commission approved a new rate class targeting high-energy large loads including data centers consuming ≥25 MW with a monthly load factor exceeding 75%. Starting January 2027, affected customers must pay at least 85% of contracted distribution and transmission demand and 60% of contracted generation demand. Directed by VA HB 1393, the new class prevents cost-shifting to residential customers. Most of Virginia's approximately 450 data centers are expected to fall under the new class.
On June 9, 2026, the Seattle City Council passed 9-0 an emergency 1-year moratorium on new data centers using more than 20 megavolt-amperes (~20 MW), with an option to extend 6 months. A companion bill requires an environmental impact study covering grid capacity, water usage, utility rates, land use, jobs, and public health.
FERC on June 5, 2026 approved SPP's CHILLS proposal (refiled February 10, 2026). CHILLS provides 7-year non-firm transmission service for large loads that agree to curtailment during emergencies. 90-day study-and-approval process. July 1, 2026 effective date confirmed.
NY S10642/A11560: 1-year moratorium on environmental permits for data centers ≥20 MW. Gov. Hochul has 30 days to act. Would be first statewide moratorium if signed.
The ERCOT Board approved NPRR1325 on June 1, 2026 as the Nodal Protocol companion to PGRR145 (Batch Zero large load framework). NPRR1325 adds two new co-location constructs to ERCOT's protocols alongside the existing Private Use Network (PUN): (1) a Battery Energy Storage System (BESS)-linked co-location path, and (2) a direct-interconnect co-location path. NPRR1325 also codifies the Provisional Controllable Load Resource (PCLR) construct, under which ERCOT can dispatch co-located large loads downward in real time during transmission constraints. The PCLR curtailment cap relaxes over time as transmission infrastructure is built. Effective date: July 11, 2026. July 15 is the Batch Zero submission deadline for Batch Zero applicants.
ERCOT will deliver Batch Zero study results by January 29, 2027, with capacity allocations for 2028-2032. July 15 is the hard submission deadline.
Board vote June 1; effective July 10 if approved
Seattle Land Use and Parks & City Light committees vote June 3; full council vote expected June 9. Moratorium would last 365 days and cover all new large data center siting.
Backstop auction moved to September; 15 GW target; data centers drove 40% of Dec auction costs
Settlement includes data center cost-causation provisions aligned with PA PUC's May 13 model tariff framework. Customers ≥50 MW individually or ≥100 MW aggregated subject to new cost-responsibility rules.
Edison Electric Institute's May 2026 Large Load Projects and Tariffs update shows member utilities tracking ~$890B in announced investments tied to ~55 GW of connected load. Utilities are actively working to connect >80 large-load projects. 18 states have approved large-load tariffs; decisions pending in 8 more. Key highlights: AWS $21B Mississippi investment in Entergy territory; PA PUC model tariff framework (May 13); AEP Ohio new data-center tariff early 2026. EEI notes tariffs require large-load customers to fund grid upgrades, shielding existing ratepayers. Next EEI tracker update expected June 2026.
6-month pause on large data centers; downtown exempt; June 16 public hearing
Denver City Council unanimous 13-0 vote. Covers new zoning permits and site development plans for data centers. Effective May 21, 2026. City working group to draft rules on energy, water, noise, and siting during the pause.
FERC publicly committed to acting on its broader large-load interconnection docket (beyond the December 2025 PJM co-location order) by June 2026. This proceeding may extend co-location / BTM rules to other RTOs/ISOs beyond PJM. PJM capacity prices for 2027/28 delivery year settled at $333.44/MW-day (UCAP), up from $28.92 in 2024/25 — a 10x increase. Data-center load accounted for $6.5B (40%) of the $16.4B in December 2025 capacity auction costs. PJM market monitor recommends dedicated data-center interconnection track.
ERCOT Technical Advisory Committee (TAC) approved PGRR145 (Batch Zero Process for Large Load Interconnections) and companion NPRR1325 in May 2026. Board of Directors vote scheduled June 1, 2026 with July 10 effective date. Framework replaces individual LLIS studies with system-wide batch approach covering 2028–2032. Steady-state and stability screening will allocate maximum peak demand per large load per year and identify required transmission upgrades. Companion protocol language (NPRR1325) also TAC-approved.
MN state moratorium legislation dead for 2026 session; local action continues
PJM's compliance filing in response to FERC's April 16 order (Docket EL25-49) is due today, May 18, 2026. The April 16 order directed PJM to: (1) replace "Point of Change in Ownership" with "Point of Interconnection" in the Co-Located Load definition, (2) remove "Co-Located Load" from BTM Generation provisions, (3) incorporate the revised Provisional Interconnection Service definition into the Tariff, (4) file FERC-accepted Tariff language. Filing not yet posted to PJM site at time of search.
MN PUC approved; 15-yr contract; 80% exit fee; separate rate class
PJM wholesale power averaged $136.53/MWh in Q1 2026, up from $77.78/MWh in Q1 2025 (+76% YoY). Monitoring Analytics (the PJM Independent Market Monitor) formally recommended PJM create a dedicated interconnection queue that only connects new data centers when adequate generation capacity exists to serve them. This is a market-structure proposal that would put a brake on the current model where data center load can be added before serving generation is in service.
MISO closed stakeholder comment period on Attachment GGG (HVDC interconnection framework) on May 12, 2026. MISO targeting initial FERC filing within 30–60 days (June–July 2026), with a second filing later in 2026. Attachment GGG studies focus on reliable physical interconnection of MHVDC facilities; transmission/deliverability rights remain under Attachment X and Module B. Large-load workshop (Jan 2026) acknowledged aggregate large-load capacity requests materially exceeding historical norms, driven primarily by data center development.
Pennsylvania Public Utility Commission issued final order May 13, 2026 establishing a model tariff framework for large-load customers (≥50 MW individual or ≥100 MW aggregate). Follows April 30 public meeting vote. EDCs (utility distribution companies) will use this template to evaluate and serve large-load customers; framework includes provisions for customers to self-construct certain infrastructure upgrades subject to safety/reliability standards. Implements over a year of stakeholder process. Not yet reflected in SEPA DELTa database (next release June 2026).
MISO requesting stakeholder feedback on proposed Attachment GGG, MPFCA, and BPM language by May 12, 2026; targeting an initial FERC filing within 30–60 days, followed by a second filing later in 2026. Proposed framework centered on three outcomes: (i) interconnection reliability requirements, (ii) speed to reliable power, and (iii) reliable operations. Companion item: PAC April 22 covered Zero-Injection GIA and Large Load Rules.
HB 2992 signed May 11, effective July 1, 2026. Requires large-load customers ≥75 MW to execute long-term cost-responsibility agreements. Adds transparency and disclosure requirements for land acquisition tied to large-load projects.
SPP refiled the CHILLS proposal Feb 10, 2026 and asked FERC to act by mid-April with a July 1, 2026 effective date. As of May 10, no final FERC order on CHILLS has been published; effective date may slip if order doesn't issue in May. HILL/HILLGA already in force from Jan 2026 approval — CHILLS is the next layer.
Georgia Power filed nearly 2 GW of new customer contracts with the Georgia PSC — first contracts under the rules approved January 2026 enabling Georgia Power to serve large-load customers (>100 MW) through customized contracts with terms including upfront infrastructure payments, 15-year commitments, financial guarantees, and minimum billing requirements. Framework is already in the SEPA DELTa database; the contract activity is new and signals the rules are operational.
Governance timeline crystallized: Protocols Revision Subcommittee vote May 6, 2026; Reliability and Operations Subcommittee vote May 7; ERCOT Board approval target June 1; target effective date July 10. Replaces individual LLIS process with system-wide batch evaluation, year-by-year transmission allocation, and an actionable transmission plan. Workshop #7 added BYOG and CLR updates.
RM26-4 addresses: whether flexible large loads get expedited 60-day studies; full vs. partial cost allocation for grid upgrades; co-location rules beyond PJM. FERC teed up the June decision after DOE ANOPR engagement.
Secretary of Energy directed FERC to initiate rulemaking to expedite data-center and large-load interconnection. ANOPR draft accompanied the directive; FERC required to respond no later than April 30, 2026. Federal-state jurisdiction tension remains the open question; NARUC and several state regulators objected to a one-size-fits-all federal approach.
Councilmember Charles Slife introduced 1-year moratorium legislation April 28. Triggered by Lakeland Equity Group's proposed $1.6B, 150 MW data center in Slavic Village. Broader Ohio wave: 18+ municipalities considering similar measures.
FERC's April 16 order on Docket EL25-49 partially accepted PJM's compliance. PJM filed its revised compliance on May 18, 2026 — now under FERC review. Final rules expected with June RM26-4 action.
FERC accepted the tariff reforms providing clarity on interconnection pathways but rejected PJM's attempt to alter the Commission-mandated definition of 'Co-Located Load' and to revise BTM application requirements. Specifically directed: (1) replace 'Point of Change in Ownership' with 'Point of Interconnection' in the Co-Located Load definition, (2) remove 'Co-Located Load' from Behind the Meter Generation provisions, (3) incorporate the revised Provisional Interconnection Service definition into the Tariff, (4) file FERC-accepted Tariff language. Next compliance filing due May 18, 2026.
Colorado SB26-102 (Large-Load Data Centers) is moving in parallel in the legislature. Xcel's tariff proposal aligns with cost-causation principles; CPUC review ongoing with no approved date set.
Xcel Energy filed its proposed Large Load Tariff with the Colorado Public Utilities Commission on April 2, 2026. Applies to new customers or significant expansions ≥50 MW (CPUC discretion for 20–50 MW). Requires customers pay for all incremental generation and transmission required. Includes a clean-transition component for data centers using geothermal, long-duration storage, or other emerging clean technologies. Requested effective date May 3, 2026; CPUC proceeding (intervention, public comment, evidentiary) continues through 2026. Not yet in SEPA DELTa.
SB 5982 requires large data center customers (tied to utility large-load tariffs) to meet the same clean energy deadlines as utilities. Utilities must develop dedicated tariffs avoiding cost-shifts to other customers by Oct 1, 2026.
PJM's Manual 13 (Emergency Operations) Revision 98 incorporates the January 2026 Behind-the-Meter (BTM) Emergency Procedure addendum into the standing operations manual. Rev 97 (effective November 20, 2025) is the last published version on pjm.com; Rev 98 formalizes the addendum issued January 29, 2026 in response to DOE Order 202(c). The procedure establishes the communication chain for dispatching customer-owned backup generation at data centers and large industrial/commercial facilities during declared grid emergencies: PJM notifies DOE when issuing NERC EEA 1 and expecting a potential EEA 3; Transmission Owners (not PJM directly) serve as the operational contact for affected large-load customers. Use of backup generation is a last resort before firm load interruption (EEA 3).
February 5 information session followed issue paper. Working group targeting technical requirements draft by end of Q1 2026. No tariff filing yet — policy development phase.
On January 26, 2026, the DOE issued a parallel Section 202(c) emergency order for PJM Interconnection, two days after the ERCOT order. The order authorized PJM, in collaboration with Transmission Owners, to direct data center and large-load customer-owned backup generation facilities to operate during emergency conditions as a last resort before firm load interruption. PJM issued a letter to members, state regulators, and large-load customers on January 29, 2026, and simultaneously released an addendum to Manual 13 ('Behind the Meter Emergency Procedure'). PJM stated it expected to operate reliably without activating the procedure but wanted all tools available. Transmission Owners (not PJM directly) are the primary operational contact for affected customers.
Energy Secretary Chris Wright issued DOE Order No. 202-26-01 on January 24, 2026, invoking FPA Section 202(c) emergency authority in response to ERCOT's request the same day. The order declared a statutory emergency in the ERCOT region due to sudden demand increase, generation shortage, and extreme cold from Winter Storm Fern. The order authorized ERCOT (as Reliability Coordinator) and its Balancing Authorities to direct backup generation resources — including auxiliary, standby, directly-connected, and battery storage resources — at data centers (including hyperscaler facilities) and other large load sites to operate as a last resort before or during an EEA 3. An amended order followed January 25. The order expired January 27, 2026. A companion order for PJM was issued January 26. DOE has since issued 43+ Section 202(c) orders since May 2025, including to stall retirement of 4.4+ GW of coal capacity across multiple regions.
FERC unanimously approved SPP's High Impact Large Load Study Process (HILL) and High Impact Large Load Generation Assessment (HILLGA) in January 2026. CHILLS (Conditional High Impact Large Loads Service) was refiled Feb 10, 2026, requesting FERC action by mid-April with July 1 effective date; approval expected. CHILLS provides non-firm, 'as available' energy/transmission as a bridge to long-term service for HILLs (≥10 MW at ≤69 kV or >50 MW at >69 kV). SPP's framework is the most complete large-load-specific interconnection structure among US RTOs.
State / federal pushback this period
Executive order (not legislation) signed Sept. 18, 2026 at the Virginia State Capitol, effective upon signing, issued under Art. V of the Virginia Constitution and Va. Code §§ 2.2-103 and 2.2-110. Operative today: VEDP barred from providing Virginia Business Ready Sites Program assistance, expedited permitting or any similar discretionary state economic development, site-readiness or expedited-review support to any new data center project with anticipated peak demand of 25 MW or greater; executive-branch NDA ban on proposed commercial data center developments; Eastern Virginia Groundwater Management Area designated a cooling water scarcity area. Agency deadlines: DEQ noise-rulemaking acceleration plan and backup-generation cumulative-impact findings at 180 days; Chief Energy Officer community-engagement toolkit at 120 days; Virginia Energy siting recommendations at 240 days; VA-LEAD tiered designation criteria by end of CY2027. Cost-allocation directives target PJM Reliability Backstop Procurement and IRAS, plus SCC work on emergency curtailment of data centers that have not brought their own IRAS capacity (contingent on FERC approval). Rescinds Youngkin EO 30 and Executive Directive 5. The Data Center Accountability Framework's most restrictive elements — eliminating by-right local approval above 25 MW, a local-government NDA ban, and behind-the-meter gas limits — require General Assembly action in the session beginning January 2027 and are not in effect. No statewide moratorium.
Austin City Council approved a resolution on Aug. 27, 2026 initiating Land Development Code amendments to define data centers and set standards for location, size, water, noise, heat, lighting and site design, expressly contemplating a ban on hyperscale facilities. This is an initiating resolution rather than an enacted ban or moratorium; Texas law requires the prohibition to be adopted through the zoning process. Staff will bring phased proposed rules back to Council, targeting a first round by end of 2026, with the broader process potentially extending into spring 2027. In the interim, staff stated that large-scale data center projects proposed within city limits require Council approval. Austin's existing code accommodates facilities up to roughly 20 MW and has no rules above 75 MW; there are 10 smaller data centers in the city and no confirmed hyperscale applications. CM Vanessa Fuentes and at least four other members (Ryan Alter, Mike Siegel, Jose Velasquez, Krista Laine) support a complete hyperscale ban.
Two state-level data center moratorium bills failed to advance when the Minnesota Legislature adjourned May 18, 2026 without a hearing. Local Minneapolis action proceeded independently.
Gov. Janet Mills vetoed LD 307 (would have been the first statewide US data center moratorium). House 72-65, Senate 20-11 — both short of the 2/3 needed to override. Mills did sign LD 713 (excludes data centers from Maine's business development tax incentives) and is creating an executive-order study council.
Allows local governments to regulate or ban data centers rather than implementing a statewide prohibition. Practical effect: county-by-county zoning fights now the contested ground.
Camden County, GA adopted a 9-month moratorium on May 5, 2026 — local-action precedent in a state where HB 1012 statewide moratorium was previously filed.
Second reading + public hearing May 18, with a May 21 effective date if approved.
Council Members Aurin Chowdhury and Jason Chavez introduced a proposal creating Chapter 597 in Title 21 of the Minneapolis Code — a citywide pause on data center uses while the city studies water, electricity, noise, and neighborhood impacts. If May 21 vote advances, proposal moves to full council in June, then to Mayor Jacob Frey for sign/veto. Council split along the usual political divide.
Both the Parks & City Light Committee and the Land Use & Sustainability Committee meet May 20, 2026; either may introduce the 365-day emergency moratorium. Pairs with utility-rate proposals and a resolution calling for impact studies on infrastructure, water use, utility rates, jobs, and public health. Two of five proposed data center projects (combined 369 MW max demand) have already withdrawn applications amid the political opposition.
119th Congress; introduced in the Senate. Would impose a federal moratorium on certain large AI data centers absent specified energy and environmental conditions. Long shot but signals the political ceiling.
Virginia legislature considered 61 data center bills in 2026 — 15 sent to the Governor's desk, 46 carry over to 2027. HB 1515 (statewide moratorium) effectively killed for the 2026 session. Most consequential signed package: cost-shift legislation requiring data centers ≥25 MW to pay for incremental generating capacity and creating voluntary demand-flexibility programs. The $1.6B/year data center tax exemption remains unresolved — Senate wants to eliminate it; House wants to tie it to environmental compliance.
Georgia House Bill 1059 (Data Center Impact Assessment and Development Moratorium Act of 2026) and HB 1012 were introduced but Georgia lawmakers never seriously considered calls for a moratorium. Legislature ended session without action despite significant community opposition. HB 1059 would have established a moratorium from July 1, 2026 to Dec 31, 2028 with a 14-member Data Center Impact Commission. SB 436 (suspend new sales tax exemptions) and SB 421 (Data Center Transparency Act — prohibit NDA on water/power usage) also failed to advance.
Oklahoma Senate Bill 1488 proposes a moratorium on new data center buildings until November 2029. Part of the broader wave of 78 active state/local moratorium efforts (up from 8 in May 2025).
New York State S9144 proposes a three-year statewide moratorium on new data centers to establish strict guidelines for utility rates and data center impacts. Follows Maine's failed moratorium attempt.
Rep. Nancy Mace (R-SC) called for a one-year moratorium on new data centers in South Carolina, freezing permits until a comprehensive oversight framework is adopted. Federal-level call mirrors state-level actions.
Pennsylvania House passed data center regulation bills in May 2026, but they stalled in the Senate. PA PUC's Model Tariff Framework (final order May 13) remains the primary regulatory action. Combined with the House-passed bills, Pennsylvania is among the most active state regulatory environments for data centers.
Governor's amendments to HB 1393 / SB 253 (signed April 22, 2026) will save residential customers money by shifting generation capacity costs to data centers and other large-load customers (≥25 MW demand). SCC gains authority to determine cost allocation through 2033. HB 507 requires Tier IV generators for all new data center air permits after July 2026. Data center tax exemption ($1.6B/year) fight continues — Senate wants to eliminate it; House wants to tie it to environmental compliance.
Source links
- Commonwealth of Virginia — Executive Order 22 (2026), Virginia Data Center Accountability Framework and AI initiatives (Sept. 18, 2026)
- Virginia Mercury — Spanberger presents slate of data center regulation proposals, puts first directives in motion (Sept. 18, 2026)
- KUT News — Austin begins writing new rules to manage, potentially ban large-scale data centers (Aug. 27, 2026)
- MultiState — May 2026 ballot measure trends
- ITBrew — Maine moratorium veto aftermath
- Capitol Hill Seattle — Seattle moratorium plan
- Carrier Mgmt — dozen states considering bans
- Congress.gov S.4214 text
ISO regulatory updates — ERCOT · MISO · PJM · SPP
Revision requests filed Mar 4, 2026 initiated formal NPRR/PGRR governance for the Batch Zero framework. April 9 workshop clarified the Provisional Controllable Load Resource (PCLR) pathway: projects facing transmission constraints in early study years can access higher demand levels while planned upgrades complete.
After 2026, only Large Loads that have executed an interconnection agreement satisfying PUC Project 58481 requirements will be included in the ERCOT Large Load forecast. Material consequence: speculative load gets removed from official load growth projections, sharpening the case for distressed-queue repurposing.
Starting March 2026, ERCOT's monthly GIS (formerly GINR) report file series includes a Transmission Interconnection Costs Report — first standardized public view of network upgrade exposure by project. Solar + ES = ~76% of generation queue. Gas project capacity +271% since 2023 (Texas Energy Fund).
PCLR pathway provides a near-term alternative to firm interconnection: conditional service with planned-upgrade trigger to firm. Useful for hyperscaler co-location plays where some interruptibility is acceptable in exchange for speed-to-energy.
New $150K study deposit + D1 application fee for Surplus Interconnection Service and Replacement Requests. First MISO update on GIP since DPP-2024 was finalized — pricing signal for SIS/replacement positioning.
Applicability: after Sep 1, 2026 any load >50 MW at a single site behind one or more transmission POIs. Existing >50 MW loads adding +25 MW also caught. Drives early planning for hyperscale builds in MISO South.
MISO continues to advance LMR/DRR reforms (RASC-2019-9). Real-time visibility and procurement of Load Modifying Resources tightening — relevant for any flexible-load thesis.
C&M threshold moved to summer 2027 (≥50 MW loads not online by June 1, 2027 subject to C&M unless they bring new gen). C&M only triggers on actual capacity shortfall and only for the shortage quantity. PJM files with FERC by July 10. Backstop bids solicited Sept 10–Oct 9; results by Nov 20. July 14: 2028/29 RPM results determine shortfall. IPPs call C&M 'illegal'; DCC will not oppose backstop. Bilateral contracting on hold until C&M finalized (~4Q 2026). Next contracting wave: 2027 with energy + storage. LCEP (Load-Contingent New Capacity at Existing Plants) proposed in RM26-4 — advantage to incumbent IPPs with existing interconnection rights.
Dec 18, 2025 final order. Three new transmission service types directed: Interim non-firm, Firm Contract Demand, and Non-firm Contract Demand. Compliance filings due Jan 20 and Feb 16, 2026. Docket EL25-49-000 reply round closed Apr 17. This is the single highest-impact regulatory event for distressed queue repurposing — co-located behind-the-meter pathways now have an enforced compliance roadmap.
Jan 20 compliance filing required PJM to describe how co-located customers can access provisional interconnection, request service below nameplate capacity, and accelerate the interconnection process. Material for AEP / Dominion / Exelon zones with constrained transmission and queue depth.
Co-located load order interlocks with capacity market design — capacity prices and the capacity-accreditation regime materially impact economics of partial-firm / interruptible service tiers. Watch for follow-on filings.
FERC approved SPP's High Impact Large Load (HILL) Study Process and High Impact Large Load Generation Assessment (HILLGA). Streamlined competitive solution for commercial/industrial growth — including hyperscaler load.
Conditional High Impact Large Load Service. 90-day study, up to 5 years interruptible transmission service in exchange for curtailment rights. Allows provisional / HILLGA generation as supporting resources, enables delivery point establishment, grants conditional service ahead of sufficient DNRs or firm transmission.
December 2025 SUF (Study Underway Funnel) updates and Joint ESWG-TWG meeting Nov 2025 set up the 2026 cluster timing; HILL companion studies open paired-resource pathways for hybrid solar+storage paired to large load.
State & federal pushback — moratoria, zoning, ratepayer protection
Bars counties and cities from issuing any permit, license, or certificate authorizing new data center construction until March 1, 2027 (exception for approvals issued before July 1, 2026).
Prohibits construction of new data centers — and any state/local approvals — unless and until the General Assembly enacts specified legislation related to co-location with new or existing power generation.
Pause construction while studying impacts on utilities, environment, and local communities.
Pause-and-study moratorium on new data center construction.
Pause-and-study moratorium on new data center construction.
Most active state on tariff side — 7 DELTa tariffs tracked, including Dominion large-load rates. Watch local zoning pushback in Loudoun and Prince William.
Trackers & data sources
- datacentertracker.org — interactive map
- datacentertracker.org — legislation tracker
- Good Jobs First — moratorium bills 2026
- MultiState — state data center policy 101
- MultiState — Apr 2026 federal-vs-state tracker
- datacenterbans.com — AI legislation tracker
- ArentFox Schiff — state regulation 2026
Note: datacentertracker.org renders its map and table client-side; the in-page narrative above is curated. Open the tracker directly for the live interactive map and CSV download.
DELTa — Database of Emerging Large-Load Tariffs — SEPA / NCCETC, official data as of 2026-03 March · 27 Edged supplemental records
| State | Utility | Tariff | Status | Yr | ISO | Min MW | Term | Narrative | Links |
|---|